McAfee-Secured Website

Exam Bundle

Exam Code: PK0-005

Exam Name CompTIA Project+

Certification Provider: CompTIA

Corresponding Certification: CompTIA Project+

CompTIA PK0-005 Bundle $44.99

100% CompTIA PK0-005 Guaranteed Success With Testking Training Materials

Get Real PK0-005 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    PK0-005 Questions & Answers

    628 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual PK0-005 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • PK0-005 Video Course

    PK0-005 Video Course

    159 Video Lectures

    PK0-005 Video Course is developed by CompTIA Professionals to help you pass the PK0-005 exam.

    Description

    This course will improve your knowledge and skills required to pass CompTIA Project+ exam.
  • Study Guide

    PK0-005 Study Guide

    682 PDF Pages

    Developed by industry experts, this 682-page guide spells out in painstaking detail all of the information you need to ace PK0-005 exam.

CompTIA Project+ (PK0-005) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    628 Questions

    $124.99
  • PK0-005 Video Course

    Video Course

    159 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    682 PDF Pages

    $29.99

CompTIA PK0-005 Practice Test 75

Question 740

For Blue Haven Media, the project steering committee reports the following delivery problem: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The resource allocation report shows project capacity returned to owning teams.
  2. The final acceptance record identifies the approved deliverables and accepting authority.
  3. The contract file shows agreed closure or transfer and settled obligations.
  4. Finance confirms final project expenditure and settled or identified outstanding liabilities.

Explanation

Correct Answer

C:

The contract file shows agreed closure or transfer and settled obligations. This is the relevant acceptance evidence because it tests whether the corrective action (Close or transition vendor agreements under the contract's applicable conditions.) fixed the original concern (A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met.) at Blue Haven Media, rather than relying only on a task marked complete. The affected work concerns creative files and production workspaces.

Incorrect Answers

A:

The resource allocation report shows project capacity returned to owning teams. This evidence would be useful for another condition (Project staff remain assigned full-time after sign-off and other workstreams cannot use them.) and its different action (Release or reassign resources through the approved closure process.). At Blue Haven Media, it does not demonstrate the required project outcome: The contract file shows agreed closure or transfer and settled obligations.

B:

The final acceptance record identifies the approved deliverables and accepting authority. This evidence would be useful for another condition (A software implementation has reached technical completion but the customer has not validated contracted outputs.) and its different action (Verify deliverables against acceptance criteria and obtain formal project sign-off.). At Blue Haven Media, it does not demonstrate the required project outcome: The contract file shows agreed closure or transfer and settled obligations.

D:

Finance confirms final project expenditure and settled or identified outstanding liabilities. This evidence would be useful for another condition (A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown.) and its different action (Reconcile final costs committed invoices and contract obligations before financial closure.). At Blue Haven Media, it does not demonstrate the required project outcome: The contract file shows agreed closure or transfer and settled obligations.

Question 741

At Aspen Digital, the delivery assessment finds: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. Which project management action BEST addresses the particular issue?

  1. Verify deliverables against acceptance criteria and obtain formal project sign-off.
  2. Close or transition vendor agreements under the contract's applicable conditions.
  3. Release or reassign resources through the approved closure process.
  4. Reconcile final costs committed invoices and contract obligations before financial closure.

Explanation

Correct Answer

B:

Close or transition vendor agreements under the contract's applicable conditions. This directly addresses the reported management gap: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. For Aspen Digital and its client advisory systems and shared files, a useful verification outcome is: The contract file shows agreed closure or transfer and settled obligations.

Incorrect Answers

A:

Verify deliverables against acceptance criteria and obtain formal project sign-off. This choice addresses another specific project condition: A software implementation has reached technical completion but the customer has not validated contracted outputs. The actual issue at Aspen Digital is: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. That other intervention does not itself establish the required result: The contract file shows agreed closure or transfer and settled obligations.

C:

Release or reassign resources through the approved closure process. This choice addresses another specific project condition: Project staff remain assigned full-time after sign-off and other workstreams cannot use them. The actual issue at Aspen Digital is: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. That other intervention does not itself establish the required result: The contract file shows agreed closure or transfer and settled obligations.

D:

Reconcile final costs committed invoices and contract obligations before financial closure. This choice addresses another specific project condition: A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown. The actual issue at Aspen Digital is: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. That other intervention does not itself establish the required result: The contract file shows agreed closure or transfer and settled obligations.

Question 742

At Aspen Digital, the delivery assessment finds: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The resource allocation report shows project capacity returned to owning teams.
  2. Finance confirms final project expenditure and settled or identified outstanding liabilities.
  3. The contract file shows agreed closure or transfer and settled obligations.
  4. The final acceptance record identifies the approved deliverables and accepting authority.

Explanation

Correct Answer

C:

The contract file shows agreed closure or transfer and settled obligations. This is the relevant acceptance evidence because it tests whether the corrective action (Close or transition vendor agreements under the contract's applicable conditions.) fixed the original concern (A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met.) at Aspen Digital, rather than relying only on a task marked complete. The affected work concerns client advisory systems and shared files.

Incorrect Answers

A:

The resource allocation report shows project capacity returned to owning teams. This evidence would be useful for another condition (Project staff remain assigned full-time after sign-off and other workstreams cannot use them.) and its different action (Release or reassign resources through the approved closure process.). At Aspen Digital, it does not demonstrate the required project outcome: The contract file shows agreed closure or transfer and settled obligations.

B:

Finance confirms final project expenditure and settled or identified outstanding liabilities. This evidence would be useful for another condition (A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown.) and its different action (Reconcile final costs committed invoices and contract obligations before financial closure.). At Aspen Digital, it does not demonstrate the required project outcome: The contract file shows agreed closure or transfer and settled obligations.

D:

The final acceptance record identifies the approved deliverables and accepting authority. This evidence would be useful for another condition (A software implementation has reached technical completion but the customer has not validated contracted outputs.) and its different action (Verify deliverables against acceptance criteria and obtain formal project sign-off.). At Aspen Digital, it does not demonstrate the required project outcome: The contract file shows agreed closure or transfer and settled obligations.

Question 743

Marshfield Bank is delivering an IT initiative involving payments and confidential client information subject to a limited implementation budget. The team observes: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. Which project management action BEST addresses the particular issue?

  1. Verify deliverables against acceptance criteria and obtain formal project sign-off.
  2. Reconcile final costs committed invoices and contract obligations before financial closure.
  3. Release or reassign resources through the approved closure process.
  4. Close or transition vendor agreements under the contract's applicable conditions.

Explanation

Correct Answer

D:

Close or transition vendor agreements under the contract's applicable conditions. This directly addresses the reported management gap: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. For Marshfield Bank and its payments and confidential client information, a useful verification outcome is: The contract file shows agreed closure or transfer and settled obligations.

Incorrect Answers

A:

Verify deliverables against acceptance criteria and obtain formal project sign-off. This choice addresses another specific project condition: A software implementation has reached technical completion but the customer has not validated contracted outputs. The actual issue at Marshfield Bank is: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. That other intervention does not itself establish the required result: The contract file shows agreed closure or transfer and settled obligations.

B:

Reconcile final costs committed invoices and contract obligations before financial closure. This choice addresses another specific project condition: A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown. The actual issue at Marshfield Bank is: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. That other intervention does not itself establish the required result: The contract file shows agreed closure or transfer and settled obligations.

C:

Release or reassign resources through the approved closure process. This choice addresses another specific project condition: Project staff remain assigned full-time after sign-off and other workstreams cannot use them. The actual issue at Marshfield Bank is: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. That other intervention does not itself establish the required result: The contract file shows agreed closure or transfer and settled obligations.

Question 744

Marshfield Bank is delivering an IT initiative involving payments and confidential client information subject to a limited implementation budget. The team observes: A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The final acceptance record identifies the approved deliverables and accepting authority.
  2. Finance confirms final project expenditure and settled or identified outstanding liabilities.
  3. The resource allocation report shows project capacity returned to owning teams.
  4. The contract file shows agreed closure or transfer and settled obligations.

Explanation

Correct Answer

D:

The contract file shows agreed closure or transfer and settled obligations. This is the relevant acceptance evidence because it tests whether the corrective action (Close or transition vendor agreements under the contract's applicable conditions.) fixed the original concern (A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met.) at Marshfield Bank, rather than relying only on a task marked complete. The affected work concerns payments and confidential client information.

Incorrect Answers

A:

The final acceptance record identifies the approved deliverables and accepting authority. This evidence would be useful for another condition (A software implementation has reached technical completion but the customer has not validated contracted outputs.) and its different action (Verify deliverables against acceptance criteria and obtain formal project sign-off.). At Marshfield Bank, it does not demonstrate the required project outcome: The contract file shows agreed closure or transfer and settled obligations.

B:

Finance confirms final project expenditure and settled or identified outstanding liabilities. This evidence would be useful for another condition (A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown.) and its different action (Reconcile final costs committed invoices and contract obligations before financial closure.). At Marshfield Bank, it does not demonstrate the required project outcome: The contract file shows agreed closure or transfer and settled obligations.

C:

The resource allocation report shows project capacity returned to owning teams. This evidence would be useful for another condition (Project staff remain assigned full-time after sign-off and other workstreams cannot use them.) and its different action (Release or reassign resources through the approved closure process.). At Marshfield Bank, it does not demonstrate the required project outcome: The contract file shows agreed closure or transfer and settled obligations.

Question 745

Ridgeview Finance is delivering an IT initiative involving financial reporting and customer portals in a mixed Agile and predictive delivery environment. The team observes: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. Which project management action BEST addresses the particular issue?

  1. Reconcile final costs committed invoices and contract obligations before financial closure.
  2. Archive controlled plans decisions runbooks and acceptance evidence in the designated repository.
  3. Evaluate actual outcomes against the original business case and success criteria.
  4. Collect team and stakeholder feedback and publish lessons learned for future initiatives.

Explanation

Correct Answer

D:

Collect team and stakeholder feedback and publish lessons learned for future initiatives. This directly addresses the reported management gap: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. For Ridgeview Finance and its financial reporting and customer portals, a useful verification outcome is: The closeout report includes actionable improvements with identifiable follow-up ownership.

Incorrect Answers

A:

Reconcile final costs committed invoices and contract obligations before financial closure. This choice addresses another specific project condition: A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown. The actual issue at Ridgeview Finance is: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. That other intervention does not itself establish the required result: The closeout report includes actionable improvements with identifiable follow-up ownership.

B:

Archive controlled plans decisions runbooks and acceptance evidence in the designated repository. This choice addresses another specific project condition: Operations cannot support a delivered service because project documentation is scattered across personal laptops. The actual issue at Ridgeview Finance is: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. That other intervention does not itself establish the required result: The closeout report includes actionable improvements with identifiable follow-up ownership.

C:

Evaluate actual outcomes against the original business case and success criteria. This choice addresses another specific project condition: A completion report celebrates release day but omits whether planned benefits and final product performance met the charter objectives. The actual issue at Ridgeview Finance is: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. That other intervention does not itself establish the required result: The closeout report includes actionable improvements with identifiable follow-up ownership.

Question 746

Ridgeview Finance is delivering an IT initiative involving financial reporting and customer portals in a mixed Agile and predictive delivery environment. The team observes: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The closeout report includes actionable improvements with identifiable follow-up ownership.
  2. Operations retrieves the approved final documents and their version history.
  3. Finance confirms final project expenditure and settled or identified outstanding liabilities.
  4. The final report identifies achieved benefits residual gaps and any post-project measurement owner.

Explanation

Correct Answer

A:

The closeout report includes actionable improvements with identifiable follow-up ownership. This is the relevant acceptance evidence because it tests whether the corrective action (Collect team and stakeholder feedback and publish lessons learned for future initiatives.) fixed the original concern (A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons.) at Ridgeview Finance, rather than relying only on a task marked complete. The affected work concerns financial reporting and customer portals.

Incorrect Answers

B:

Operations retrieves the approved final documents and their version history. This evidence would be useful for another condition (Operations cannot support a delivered service because project documentation is scattered across personal laptops.) and its different action (Archive controlled plans decisions runbooks and acceptance evidence in the designated repository.). At Ridgeview Finance, it does not demonstrate the required project outcome: The closeout report includes actionable improvements with identifiable follow-up ownership.

C:

Finance confirms final project expenditure and settled or identified outstanding liabilities. This evidence would be useful for another condition (A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown.) and its different action (Reconcile final costs committed invoices and contract obligations before financial closure.). At Ridgeview Finance, it does not demonstrate the required project outcome: The closeout report includes actionable improvements with identifiable follow-up ownership.

D:

The final report identifies achieved benefits residual gaps and any post-project measurement owner. This evidence would be useful for another condition (A completion report celebrates release day but omits whether planned benefits and final product performance met the charter objectives.) and its different action (Evaluate actual outcomes against the original business case and success criteria.). At Ridgeview Finance, it does not demonstrate the required project outcome: The closeout report includes actionable improvements with identifiable follow-up ownership.

Question 747

For Northshore Hospitality, the delivery lead reports the following delivery problem: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. Which project management action BEST addresses the particular issue?

  1. Collect team and stakeholder feedback and publish lessons learned for future initiatives.
  2. Reconcile final costs committed invoices and contract obligations before financial closure.
  3. Archive controlled plans decisions runbooks and acceptance evidence in the designated repository.
  4. Evaluate actual outcomes against the original business case and success criteria.

Explanation

Correct Answer

A:

Collect team and stakeholder feedback and publish lessons learned for future initiatives. This directly addresses the reported management gap: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. For Northshore Hospitality and its reservation applications and staff devices, a useful verification outcome is: The closeout report includes actionable improvements with identifiable follow-up ownership.

Incorrect Answers

B:

Reconcile final costs committed invoices and contract obligations before financial closure. This choice addresses another specific project condition: A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown. The actual issue at Northshore Hospitality is: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. That other intervention does not itself establish the required result: The closeout report includes actionable improvements with identifiable follow-up ownership.

C:

Archive controlled plans decisions runbooks and acceptance evidence in the designated repository. This choice addresses another specific project condition: Operations cannot support a delivered service because project documentation is scattered across personal laptops. The actual issue at Northshore Hospitality is: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. That other intervention does not itself establish the required result: The closeout report includes actionable improvements with identifiable follow-up ownership.

D:

Evaluate actual outcomes against the original business case and success criteria. This choice addresses another specific project condition: A completion report celebrates release day but omits whether planned benefits and final product performance met the charter objectives. The actual issue at Northshore Hospitality is: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. That other intervention does not itself establish the required result: The closeout report includes actionable improvements with identifiable follow-up ownership.

Question 748

For Northshore Hospitality, the delivery lead reports the following delivery problem: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The final report identifies achieved benefits residual gaps and any post-project measurement owner.
  2. Finance confirms final project expenditure and settled or identified outstanding liabilities.
  3. The closeout report includes actionable improvements with identifiable follow-up ownership.
  4. Operations retrieves the approved final documents and their version history.

Explanation

Correct Answer

C:

The closeout report includes actionable improvements with identifiable follow-up ownership. This is the relevant acceptance evidence because it tests whether the corrective action (Collect team and stakeholder feedback and publish lessons learned for future initiatives.) fixed the original concern (A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons.) at Northshore Hospitality, rather than relying only on a task marked complete. The affected work concerns reservation applications and staff devices.

Incorrect Answers

A:

The final report identifies achieved benefits residual gaps and any post-project measurement owner. This evidence would be useful for another condition (A completion report celebrates release day but omits whether planned benefits and final product performance met the charter objectives.) and its different action (Evaluate actual outcomes against the original business case and success criteria.). At Northshore Hospitality, it does not demonstrate the required project outcome: The closeout report includes actionable improvements with identifiable follow-up ownership.

B:

Finance confirms final project expenditure and settled or identified outstanding liabilities. This evidence would be useful for another condition (A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown.) and its different action (Reconcile final costs committed invoices and contract obligations before financial closure.). At Northshore Hospitality, it does not demonstrate the required project outcome: The closeout report includes actionable improvements with identifiable follow-up ownership.

D:

Operations retrieves the approved final documents and their version history. This evidence would be useful for another condition (Operations cannot support a delivered service because project documentation is scattered across personal laptops.) and its different action (Archive controlled plans decisions runbooks and acceptance evidence in the designated repository.). At Northshore Hospitality, it does not demonstrate the required project outcome: The closeout report includes actionable improvements with identifiable follow-up ownership.

Question 749

At Evergreen Hospital, the delivery assessment finds: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. Which project management action BEST addresses the particular issue?

  1. Collect team and stakeholder feedback and publish lessons learned for future initiatives.
  2. Reconcile final costs committed invoices and contract obligations before financial closure.
  3. Evaluate actual outcomes against the original business case and success criteria.
  4. Archive controlled plans decisions runbooks and acceptance evidence in the designated repository.

Explanation

Correct Answer

A:

Collect team and stakeholder feedback and publish lessons learned for future initiatives. This directly addresses the reported management gap: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. For Evergreen Hospital and its care coordination and staff identity services, a useful verification outcome is: The closeout report includes actionable improvements with identifiable follow-up ownership.

Incorrect Answers

B:

Reconcile final costs committed invoices and contract obligations before financial closure. This choice addresses another specific project condition: A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown. The actual issue at Evergreen Hospital is: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. That other intervention does not itself establish the required result: The closeout report includes actionable improvements with identifiable follow-up ownership.

C:

Evaluate actual outcomes against the original business case and success criteria. This choice addresses another specific project condition: A completion report celebrates release day but omits whether planned benefits and final product performance met the charter objectives. The actual issue at Evergreen Hospital is: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. That other intervention does not itself establish the required result: The closeout report includes actionable improvements with identifiable follow-up ownership.

D:

Archive controlled plans decisions runbooks and acceptance evidence in the designated repository. This choice addresses another specific project condition: Operations cannot support a delivered service because project documentation is scattered across personal laptops. The actual issue at Evergreen Hospital is: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. That other intervention does not itself establish the required result: The closeout report includes actionable improvements with identifiable follow-up ownership.

Question 750

At Evergreen Hospital, the delivery assessment finds: A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The final report identifies achieved benefits residual gaps and any post-project measurement owner.
  2. Finance confirms final project expenditure and settled or identified outstanding liabilities.
  3. Operations retrieves the approved final documents and their version history.
  4. The closeout report includes actionable improvements with identifiable follow-up ownership.

Explanation

Correct Answer

D:

The closeout report includes actionable improvements with identifiable follow-up ownership. This is the relevant acceptance evidence because it tests whether the corrective action (Collect team and stakeholder feedback and publish lessons learned for future initiatives.) fixed the original concern (A final launch retrospective is skipped because senior leaders believe only failed projects produce lessons.) at Evergreen Hospital, rather than relying only on a task marked complete. The affected work concerns care coordination and staff identity services.

Incorrect Answers

A:

The final report identifies achieved benefits residual gaps and any post-project measurement owner. This evidence would be useful for another condition (A completion report celebrates release day but omits whether planned benefits and final product performance met the charter objectives.) and its different action (Evaluate actual outcomes against the original business case and success criteria.). At Evergreen Hospital, it does not demonstrate the required project outcome: The closeout report includes actionable improvements with identifiable follow-up ownership.

B:

Finance confirms final project expenditure and settled or identified outstanding liabilities. This evidence would be useful for another condition (A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown.) and its different action (Reconcile final costs committed invoices and contract obligations before financial closure.). At Evergreen Hospital, it does not demonstrate the required project outcome: The closeout report includes actionable improvements with identifiable follow-up ownership.

C:

Operations retrieves the approved final documents and their version history. This evidence would be useful for another condition (Operations cannot support a delivered service because project documentation is scattered across personal laptops.) and its different action (Archive controlled plans decisions runbooks and acceptance evidence in the designated repository.). At Evergreen Hospital, it does not demonstrate the required project outcome: The closeout report includes actionable improvements with identifiable follow-up ownership.