Question 730
For Evermere Health, the project governance analyst reports the following delivery problem: Project staff remain assigned full-time after sign-off and other workstreams cannot use them. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The resource allocation report shows project capacity returned to owning teams. This is the relevant acceptance evidence because it tests whether the corrective action (Release or reassign resources through the approved closure process.) fixed the original concern (Project staff remain assigned full-time after sign-off and other workstreams cannot use them.) at Evermere Health, rather than relying only on a task marked complete. The affected work concerns care team access and regulated data handling.
Incorrect Answers
The final acceptance record identifies the approved deliverables and accepting authority. This evidence would be useful for another condition (A software implementation has reached technical completion but the customer has not validated contracted outputs.) and its different action (Verify deliverables against acceptance criteria and obtain formal project sign-off.). At Evermere Health, it does not demonstrate the required project outcome: The resource allocation report shows project capacity returned to owning teams.
The contract file shows agreed closure or transfer and settled obligations. This evidence would be useful for another condition (A vendor maintenance contract is left open after project closure although the deliverable was accepted and termination conditions were met.) and its different action (Close or transition vendor agreements under the contract's applicable conditions.). At Evermere Health, it does not demonstrate the required project outcome: The resource allocation report shows project capacity returned to owning teams.
Finance confirms final project expenditure and settled or identified outstanding liabilities. This evidence would be useful for another condition (A project closes financial tracking when work ends though supplier invoices remain outstanding and contract balances are unknown.) and its different action (Reconcile final costs committed invoices and contract obligations before financial closure.). At Evermere Health, it does not demonstrate the required project outcome: The resource allocation report shows project capacity returned to owning teams.