McAfee-Secured Website

Exam Bundle

Exam Code: PK0-005

Exam Name CompTIA Project+

Certification Provider: CompTIA

Corresponding Certification: CompTIA Project+

CompTIA PK0-005 Bundle $44.99

100% CompTIA PK0-005 Guaranteed Success With Testking Training Materials

Get Real PK0-005 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    PK0-005 Questions & Answers

    628 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual PK0-005 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • PK0-005 Video Course

    PK0-005 Video Course

    159 Video Lectures

    PK0-005 Video Course is developed by CompTIA Professionals to help you pass the PK0-005 exam.

    Description

    This course will improve your knowledge and skills required to pass CompTIA Project+ exam.
  • Study Guide

    PK0-005 Study Guide

    682 PDF Pages

    Developed by industry experts, this 682-page guide spells out in painstaking detail all of the information you need to ace PK0-005 exam.

CompTIA Project+ (PK0-005) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    628 Questions

    $124.99
  • PK0-005 Video Course

    Video Course

    159 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    682 PDF Pages

    $29.99

CompTIA PK0-005 Practice Test 23

Question 220

At Silver Cove Payments, the delivery assessment finds: A team treats a zero-duration launch gate as a week-long task and misstates the project completion date. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The schedule marks a dated zero-duration decision gate after required tasks finish.
  2. The schedule will not start integration testing before the required build output is available.
  3. The forecast identifies which dependent activities and completion date are impacted by the delay.
  4. The resource loading report no longer shows impossible concurrent allocations for that engineer.

Explanation

Correct Answer

A:

The schedule marks a dated zero-duration decision gate after required tasks finish. This is the relevant acceptance evidence because it tests whether the corrective action (Represent the launch approval as a milestone with properly linked predecessor activities.) fixed the original concern (A team treats a zero-duration launch gate as a week-long task and misstates the project completion date.) at Silver Cove Payments, rather than relying only on a task marked complete. The affected work concerns transaction data and fraud monitoring.

Incorrect Answers

B:

The schedule will not start integration testing before the required build output is available. This evidence would be useful for another condition (A plan places integration testing before the dependent build is finished and reports no schedule conflict.) and its different action (Define the correct finish-to-start dependency between build completion and integration testing.). At Silver Cove Payments, it does not demonstrate the required project outcome: The schedule marks a dated zero-duration decision gate after required tasks finish.

C:

The forecast identifies which dependent activities and completion date are impacted by the delay. This evidence would be useful for another condition (A schedule lists ten activities but contains no predecessor logic so a one-week delay has no visible downstream impact.) and its different action (Construct a dependency network and calculate the critical path for baseline monitoring.). At Silver Cove Payments, it does not demonstrate the required project outcome: The schedule marks a dated zero-duration decision gate after required tasks finish.

D:

The resource loading report no longer shows impossible concurrent allocations for that engineer. This evidence would be useful for another condition (Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged.) and its different action (Level or reassign overallocated resource tasks and document the resulting schedule impacts.). At Silver Cove Payments, it does not demonstrate the required project outcome: The schedule marks a dated zero-duration decision gate after required tasks finish.

Question 221

Northbridge University is delivering an IT initiative involving student collaboration and research access under controlled release and records requirements. The team observes: A team treats a zero-duration launch gate as a week-long task and misstates the project completion date. Which project management action BEST addresses the particular issue?

  1. Level or reassign overallocated resource tasks and document the resulting schedule impacts.
  2. Define the correct finish-to-start dependency between build completion and integration testing.
  3. Construct a dependency network and calculate the critical path for baseline monitoring.
  4. Represent the launch approval as a milestone with properly linked predecessor activities.

Explanation

Correct Answer

D:

Represent the launch approval as a milestone with properly linked predecessor activities. This directly addresses the reported management gap: A team treats a zero-duration launch gate as a week-long task and misstates the project completion date. For Northbridge University and its student collaboration and research access, a useful verification outcome is: The schedule marks a dated zero-duration decision gate after required tasks finish.

Incorrect Answers

A:

Level or reassign overallocated resource tasks and document the resulting schedule impacts. This choice addresses another specific project condition: Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged. The actual issue at Northbridge University is: A team treats a zero-duration launch gate as a week-long task and misstates the project completion date. That other intervention does not itself establish the required result: The schedule marks a dated zero-duration decision gate after required tasks finish.

B:

Define the correct finish-to-start dependency between build completion and integration testing. This choice addresses another specific project condition: A plan places integration testing before the dependent build is finished and reports no schedule conflict. The actual issue at Northbridge University is: A team treats a zero-duration launch gate as a week-long task and misstates the project completion date. That other intervention does not itself establish the required result: The schedule marks a dated zero-duration decision gate after required tasks finish.

C:

Construct a dependency network and calculate the critical path for baseline monitoring. This choice addresses another specific project condition: A schedule lists ten activities but contains no predecessor logic so a one-week delay has no visible downstream impact. The actual issue at Northbridge University is: A team treats a zero-duration launch gate as a week-long task and misstates the project completion date. That other intervention does not itself establish the required result: The schedule marks a dated zero-duration decision gate after required tasks finish.

Question 222

Northbridge University is delivering an IT initiative involving student collaboration and research access under controlled release and records requirements. The team observes: A team treats a zero-duration launch gate as a week-long task and misstates the project completion date. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The forecast identifies which dependent activities and completion date are impacted by the delay.
  2. The resource loading report no longer shows impossible concurrent allocations for that engineer.
  3. The schedule marks a dated zero-duration decision gate after required tasks finish.
  4. The schedule will not start integration testing before the required build output is available.

Explanation

Correct Answer

C:

The schedule marks a dated zero-duration decision gate after required tasks finish. This is the relevant acceptance evidence because it tests whether the corrective action (Represent the launch approval as a milestone with properly linked predecessor activities.) fixed the original concern (A team treats a zero-duration launch gate as a week-long task and misstates the project completion date.) at Northbridge University, rather than relying only on a task marked complete. The affected work concerns student collaboration and research access.

Incorrect Answers

A:

The forecast identifies which dependent activities and completion date are impacted by the delay. This evidence would be useful for another condition (A schedule lists ten activities but contains no predecessor logic so a one-week delay has no visible downstream impact.) and its different action (Construct a dependency network and calculate the critical path for baseline monitoring.). At Northbridge University, it does not demonstrate the required project outcome: The schedule marks a dated zero-duration decision gate after required tasks finish.

B:

The resource loading report no longer shows impossible concurrent allocations for that engineer. This evidence would be useful for another condition (Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged.) and its different action (Level or reassign overallocated resource tasks and document the resulting schedule impacts.). At Northbridge University, it does not demonstrate the required project outcome: The schedule marks a dated zero-duration decision gate after required tasks finish.

D:

The schedule will not start integration testing before the required build output is available. This evidence would be useful for another condition (A plan places integration testing before the dependent build is finished and reports no schedule conflict.) and its different action (Define the correct finish-to-start dependency between build completion and integration testing.). At Northbridge University, it does not demonstrate the required project outcome: The schedule marks a dated zero-duration decision gate after required tasks finish.

Question 223

Newbridge Charity is delivering an IT initiative involving donation workflows and volunteer accounts with multiple distributed delivery teams. The team observes: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. Which project management action BEST addresses the particular issue?

  1. Define the correct finish-to-start dependency between build completion and integration testing.
  2. Break the epic into smaller estimable stories and prioritize them for feasible sprint planning.
  3. Size and document an appropriate contingency reserve based on risk and supplier uncertainty.
  4. Construct a dependency network and calculate the critical path for baseline monitoring.

Explanation

Correct Answer

B:

Break the epic into smaller estimable stories and prioritize them for feasible sprint planning. This directly addresses the reported management gap: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. For Newbridge Charity and its donation workflows and volunteer accounts, a useful verification outcome is: Sprint commitments contain small independently testable stories with explicit capacity estimates.

Incorrect Answers

A:

Define the correct finish-to-start dependency between build completion and integration testing. This choice addresses another specific project condition: A plan places integration testing before the dependent build is finished and reports no schedule conflict. The actual issue at Newbridge Charity is: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. That other intervention does not itself establish the required result: Sprint commitments contain small independently testable stories with explicit capacity estimates.

C:

Size and document an appropriate contingency reserve based on risk and supplier uncertainty. This choice addresses another specific project condition: The plan has no schedule buffer for a supplier dependency known to have significant delivery variability. The actual issue at Newbridge Charity is: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. That other intervention does not itself establish the required result: Sprint commitments contain small independently testable stories with explicit capacity estimates.

D:

Construct a dependency network and calculate the critical path for baseline monitoring. This choice addresses another specific project condition: A schedule lists ten activities but contains no predecessor logic so a one-week delay has no visible downstream impact. The actual issue at Newbridge Charity is: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. That other intervention does not itself establish the required result: Sprint commitments contain small independently testable stories with explicit capacity estimates.

Question 224

Newbridge Charity is delivering an IT initiative involving donation workflows and volunteer accounts with multiple distributed delivery teams. The team observes: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The schedule will not start integration testing before the required build output is available.
  2. Sprint commitments contain small independently testable stories with explicit capacity estimates.
  3. The forecast identifies which dependent activities and completion date are impacted by the delay.
  4. The schedule shows an owned buffer and forecast updates when the supplier risk materializes.

Explanation

Correct Answer

B:

Sprint commitments contain small independently testable stories with explicit capacity estimates. This is the relevant acceptance evidence because it tests whether the corrective action (Break the epic into smaller estimable stories and prioritize them for feasible sprint planning.) fixed the original concern (An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments.) at Newbridge Charity, rather than relying only on a task marked complete. The affected work concerns donation workflows and volunteer accounts.

Incorrect Answers

A:

The schedule will not start integration testing before the required build output is available. This evidence would be useful for another condition (A plan places integration testing before the dependent build is finished and reports no schedule conflict.) and its different action (Define the correct finish-to-start dependency between build completion and integration testing.). At Newbridge Charity, it does not demonstrate the required project outcome: Sprint commitments contain small independently testable stories with explicit capacity estimates.

C:

The forecast identifies which dependent activities and completion date are impacted by the delay. This evidence would be useful for another condition (A schedule lists ten activities but contains no predecessor logic so a one-week delay has no visible downstream impact.) and its different action (Construct a dependency network and calculate the critical path for baseline monitoring.). At Newbridge Charity, it does not demonstrate the required project outcome: Sprint commitments contain small independently testable stories with explicit capacity estimates.

D:

The schedule shows an owned buffer and forecast updates when the supplier risk materializes. This evidence would be useful for another condition (The plan has no schedule buffer for a supplier dependency known to have significant delivery variability.) and its different action (Size and document an appropriate contingency reserve based on risk and supplier uncertainty.). At Newbridge Charity, it does not demonstrate the required project outcome: Sprint commitments contain small independently testable stories with explicit capacity estimates.

Question 225

For Greenpeak Civic Services, the implementation team reports the following delivery problem: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. Which project management action BEST addresses the particular issue?

  1. Size and document an appropriate contingency reserve based on risk and supplier uncertainty.
  2. Define the correct finish-to-start dependency between build completion and integration testing.
  3. Break the epic into smaller estimable stories and prioritize them for feasible sprint planning.
  4. Construct a dependency network and calculate the critical path for baseline monitoring.

Explanation

Correct Answer

C:

Break the epic into smaller estimable stories and prioritize them for feasible sprint planning. This directly addresses the reported management gap: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. For Greenpeak Civic Services and its citizen services and digital identity, a useful verification outcome is: Sprint commitments contain small independently testable stories with explicit capacity estimates.

Incorrect Answers

A:

Size and document an appropriate contingency reserve based on risk and supplier uncertainty. This choice addresses another specific project condition: The plan has no schedule buffer for a supplier dependency known to have significant delivery variability. The actual issue at Greenpeak Civic Services is: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. That other intervention does not itself establish the required result: Sprint commitments contain small independently testable stories with explicit capacity estimates.

B:

Define the correct finish-to-start dependency between build completion and integration testing. This choice addresses another specific project condition: A plan places integration testing before the dependent build is finished and reports no schedule conflict. The actual issue at Greenpeak Civic Services is: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. That other intervention does not itself establish the required result: Sprint commitments contain small independently testable stories with explicit capacity estimates.

D:

Construct a dependency network and calculate the critical path for baseline monitoring. This choice addresses another specific project condition: A schedule lists ten activities but contains no predecessor logic so a one-week delay has no visible downstream impact. The actual issue at Greenpeak Civic Services is: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. That other intervention does not itself establish the required result: Sprint commitments contain small independently testable stories with explicit capacity estimates.

Question 226

For Greenpeak Civic Services, the implementation team reports the following delivery problem: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The schedule will not start integration testing before the required build output is available.
  2. The schedule shows an owned buffer and forecast updates when the supplier risk materializes.
  3. The forecast identifies which dependent activities and completion date are impacted by the delay.
  4. Sprint commitments contain small independently testable stories with explicit capacity estimates.

Explanation

Correct Answer

D:

Sprint commitments contain small independently testable stories with explicit capacity estimates. This is the relevant acceptance evidence because it tests whether the corrective action (Break the epic into smaller estimable stories and prioritize them for feasible sprint planning.) fixed the original concern (An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments.) at Greenpeak Civic Services, rather than relying only on a task marked complete. The affected work concerns citizen services and digital identity.

Incorrect Answers

A:

The schedule will not start integration testing before the required build output is available. This evidence would be useful for another condition (A plan places integration testing before the dependent build is finished and reports no schedule conflict.) and its different action (Define the correct finish-to-start dependency between build completion and integration testing.). At Greenpeak Civic Services, it does not demonstrate the required project outcome: Sprint commitments contain small independently testable stories with explicit capacity estimates.

B:

The schedule shows an owned buffer and forecast updates when the supplier risk materializes. This evidence would be useful for another condition (The plan has no schedule buffer for a supplier dependency known to have significant delivery variability.) and its different action (Size and document an appropriate contingency reserve based on risk and supplier uncertainty.). At Greenpeak Civic Services, it does not demonstrate the required project outcome: Sprint commitments contain small independently testable stories with explicit capacity estimates.

C:

The forecast identifies which dependent activities and completion date are impacted by the delay. This evidence would be useful for another condition (A schedule lists ten activities but contains no predecessor logic so a one-week delay has no visible downstream impact.) and its different action (Construct a dependency network and calculate the critical path for baseline monitoring.). At Greenpeak Civic Services, it does not demonstrate the required project outcome: Sprint commitments contain small independently testable stories with explicit capacity estimates.

Question 227

At Atlas Scientific, the delivery assessment finds: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. Which project management action BEST addresses the particular issue?

  1. Break the epic into smaller estimable stories and prioritize them for feasible sprint planning.
  2. Construct a dependency network and calculate the critical path for baseline monitoring.
  3. Size and document an appropriate contingency reserve based on risk and supplier uncertainty.
  4. Define the correct finish-to-start dependency between build completion and integration testing.

Explanation

Correct Answer

A:

Break the epic into smaller estimable stories and prioritize them for feasible sprint planning. This directly addresses the reported management gap: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. For Atlas Scientific and its lab collaboration and cloud-hosted research, a useful verification outcome is: Sprint commitments contain small independently testable stories with explicit capacity estimates.

Incorrect Answers

B:

Construct a dependency network and calculate the critical path for baseline monitoring. This choice addresses another specific project condition: A schedule lists ten activities but contains no predecessor logic so a one-week delay has no visible downstream impact. The actual issue at Atlas Scientific is: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. That other intervention does not itself establish the required result: Sprint commitments contain small independently testable stories with explicit capacity estimates.

C:

Size and document an appropriate contingency reserve based on risk and supplier uncertainty. This choice addresses another specific project condition: The plan has no schedule buffer for a supplier dependency known to have significant delivery variability. The actual issue at Atlas Scientific is: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. That other intervention does not itself establish the required result: Sprint commitments contain small independently testable stories with explicit capacity estimates.

D:

Define the correct finish-to-start dependency between build completion and integration testing. This choice addresses another specific project condition: A plan places integration testing before the dependent build is finished and reports no schedule conflict. The actual issue at Atlas Scientific is: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. That other intervention does not itself establish the required result: Sprint commitments contain small independently testable stories with explicit capacity estimates.

Question 228

At Atlas Scientific, the delivery assessment finds: An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The schedule will not start integration testing before the required build output is available.
  2. The forecast identifies which dependent activities and completion date are impacted by the delay.
  3. Sprint commitments contain small independently testable stories with explicit capacity estimates.
  4. The schedule shows an owned buffer and forecast updates when the supplier risk materializes.

Explanation

Correct Answer

C:

Sprint commitments contain small independently testable stories with explicit capacity estimates. This is the relevant acceptance evidence because it tests whether the corrective action (Break the epic into smaller estimable stories and prioritize them for feasible sprint planning.) fixed the original concern (An Agile team estimates a large user story as a complete project plan without splitting it into deliverable increments.) at Atlas Scientific, rather than relying only on a task marked complete. The affected work concerns lab collaboration and cloud-hosted research.

Incorrect Answers

A:

The schedule will not start integration testing before the required build output is available. This evidence would be useful for another condition (A plan places integration testing before the dependent build is finished and reports no schedule conflict.) and its different action (Define the correct finish-to-start dependency between build completion and integration testing.). At Atlas Scientific, it does not demonstrate the required project outcome: Sprint commitments contain small independently testable stories with explicit capacity estimates.

B:

The forecast identifies which dependent activities and completion date are impacted by the delay. This evidence would be useful for another condition (A schedule lists ten activities but contains no predecessor logic so a one-week delay has no visible downstream impact.) and its different action (Construct a dependency network and calculate the critical path for baseline monitoring.). At Atlas Scientific, it does not demonstrate the required project outcome: Sprint commitments contain small independently testable stories with explicit capacity estimates.

D:

The schedule shows an owned buffer and forecast updates when the supplier risk materializes. This evidence would be useful for another condition (The plan has no schedule buffer for a supplier dependency known to have significant delivery variability.) and its different action (Size and document an appropriate contingency reserve based on risk and supplier uncertainty.). At Atlas Scientific, it does not demonstrate the required project outcome: Sprint commitments contain small independently testable stories with explicit capacity estimates.

Question 229

At Granite Peak Sports, the delivery assessment finds: Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged. Which project management action BEST addresses the particular issue?

  1. Define the correct finish-to-start dependency between build completion and integration testing.
  2. Maintain the original approved baseline and forecast the variance unless formal rebaselining is authorized.
  3. Level or reassign overallocated resource tasks and document the resulting schedule impacts.
  4. Represent the launch approval as a milestone with properly linked predecessor activities.

Explanation

Correct Answer

C:

Level or reassign overallocated resource tasks and document the resulting schedule impacts. This directly addresses the reported management gap: Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged. For Granite Peak Sports and its sports analytics and media distribution, a useful verification outcome is: The resource loading report no longer shows impossible concurrent allocations for that engineer.

Incorrect Answers

A:

Define the correct finish-to-start dependency between build completion and integration testing. This choice addresses another specific project condition: A plan places integration testing before the dependent build is finished and reports no schedule conflict. The actual issue at Granite Peak Sports is: Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged. That other intervention does not itself establish the required result: The resource loading report no longer shows impossible concurrent allocations for that engineer.

B:

Maintain the original approved baseline and forecast the variance unless formal rebaselining is authorized. This choice addresses another specific project condition: A PM quietly changes the approved end date after a task slips and reports the revised dates as if no variance occurred. The actual issue at Granite Peak Sports is: Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged. That other intervention does not itself establish the required result: The resource loading report no longer shows impossible concurrent allocations for that engineer.

D:

Represent the launch approval as a milestone with properly linked predecessor activities. This choice addresses another specific project condition: A team treats a zero-duration launch gate as a week-long task and misstates the project completion date. The actual issue at Granite Peak Sports is: Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged. That other intervention does not itself establish the required result: The resource loading report no longer shows impossible concurrent allocations for that engineer.

Question 230

At Granite Peak Sports, the delivery assessment finds: Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The resource loading report no longer shows impossible concurrent allocations for that engineer.
  2. The schedule marks a dated zero-duration decision gate after required tasks finish.
  3. The schedule will not start integration testing before the required build output is available.
  4. The report distinguishes baseline variance from the current forecast and any approved new baseline.

Explanation

Correct Answer

A:

The resource loading report no longer shows impossible concurrent allocations for that engineer. This is the relevant acceptance evidence because it tests whether the corrective action (Level or reassign overallocated resource tasks and document the resulting schedule impacts.) fixed the original concern (Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged.) at Granite Peak Sports, rather than relying only on a task marked complete. The affected work concerns sports analytics and media distribution.

Incorrect Answers

B:

The schedule marks a dated zero-duration decision gate after required tasks finish. This evidence would be useful for another condition (A team treats a zero-duration launch gate as a week-long task and misstates the project completion date.) and its different action (Represent the launch approval as a milestone with properly linked predecessor activities.). At Granite Peak Sports, it does not demonstrate the required project outcome: The resource loading report no longer shows impossible concurrent allocations for that engineer.

C:

The schedule will not start integration testing before the required build output is available. This evidence would be useful for another condition (A plan places integration testing before the dependent build is finished and reports no schedule conflict.) and its different action (Define the correct finish-to-start dependency between build completion and integration testing.). At Granite Peak Sports, it does not demonstrate the required project outcome: The resource loading report no longer shows impossible concurrent allocations for that engineer.

D:

The report distinguishes baseline variance from the current forecast and any approved new baseline. This evidence would be useful for another condition (A PM quietly changes the approved end date after a task slips and reports the revised dates as if no variance occurred.) and its different action (Maintain the original approved baseline and forecast the variance unless formal rebaselining is authorized.). At Granite Peak Sports, it does not demonstrate the required project outcome: The resource loading report no longer shows impossible concurrent allocations for that engineer.