Question 200
A project governance review at Harbor Point Medical identifies this problem during a product deployment planning session: A project issue is marked closed when code is merged though the customer still sees the problem in acceptance testing. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
An acceptance retest passes and the issue record shows who verified resolution. This is the relevant acceptance evidence because it tests whether the corrective action (Require outcome verification and impacted stakeholder confirmation before issue closure.) fixed the original concern (A project issue is marked closed when code is merged though the customer still sees the problem in acceptance testing.) at Harbor Point Medical, rather than relying only on a task marked complete. The affected work concerns clinical collaboration and patient information.
Incorrect Answers
The escalation record shows timely notice and a decision before the regulatory deadline is missed. This evidence would be useful for another condition (A blocker affects a regulatory deadline but the engineer waits for the normal monthly status review to tell leadership.) and its different action (Escalate the high-impact issue immediately through the agreed authority path.). At Harbor Point Medical, it does not demonstrate the required project outcome: An acceptance retest passes and the issue record shows who verified resolution.
The issue dashboard shows one underlying failure with accurate affected milestones and owners. This evidence would be useful for another condition (Two teams open separate tickets for one shared dependency outage and estimate different project impacts.) and its different action (Link related issue records to a common root cause and reconcile cross-team impact reporting.). At Harbor Point Medical, it does not demonstrate the required project outcome: An acceptance retest passes and the issue record shows who verified resolution.
The issue log shows the actual outage and updates until testing can resume. This evidence would be useful for another condition (A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution.) and its different action (Open an issue with severity urgency owner escalation route and restoration actions.). At Harbor Point Medical, it does not demonstrate the required project outcome: An acceptance retest passes and the issue record shows who verified resolution.