Question 230
At Granite Peak Sports, the delivery assessment finds: Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The resource loading report no longer shows impossible concurrent allocations for that engineer. This is the relevant acceptance evidence because it tests whether the corrective action (Level or reassign overallocated resource tasks and document the resulting schedule impacts.) fixed the original concern (Project planners allocate one engineer at 200 percent capacity while assuming the milestone dates are unchanged.) at Granite Peak Sports, rather than relying only on a task marked complete. The affected work concerns sports analytics and media distribution.
Incorrect Answers
The schedule marks a dated zero-duration decision gate after required tasks finish. This evidence would be useful for another condition (A team treats a zero-duration launch gate as a week-long task and misstates the project completion date.) and its different action (Represent the launch approval as a milestone with properly linked predecessor activities.). At Granite Peak Sports, it does not demonstrate the required project outcome: The resource loading report no longer shows impossible concurrent allocations for that engineer.
The schedule will not start integration testing before the required build output is available. This evidence would be useful for another condition (A plan places integration testing before the dependent build is finished and reports no schedule conflict.) and its different action (Define the correct finish-to-start dependency between build completion and integration testing.). At Granite Peak Sports, it does not demonstrate the required project outcome: The resource loading report no longer shows impossible concurrent allocations for that engineer.
The report distinguishes baseline variance from the current forecast and any approved new baseline. This evidence would be useful for another condition (A PM quietly changes the approved end date after a task slips and reports the revised dates as if no variance occurred.) and its different action (Maintain the original approved baseline and forecast the variance unless formal rebaselining is authorized.). At Granite Peak Sports, it does not demonstrate the required project outcome: The resource loading report no longer shows impossible concurrent allocations for that engineer.