Question 190
A project governance review at Lakeview Insurance identifies this problem during a vendor selection exercise: A defect is repeatedly fixed with a temporary workaround and nobody investigates why it returns. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The defect stays absent in regression runs and the issue record documents its root cause. This is the relevant acceptance evidence because it tests whether the corrective action (Record interim containment while conducting a root cause analysis and permanent corrective action.) fixed the original concern (A defect is repeatedly fixed with a temporary workaround and nobody investigates why it returns.) at Lakeview Insurance, rather than relying only on a task marked complete. The affected work concerns broker collaboration and claim applications.
Incorrect Answers
The issue log shows the actual outage and updates until testing can resume. This evidence would be useful for another condition (A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution.) and its different action (Open an issue with severity urgency owner escalation route and restoration actions.). At Lakeview Insurance, it does not demonstrate the required project outcome: The defect stays absent in regression runs and the issue record documents its root cause.
The escalation record shows timely notice and a decision before the regulatory deadline is missed. This evidence would be useful for another condition (A blocker affects a regulatory deadline but the engineer waits for the normal monthly status review to tell leadership.) and its different action (Escalate the high-impact issue immediately through the agreed authority path.). At Lakeview Insurance, it does not demonstrate the required project outcome: The defect stays absent in regression runs and the issue record documents its root cause.
The issue dashboard shows one underlying failure with accurate affected milestones and owners. This evidence would be useful for another condition (Two teams open separate tickets for one shared dependency outage and estimate different project impacts.) and its different action (Link related issue records to a common root cause and reconcile cross-team impact reporting.). At Lakeview Insurance, it does not demonstrate the required project outcome: The defect stays absent in regression runs and the issue record documents its root cause.