McAfee-Secured Website

Exam Bundle

Exam Code: PK0-005

Exam Name CompTIA Project+

Certification Provider: CompTIA

Corresponding Certification: CompTIA Project+

CompTIA PK0-005 Bundle $44.99

100% CompTIA PK0-005 Guaranteed Success With Testking Training Materials

Get Real PK0-005 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    PK0-005 Questions & Answers

    628 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual PK0-005 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • PK0-005 Video Course

    PK0-005 Video Course

    159 Video Lectures

    PK0-005 Video Course is developed by CompTIA Professionals to help you pass the PK0-005 exam.

    Description

    This course will improve your knowledge and skills required to pass CompTIA Project+ exam.
  • Study Guide

    PK0-005 Study Guide

    682 PDF Pages

    Developed by industry experts, this 682-page guide spells out in painstaking detail all of the information you need to ace PK0-005 exam.

CompTIA Project+ (PK0-005) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    628 Questions

    $124.99
  • PK0-005 Video Course

    Video Course

    159 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    682 PDF Pages

    $29.99

CompTIA PK0-005 Practice Test 18

Question 170

Eastport Research Hospital is delivering an IT initiative involving medical research systems and directory accounts with several affected stakeholder groups. The team observes: The project relies on a single specialist and the contingency plan assumes that specialist is always available. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The risk matrix shows a justified rating and corresponding treatment owner.
  2. A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.
  3. The risk register tracks the possible supplier delay before a failure occurs.
  4. The issue log names an owner resolution deadline and actual schedule impact.

Explanation

Correct Answer

B:

A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable. This is the relevant acceptance evidence because it tests whether the corrective action (Create a fallback resource plan and reserve appropriate time or budget for the dependency.) fixed the original concern (The project relies on a single specialist and the contingency plan assumes that specialist is always available.) at Eastport Research Hospital, rather than relying only on a task marked complete. The affected work concerns medical research systems and directory accounts.

Incorrect Answers

A:

The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Eastport Research Hospital, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

C:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Eastport Research Hospital, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

D:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Eastport Research Hospital, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Question 171

For Pinecrest Research, the business analyst reports the following delivery problem: The project relies on a single specialist and the contingency plan assumes that specialist is always available. Which project management action BEST addresses the particular issue?

  1. Perform qualitative probability-impact assessment and prioritize according to defined criteria.
  2. Log the realized delay as an issue and invoke the response plan while updating related risks.
  3. Create a fallback resource plan and reserve appropriate time or budget for the dependency.
  4. Record the uncertain event as a risk with probability impact owner and planned response.

Explanation

Correct Answer

C:

Create a fallback resource plan and reserve appropriate time or budget for the dependency. This directly addresses the reported management gap: The project relies on a single specialist and the contingency plan assumes that specialist is always available. For Pinecrest Research and its research data and distributed collaboration, a useful verification outcome is: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Incorrect Answers

A:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This choice addresses another specific project condition: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The actual issue at Pinecrest Research is: The project relies on a single specialist and the contingency plan assumes that specialist is always available. That other intervention does not itself establish the required result: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

B:

Log the realized delay as an issue and invoke the response plan while updating related risks. This choice addresses another specific project condition: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The actual issue at Pinecrest Research is: The project relies on a single specialist and the contingency plan assumes that specialist is always available. That other intervention does not itself establish the required result: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

D:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Pinecrest Research is: The project relies on a single specialist and the contingency plan assumes that specialist is always available. That other intervention does not itself establish the required result: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Question 172

For Pinecrest Research, the business analyst reports the following delivery problem: The project relies on a single specialist and the contingency plan assumes that specialist is always available. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The issue log names an owner resolution deadline and actual schedule impact.
  2. The risk register tracks the possible supplier delay before a failure occurs.
  3. The risk matrix shows a justified rating and corresponding treatment owner.
  4. A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Explanation

Correct Answer

D:

A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable. This is the relevant acceptance evidence because it tests whether the corrective action (Create a fallback resource plan and reserve appropriate time or budget for the dependency.) fixed the original concern (The project relies on a single specialist and the contingency plan assumes that specialist is always available.) at Pinecrest Research, rather than relying only on a task marked complete. The affected work concerns research data and distributed collaboration.

Incorrect Answers

A:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Pinecrest Research, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

B:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Pinecrest Research, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

C:

The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Pinecrest Research, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Question 173

At Willowbrook Education, the delivery assessment finds: The project relies on a single specialist and the contingency plan assumes that specialist is always available. Which project management action BEST addresses the particular issue?

  1. Perform qualitative probability-impact assessment and prioritize according to defined criteria.
  2. Log the realized delay as an issue and invoke the response plan while updating related risks.
  3. Record the uncertain event as a risk with probability impact owner and planned response.
  4. Create a fallback resource plan and reserve appropriate time or budget for the dependency.

Explanation

Correct Answer

D:

Create a fallback resource plan and reserve appropriate time or budget for the dependency. This directly addresses the reported management gap: The project relies on a single specialist and the contingency plan assumes that specialist is always available. For Willowbrook Education and its student registration and teacher collaboration, a useful verification outcome is: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Incorrect Answers

A:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This choice addresses another specific project condition: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The actual issue at Willowbrook Education is: The project relies on a single specialist and the contingency plan assumes that specialist is always available. That other intervention does not itself establish the required result: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

B:

Log the realized delay as an issue and invoke the response plan while updating related risks. This choice addresses another specific project condition: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The actual issue at Willowbrook Education is: The project relies on a single specialist and the contingency plan assumes that specialist is always available. That other intervention does not itself establish the required result: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

C:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Willowbrook Education is: The project relies on a single specialist and the contingency plan assumes that specialist is always available. That other intervention does not itself establish the required result: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Question 174

At Willowbrook Education, the delivery assessment finds: The project relies on a single specialist and the contingency plan assumes that specialist is always available. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The issue log names an owner resolution deadline and actual schedule impact.
  2. The risk register tracks the possible supplier delay before a failure occurs.
  3. A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.
  4. The risk matrix shows a justified rating and corresponding treatment owner.

Explanation

Correct Answer

C:

A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable. This is the relevant acceptance evidence because it tests whether the corrective action (Create a fallback resource plan and reserve appropriate time or budget for the dependency.) fixed the original concern (The project relies on a single specialist and the contingency plan assumes that specialist is always available.) at Willowbrook Education, rather than relying only on a task marked complete. The affected work concerns student registration and teacher collaboration.

Incorrect Answers

A:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Willowbrook Education, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

B:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Willowbrook Education, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

D:

The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Willowbrook Education, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Question 175

A project affecting vehicle engineering and customer services at Riverbend Automotive encounters a management concern: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. Which project management action BEST addresses the particular issue?

  1. Open an issue with severity urgency owner escalation route and restoration actions.
  2. Escalate the high-impact issue immediately through the agreed authority path.
  3. Link related issue records to a common root cause and reconcile cross-team impact reporting.
  4. Require outcome verification and impacted stakeholder confirmation before issue closure.

Explanation

Correct Answer

A:

Open an issue with severity urgency owner escalation route and restoration actions. This directly addresses the reported management gap: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. For Riverbend Automotive and its vehicle engineering and customer services, a useful verification outcome is: The issue log shows the actual outage and updates until testing can resume.

Incorrect Answers

B:

Escalate the high-impact issue immediately through the agreed authority path. This choice addresses another specific project condition: A blocker affects a regulatory deadline but the engineer waits for the normal monthly status review to tell leadership. The actual issue at Riverbend Automotive is: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. That other intervention does not itself establish the required result: The issue log shows the actual outage and updates until testing can resume.

C:

Link related issue records to a common root cause and reconcile cross-team impact reporting. This choice addresses another specific project condition: Two teams open separate tickets for one shared dependency outage and estimate different project impacts. The actual issue at Riverbend Automotive is: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. That other intervention does not itself establish the required result: The issue log shows the actual outage and updates until testing can resume.

D:

Require outcome verification and impacted stakeholder confirmation before issue closure. This choice addresses another specific project condition: A project issue is marked closed when code is merged though the customer still sees the problem in acceptance testing. The actual issue at Riverbend Automotive is: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. That other intervention does not itself establish the required result: The issue log shows the actual outage and updates until testing can resume.

Question 176

A project affecting vehicle engineering and customer services at Riverbend Automotive encounters a management concern: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The issue dashboard shows one underlying failure with accurate affected milestones and owners.
  2. An acceptance retest passes and the issue record shows who verified resolution.
  3. The issue log shows the actual outage and updates until testing can resume.
  4. The escalation record shows timely notice and a decision before the regulatory deadline is missed.

Explanation

Correct Answer

C:

The issue log shows the actual outage and updates until testing can resume. This is the relevant acceptance evidence because it tests whether the corrective action (Open an issue with severity urgency owner escalation route and restoration actions.) fixed the original concern (A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution.) at Riverbend Automotive, rather than relying only on a task marked complete. The affected work concerns vehicle engineering and customer services.

Incorrect Answers

A:

The issue dashboard shows one underlying failure with accurate affected milestones and owners. This evidence would be useful for another condition (Two teams open separate tickets for one shared dependency outage and estimate different project impacts.) and its different action (Link related issue records to a common root cause and reconcile cross-team impact reporting.). At Riverbend Automotive, it does not demonstrate the required project outcome: The issue log shows the actual outage and updates until testing can resume.

B:

An acceptance retest passes and the issue record shows who verified resolution. This evidence would be useful for another condition (A project issue is marked closed when code is merged though the customer still sees the problem in acceptance testing.) and its different action (Require outcome verification and impacted stakeholder confirmation before issue closure.). At Riverbend Automotive, it does not demonstrate the required project outcome: The issue log shows the actual outage and updates until testing can resume.

D:

The escalation record shows timely notice and a decision before the regulatory deadline is missed. This evidence would be useful for another condition (A blocker affects a regulatory deadline but the engineer waits for the normal monthly status review to tell leadership.) and its different action (Escalate the high-impact issue immediately through the agreed authority path.). At Riverbend Automotive, it does not demonstrate the required project outcome: The issue log shows the actual outage and updates until testing can resume.

Question 177

During a vendor selection exercise at Summit Rail Authority, the project manager identifies an issue: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. Which project management action BEST addresses the particular issue?

  1. Require outcome verification and impacted stakeholder confirmation before issue closure.
  2. Escalate the high-impact issue immediately through the agreed authority path.
  3. Open an issue with severity urgency owner escalation route and restoration actions.
  4. Link related issue records to a common root cause and reconcile cross-team impact reporting.

Explanation

Correct Answer

C:

Open an issue with severity urgency owner escalation route and restoration actions. This directly addresses the reported management gap: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. For Summit Rail Authority and its ticketing and customer-service applications, a useful verification outcome is: The issue log shows the actual outage and updates until testing can resume.

Incorrect Answers

A:

Require outcome verification and impacted stakeholder confirmation before issue closure. This choice addresses another specific project condition: A project issue is marked closed when code is merged though the customer still sees the problem in acceptance testing. The actual issue at Summit Rail Authority is: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. That other intervention does not itself establish the required result: The issue log shows the actual outage and updates until testing can resume.

B:

Escalate the high-impact issue immediately through the agreed authority path. This choice addresses another specific project condition: A blocker affects a regulatory deadline but the engineer waits for the normal monthly status review to tell leadership. The actual issue at Summit Rail Authority is: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. That other intervention does not itself establish the required result: The issue log shows the actual outage and updates until testing can resume.

D:

Link related issue records to a common root cause and reconcile cross-team impact reporting. This choice addresses another specific project condition: Two teams open separate tickets for one shared dependency outage and estimate different project impacts. The actual issue at Summit Rail Authority is: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. That other intervention does not itself establish the required result: The issue log shows the actual outage and updates until testing can resume.

Question 178

During a vendor selection exercise at Summit Rail Authority, the project manager identifies an issue: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. An acceptance retest passes and the issue record shows who verified resolution.
  2. The issue log shows the actual outage and updates until testing can resume.
  3. The escalation record shows timely notice and a decision before the regulatory deadline is missed.
  4. The issue dashboard shows one underlying failure with accurate affected milestones and owners.

Explanation

Correct Answer

B:

The issue log shows the actual outage and updates until testing can resume. This is the relevant acceptance evidence because it tests whether the corrective action (Open an issue with severity urgency owner escalation route and restoration actions.) fixed the original concern (A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution.) at Summit Rail Authority, rather than relying only on a task marked complete. The affected work concerns ticketing and customer-service applications.

Incorrect Answers

A:

An acceptance retest passes and the issue record shows who verified resolution. This evidence would be useful for another condition (A project issue is marked closed when code is merged though the customer still sees the problem in acceptance testing.) and its different action (Require outcome verification and impacted stakeholder confirmation before issue closure.). At Summit Rail Authority, it does not demonstrate the required project outcome: The issue log shows the actual outage and updates until testing can resume.

C:

The escalation record shows timely notice and a decision before the regulatory deadline is missed. This evidence would be useful for another condition (A blocker affects a regulatory deadline but the engineer waits for the normal monthly status review to tell leadership.) and its different action (Escalate the high-impact issue immediately through the agreed authority path.). At Summit Rail Authority, it does not demonstrate the required project outcome: The issue log shows the actual outage and updates until testing can resume.

D:

The issue dashboard shows one underlying failure with accurate affected milestones and owners. This evidence would be useful for another condition (Two teams open separate tickets for one shared dependency outage and estimate different project impacts.) and its different action (Link related issue records to a common root cause and reconcile cross-team impact reporting.). At Summit Rail Authority, it does not demonstrate the required project outcome: The issue log shows the actual outage and updates until testing can resume.

Question 179

A project governance review at Frostline Distribution identifies this problem during a high-priority issue escalation: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. Which project management action BEST addresses the particular issue?

  1. Escalate the high-impact issue immediately through the agreed authority path.
  2. Open an issue with severity urgency owner escalation route and restoration actions.
  3. Link related issue records to a common root cause and reconcile cross-team impact reporting.
  4. Require outcome verification and impacted stakeholder confirmation before issue closure.

Explanation

Correct Answer

B:

Open an issue with severity urgency owner escalation route and restoration actions. This directly addresses the reported management gap: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. For Frostline Distribution and its inventory systems and supplier access, a useful verification outcome is: The issue log shows the actual outage and updates until testing can resume.

Incorrect Answers

A:

Escalate the high-impact issue immediately through the agreed authority path. This choice addresses another specific project condition: A blocker affects a regulatory deadline but the engineer waits for the normal monthly status review to tell leadership. The actual issue at Frostline Distribution is: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. That other intervention does not itself establish the required result: The issue log shows the actual outage and updates until testing can resume.

C:

Link related issue records to a common root cause and reconcile cross-team impact reporting. This choice addresses another specific project condition: Two teams open separate tickets for one shared dependency outage and estimate different project impacts. The actual issue at Frostline Distribution is: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. That other intervention does not itself establish the required result: The issue log shows the actual outage and updates until testing can resume.

D:

Require outcome verification and impacted stakeholder confirmation before issue closure. This choice addresses another specific project condition: A project issue is marked closed when code is merged though the customer still sees the problem in acceptance testing. The actual issue at Frostline Distribution is: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. That other intervention does not itself establish the required result: The issue log shows the actual outage and updates until testing can resume.

Question 180

A project governance review at Frostline Distribution identifies this problem during a high-priority issue escalation: A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. An acceptance retest passes and the issue record shows who verified resolution.
  2. The issue dashboard shows one underlying failure with accurate affected milestones and owners.
  3. The issue log shows the actual outage and updates until testing can resume.
  4. The escalation record shows timely notice and a decision before the regulatory deadline is missed.

Explanation

Correct Answer

C:

The issue log shows the actual outage and updates until testing can resume. This is the relevant acceptance evidence because it tests whether the corrective action (Open an issue with severity urgency owner escalation route and restoration actions.) fixed the original concern (A server outage is blocking active testing but the PM puts it in the future risk register rather than tracking current resolution.) at Frostline Distribution, rather than relying only on a task marked complete. The affected work concerns inventory systems and supplier access.

Incorrect Answers

A:

An acceptance retest passes and the issue record shows who verified resolution. This evidence would be useful for another condition (A project issue is marked closed when code is merged though the customer still sees the problem in acceptance testing.) and its different action (Require outcome verification and impacted stakeholder confirmation before issue closure.). At Frostline Distribution, it does not demonstrate the required project outcome: The issue log shows the actual outage and updates until testing can resume.

B:

The issue dashboard shows one underlying failure with accurate affected milestones and owners. This evidence would be useful for another condition (Two teams open separate tickets for one shared dependency outage and estimate different project impacts.) and its different action (Link related issue records to a common root cause and reconcile cross-team impact reporting.). At Frostline Distribution, it does not demonstrate the required project outcome: The issue log shows the actual outage and updates until testing can resume.

D:

The escalation record shows timely notice and a decision before the regulatory deadline is missed. This evidence would be useful for another condition (A blocker affects a regulatory deadline but the engineer waits for the normal monthly status review to tell leadership.) and its different action (Escalate the high-impact issue immediately through the agreed authority path.). At Frostline Distribution, it does not demonstrate the required project outcome: The issue log shows the actual outage and updates until testing can resume.