Question 160
Copper Hill Studios is delivering an IT initiative involving media assets and freelancer collaboration in a mixed Agile and predictive delivery environment. The team observes: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The revised solution no longer includes the risky function and its scope change is recorded. This is the relevant acceptance evidence because it tests whether the corrective action (Avoid the risk by removing the unnecessary exposure through an approved scope decision.) fixed the original concern (A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead.) at Copper Hill Studios, rather than relying only on a task marked complete. The affected work concerns media assets and freelancer collaboration.
Incorrect Answers
The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Copper Hill Studios, it does not demonstrate the required project outcome: The revised solution no longer includes the risky function and its scope change is recorded.
The treatment record identifies transferred financial exposure and separately managed remaining risks. This evidence would be useful for another condition (A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination.) and its different action (Classify insurance as risk transfer and retain ownership of any residual project consequences.). At Copper Hill Studios, it does not demonstrate the required project outcome: The revised solution no longer includes the risky function and its scope change is recorded.
The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Copper Hill Studios, it does not demonstrate the required project outcome: The revised solution no longer includes the risky function and its scope change is recorded.