McAfee-Secured Website

Exam Bundle

Exam Code: PK0-005

Exam Name CompTIA Project+

Certification Provider: CompTIA

Corresponding Certification: CompTIA Project+

CompTIA PK0-005 Bundle $44.99

100% CompTIA PK0-005 Guaranteed Success With Testking Training Materials

Get Real PK0-005 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    PK0-005 Questions & Answers

    628 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual PK0-005 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • PK0-005 Video Course

    PK0-005 Video Course

    159 Video Lectures

    PK0-005 Video Course is developed by CompTIA Professionals to help you pass the PK0-005 exam.

    Description

    This course will improve your knowledge and skills required to pass CompTIA Project+ exam.
  • Study Guide

    PK0-005 Study Guide

    682 PDF Pages

    Developed by industry experts, this 682-page guide spells out in painstaking detail all of the information you need to ace PK0-005 exam.

CompTIA Project+ (PK0-005) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    628 Questions

    $124.99
  • PK0-005 Video Course

    Video Course

    159 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    682 PDF Pages

    $29.99

CompTIA PK0-005 Practice Test 17

Question 160

Copper Hill Studios is delivering an IT initiative involving media assets and freelancer collaboration in a mixed Agile and predictive delivery environment. The team observes: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The risk matrix shows a justified rating and corresponding treatment owner.
  2. The revised solution no longer includes the risky function and its scope change is recorded.
  3. The treatment record identifies transferred financial exposure and separately managed remaining risks.
  4. The risk register tracks the possible supplier delay before a failure occurs.

Explanation

Correct Answer

B:

The revised solution no longer includes the risky function and its scope change is recorded. This is the relevant acceptance evidence because it tests whether the corrective action (Avoid the risk by removing the unnecessary exposure through an approved scope decision.) fixed the original concern (A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead.) at Copper Hill Studios, rather than relying only on a task marked complete. The affected work concerns media assets and freelancer collaboration.

Incorrect Answers

A:

The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Copper Hill Studios, it does not demonstrate the required project outcome: The revised solution no longer includes the risky function and its scope change is recorded.

C:

The treatment record identifies transferred financial exposure and separately managed remaining risks. This evidence would be useful for another condition (A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination.) and its different action (Classify insurance as risk transfer and retain ownership of any residual project consequences.). At Copper Hill Studios, it does not demonstrate the required project outcome: The revised solution no longer includes the risky function and its scope change is recorded.

D:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Copper Hill Studios, it does not demonstrate the required project outcome: The revised solution no longer includes the risky function and its scope change is recorded.

Question 161

For Aster Mutual, the implementation team reports the following delivery problem: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. Which project management action BEST addresses the particular issue?

  1. Record the uncertain event as a risk with probability impact owner and planned response.
  2. Classify insurance as risk transfer and retain ownership of any residual project consequences.
  3. Avoid the risk by removing the unnecessary exposure through an approved scope decision.
  4. Perform qualitative probability-impact assessment and prioritize according to defined criteria.

Explanation

Correct Answer

C:

Avoid the risk by removing the unnecessary exposure through an approved scope decision. This directly addresses the reported management gap: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. For Aster Mutual and its claims processing and confidential customer records, a useful verification outcome is: The revised solution no longer includes the risky function and its scope change is recorded.

Incorrect Answers

A:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Aster Mutual is: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. That other intervention does not itself establish the required result: The revised solution no longer includes the risky function and its scope change is recorded.

B:

Classify insurance as risk transfer and retain ownership of any residual project consequences. This choice addresses another specific project condition: A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination. The actual issue at Aster Mutual is: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. That other intervention does not itself establish the required result: The revised solution no longer includes the risky function and its scope change is recorded.

D:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This choice addresses another specific project condition: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The actual issue at Aster Mutual is: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. That other intervention does not itself establish the required result: The revised solution no longer includes the risky function and its scope change is recorded.

Question 162

For Aster Mutual, the implementation team reports the following delivery problem: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The risk matrix shows a justified rating and corresponding treatment owner.
  2. The treatment record identifies transferred financial exposure and separately managed remaining risks.
  3. The risk register tracks the possible supplier delay before a failure occurs.
  4. The revised solution no longer includes the risky function and its scope change is recorded.

Explanation

Correct Answer

D:

The revised solution no longer includes the risky function and its scope change is recorded. This is the relevant acceptance evidence because it tests whether the corrective action (Avoid the risk by removing the unnecessary exposure through an approved scope decision.) fixed the original concern (A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead.) at Aster Mutual, rather than relying only on a task marked complete. The affected work concerns claims processing and confidential customer records.

Incorrect Answers

A:

The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Aster Mutual, it does not demonstrate the required project outcome: The revised solution no longer includes the risky function and its scope change is recorded.

B:

The treatment record identifies transferred financial exposure and separately managed remaining risks. This evidence would be useful for another condition (A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination.) and its different action (Classify insurance as risk transfer and retain ownership of any residual project consequences.). At Aster Mutual, it does not demonstrate the required project outcome: The revised solution no longer includes the risky function and its scope change is recorded.

C:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Aster Mutual, it does not demonstrate the required project outcome: The revised solution no longer includes the risky function and its scope change is recorded.

Question 163

For Lakeview Insurance, the implementation team reports the following delivery problem: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. Which project management action BEST addresses the particular issue?

  1. Record the uncertain event as a risk with probability impact owner and planned response.
  2. Classify insurance as risk transfer and retain ownership of any residual project consequences.
  3. Log the realized delay as an issue and invoke the response plan while updating related risks.
  4. Record the positive risk and consider an opportunity response such as enhance or exploit.

Explanation

Correct Answer

D:

Record the positive risk and consider an opportunity response such as enhance or exploit. This directly addresses the reported management gap: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. For Lakeview Insurance and its broker collaboration and claim applications, a useful verification outcome is: The opportunity log names an owner action and measurable potential schedule benefit.

Incorrect Answers

A:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Lakeview Insurance is: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. That other intervention does not itself establish the required result: The opportunity log names an owner action and measurable potential schedule benefit.

B:

Classify insurance as risk transfer and retain ownership of any residual project consequences. This choice addresses another specific project condition: A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination. The actual issue at Lakeview Insurance is: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. That other intervention does not itself establish the required result: The opportunity log names an owner action and measurable potential schedule benefit.

C:

Log the realized delay as an issue and invoke the response plan while updating related risks. This choice addresses another specific project condition: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The actual issue at Lakeview Insurance is: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. That other intervention does not itself establish the required result: The opportunity log names an owner action and measurable potential schedule benefit.

Question 164

For Lakeview Insurance, the implementation team reports the following delivery problem: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The opportunity log names an owner action and measurable potential schedule benefit.
  2. The risk register tracks the possible supplier delay before a failure occurs.
  3. The treatment record identifies transferred financial exposure and separately managed remaining risks.
  4. The issue log names an owner resolution deadline and actual schedule impact.

Explanation

Correct Answer

A:

The opportunity log names an owner action and measurable potential schedule benefit. This is the relevant acceptance evidence because it tests whether the corrective action (Record the positive risk and consider an opportunity response such as enhance or exploit.) fixed the original concern (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) at Lakeview Insurance, rather than relying only on a task marked complete. The affected work concerns broker collaboration and claim applications.

Incorrect Answers

B:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Lakeview Insurance, it does not demonstrate the required project outcome: The opportunity log names an owner action and measurable potential schedule benefit.

C:

The treatment record identifies transferred financial exposure and separately managed remaining risks. This evidence would be useful for another condition (A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination.) and its different action (Classify insurance as risk transfer and retain ownership of any residual project consequences.). At Lakeview Insurance, it does not demonstrate the required project outcome: The opportunity log names an owner action and measurable potential schedule benefit.

D:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Lakeview Insurance, it does not demonstrate the required project outcome: The opportunity log names an owner action and measurable potential schedule benefit.

Question 165

At Orion Network Services, the delivery assessment finds: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. Which project management action BEST addresses the particular issue?

  1. Record the uncertain event as a risk with probability impact owner and planned response.
  2. Record the positive risk and consider an opportunity response such as enhance or exploit.
  3. Classify insurance as risk transfer and retain ownership of any residual project consequences.
  4. Log the realized delay as an issue and invoke the response plan while updating related risks.

Explanation

Correct Answer

B:

Record the positive risk and consider an opportunity response such as enhance or exploit. This directly addresses the reported management gap: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. For Orion Network Services and its subscriber applications and remote operations, a useful verification outcome is: The opportunity log names an owner action and measurable potential schedule benefit.

Incorrect Answers

A:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Orion Network Services is: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. That other intervention does not itself establish the required result: The opportunity log names an owner action and measurable potential schedule benefit.

C:

Classify insurance as risk transfer and retain ownership of any residual project consequences. This choice addresses another specific project condition: A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination. The actual issue at Orion Network Services is: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. That other intervention does not itself establish the required result: The opportunity log names an owner action and measurable potential schedule benefit.

D:

Log the realized delay as an issue and invoke the response plan while updating related risks. This choice addresses another specific project condition: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The actual issue at Orion Network Services is: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. That other intervention does not itself establish the required result: The opportunity log names an owner action and measurable potential schedule benefit.

Question 166

At Orion Network Services, the delivery assessment finds: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The treatment record identifies transferred financial exposure and separately managed remaining risks.
  2. The opportunity log names an owner action and measurable potential schedule benefit.
  3. The risk register tracks the possible supplier delay before a failure occurs.
  4. The issue log names an owner resolution deadline and actual schedule impact.

Explanation

Correct Answer

B:

The opportunity log names an owner action and measurable potential schedule benefit. This is the relevant acceptance evidence because it tests whether the corrective action (Record the positive risk and consider an opportunity response such as enhance or exploit.) fixed the original concern (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) at Orion Network Services, rather than relying only on a task marked complete. The affected work concerns subscriber applications and remote operations.

Incorrect Answers

A:

The treatment record identifies transferred financial exposure and separately managed remaining risks. This evidence would be useful for another condition (A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination.) and its different action (Classify insurance as risk transfer and retain ownership of any residual project consequences.). At Orion Network Services, it does not demonstrate the required project outcome: The opportunity log names an owner action and measurable potential schedule benefit.

C:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Orion Network Services, it does not demonstrate the required project outcome: The opportunity log names an owner action and measurable potential schedule benefit.

D:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Orion Network Services, it does not demonstrate the required project outcome: The opportunity log names an owner action and measurable potential schedule benefit.

Question 167

Horizon Energy Services is delivering an IT initiative involving remote field-worker sign-ins and operations with multiple distributed delivery teams. The team observes: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. Which project management action BEST addresses the particular issue?

  1. Log the realized delay as an issue and invoke the response plan while updating related risks.
  2. Record the positive risk and consider an opportunity response such as enhance or exploit.
  3. Record the uncertain event as a risk with probability impact owner and planned response.
  4. Classify insurance as risk transfer and retain ownership of any residual project consequences.

Explanation

Correct Answer

B:

Record the positive risk and consider an opportunity response such as enhance or exploit. This directly addresses the reported management gap: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. For Horizon Energy Services and its remote field-worker sign-ins and operations, a useful verification outcome is: The opportunity log names an owner action and measurable potential schedule benefit.

Incorrect Answers

A:

Log the realized delay as an issue and invoke the response plan while updating related risks. This choice addresses another specific project condition: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The actual issue at Horizon Energy Services is: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. That other intervention does not itself establish the required result: The opportunity log names an owner action and measurable potential schedule benefit.

C:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Horizon Energy Services is: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. That other intervention does not itself establish the required result: The opportunity log names an owner action and measurable potential schedule benefit.

D:

Classify insurance as risk transfer and retain ownership of any residual project consequences. This choice addresses another specific project condition: A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination. The actual issue at Horizon Energy Services is: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. That other intervention does not itself establish the required result: The opportunity log names an owner action and measurable potential schedule benefit.

Question 168

Horizon Energy Services is delivering an IT initiative involving remote field-worker sign-ins and operations with multiple distributed delivery teams. The team observes: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The risk register tracks the possible supplier delay before a failure occurs.
  2. The opportunity log names an owner action and measurable potential schedule benefit.
  3. The treatment record identifies transferred financial exposure and separately managed remaining risks.
  4. The issue log names an owner resolution deadline and actual schedule impact.

Explanation

Correct Answer

B:

The opportunity log names an owner action and measurable potential schedule benefit. This is the relevant acceptance evidence because it tests whether the corrective action (Record the positive risk and consider an opportunity response such as enhance or exploit.) fixed the original concern (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) at Horizon Energy Services, rather than relying only on a task marked complete. The affected work concerns remote field-worker sign-ins and operations.

Incorrect Answers

A:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Horizon Energy Services, it does not demonstrate the required project outcome: The opportunity log names an owner action and measurable potential schedule benefit.

C:

The treatment record identifies transferred financial exposure and separately managed remaining risks. This evidence would be useful for another condition (A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination.) and its different action (Classify insurance as risk transfer and retain ownership of any residual project consequences.). At Horizon Energy Services, it does not demonstrate the required project outcome: The opportunity log names an owner action and measurable potential schedule benefit.

D:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Horizon Energy Services, it does not demonstrate the required project outcome: The opportunity log names an owner action and measurable potential schedule benefit.

Question 169

Eastport Research Hospital is delivering an IT initiative involving medical research systems and directory accounts with several affected stakeholder groups. The team observes: The project relies on a single specialist and the contingency plan assumes that specialist is always available. Which project management action BEST addresses the particular issue?

  1. Perform qualitative probability-impact assessment and prioritize according to defined criteria.
  2. Log the realized delay as an issue and invoke the response plan while updating related risks.
  3. Record the uncertain event as a risk with probability impact owner and planned response.
  4. Create a fallback resource plan and reserve appropriate time or budget for the dependency.

Explanation

Correct Answer

D:

Create a fallback resource plan and reserve appropriate time or budget for the dependency. This directly addresses the reported management gap: The project relies on a single specialist and the contingency plan assumes that specialist is always available. For Eastport Research Hospital and its medical research systems and directory accounts, a useful verification outcome is: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Incorrect Answers

A:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This choice addresses another specific project condition: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The actual issue at Eastport Research Hospital is: The project relies on a single specialist and the contingency plan assumes that specialist is always available. That other intervention does not itself establish the required result: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

B:

Log the realized delay as an issue and invoke the response plan while updating related risks. This choice addresses another specific project condition: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The actual issue at Eastport Research Hospital is: The project relies on a single specialist and the contingency plan assumes that specialist is always available. That other intervention does not itself establish the required result: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

C:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Eastport Research Hospital is: The project relies on a single specialist and the contingency plan assumes that specialist is always available. That other intervention does not itself establish the required result: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

Question 170

Eastport Research Hospital is delivering an IT initiative involving medical research systems and directory accounts with several affected stakeholder groups. The team observes: The project relies on a single specialist and the contingency plan assumes that specialist is always available. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The risk matrix shows a justified rating and corresponding treatment owner.
  2. A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.
  3. The risk register tracks the possible supplier delay before a failure occurs.
  4. The issue log names an owner resolution deadline and actual schedule impact.

Explanation

Correct Answer

B:

A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable. This is the relevant acceptance evidence because it tests whether the corrective action (Create a fallback resource plan and reserve appropriate time or budget for the dependency.) fixed the original concern (The project relies on a single specialist and the contingency plan assumes that specialist is always available.) at Eastport Research Hospital, rather than relying only on a task marked complete. The affected work concerns medical research systems and directory accounts.

Incorrect Answers

A:

The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Eastport Research Hospital, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

C:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Eastport Research Hospital, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.

D:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Eastport Research Hospital, it does not demonstrate the required project outcome: A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.