McAfee-Secured Website

Exam Bundle

Exam Code: PK0-005

Exam Name CompTIA Project+

Certification Provider: CompTIA

Corresponding Certification: CompTIA Project+

CompTIA PK0-005 Bundle $44.99

100% CompTIA PK0-005 Guaranteed Success With Testking Training Materials

Get Real PK0-005 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    PK0-005 Questions & Answers

    628 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual PK0-005 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • PK0-005 Video Course

    PK0-005 Video Course

    159 Video Lectures

    PK0-005 Video Course is developed by CompTIA Professionals to help you pass the PK0-005 exam.

    Description

    This course will improve your knowledge and skills required to pass CompTIA Project+ exam.
  • Study Guide

    PK0-005 Study Guide

    682 PDF Pages

    Developed by industry experts, this 682-page guide spells out in painstaking detail all of the information you need to ace PK0-005 exam.

CompTIA Project+ (PK0-005) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    628 Questions

    $124.99
  • PK0-005 Video Course

    Video Course

    159 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    682 PDF Pages

    $29.99

CompTIA PK0-005 Practice Test 15

Question 140

At Clearwater Airport, the delivery assessment finds: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.
  2. The risk register tracks the possible supplier delay before a failure occurs.
  3. The opportunity log names an owner action and measurable potential schedule benefit.
  4. The issue log names an owner resolution deadline and actual schedule impact.

Explanation

Correct Answer

D:

The issue log names an owner resolution deadline and actual schedule impact. This is the relevant acceptance evidence because it tests whether the corrective action (Log the realized delay as an issue and invoke the response plan while updating related risks.) fixed the original concern (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) at Clearwater Airport, rather than relying only on a task marked complete. The affected work concerns operations systems and personnel access.

Incorrect Answers

A:

A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable. This evidence would be useful for another condition (The project relies on a single specialist and the contingency plan assumes that specialist is always available.) and its different action (Create a fallback resource plan and reserve appropriate time or budget for the dependency.). At Clearwater Airport, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

B:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Clearwater Airport, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

C:

The opportunity log names an owner action and measurable potential schedule benefit. This evidence would be useful for another condition (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) and its different action (Record the positive risk and consider an opportunity response such as enhance or exploit.). At Clearwater Airport, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

Question 141

Briarwood Property Group is delivering an IT initiative involving tenant portals and property records in a mixed Agile and predictive delivery environment. The team observes: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. Which project management action BEST addresses the particular issue?

  1. Create a fallback resource plan and reserve appropriate time or budget for the dependency.
  2. Record the positive risk and consider an opportunity response such as enhance or exploit.
  3. Log the realized delay as an issue and invoke the response plan while updating related risks.
  4. Record the uncertain event as a risk with probability impact owner and planned response.

Explanation

Correct Answer

C:

Log the realized delay as an issue and invoke the response plan while updating related risks. This directly addresses the reported management gap: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. For Briarwood Property Group and its tenant portals and property records, a useful verification outcome is: The issue log names an owner resolution deadline and actual schedule impact.

Incorrect Answers

A:

Create a fallback resource plan and reserve appropriate time or budget for the dependency. This choice addresses another specific project condition: The project relies on a single specialist and the contingency plan assumes that specialist is always available. The actual issue at Briarwood Property Group is: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. That other intervention does not itself establish the required result: The issue log names an owner resolution deadline and actual schedule impact.

B:

Record the positive risk and consider an opportunity response such as enhance or exploit. This choice addresses another specific project condition: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. The actual issue at Briarwood Property Group is: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. That other intervention does not itself establish the required result: The issue log names an owner resolution deadline and actual schedule impact.

D:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Briarwood Property Group is: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. That other intervention does not itself establish the required result: The issue log names an owner resolution deadline and actual schedule impact.

Question 142

Briarwood Property Group is delivering an IT initiative involving tenant portals and property records in a mixed Agile and predictive delivery environment. The team observes: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The opportunity log names an owner action and measurable potential schedule benefit.
  2. The issue log names an owner resolution deadline and actual schedule impact.
  3. A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.
  4. The risk register tracks the possible supplier delay before a failure occurs.

Explanation

Correct Answer

B:

The issue log names an owner resolution deadline and actual schedule impact. This is the relevant acceptance evidence because it tests whether the corrective action (Log the realized delay as an issue and invoke the response plan while updating related risks.) fixed the original concern (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) at Briarwood Property Group, rather than relying only on a task marked complete. The affected work concerns tenant portals and property records.

Incorrect Answers

A:

The opportunity log names an owner action and measurable potential schedule benefit. This evidence would be useful for another condition (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) and its different action (Record the positive risk and consider an opportunity response such as enhance or exploit.). At Briarwood Property Group, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

C:

A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable. This evidence would be useful for another condition (The project relies on a single specialist and the contingency plan assumes that specialist is always available.) and its different action (Create a fallback resource plan and reserve appropriate time or budget for the dependency.). At Briarwood Property Group, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

D:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Briarwood Property Group, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

Question 143

For Oak River Energy, the project steering committee reports the following delivery problem: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. Which project management action BEST addresses the particular issue?

  1. Record the positive risk and consider an opportunity response such as enhance or exploit.
  2. Record the uncertain event as a risk with probability impact owner and planned response.
  3. Create a fallback resource plan and reserve appropriate time or budget for the dependency.
  4. Log the realized delay as an issue and invoke the response plan while updating related risks.

Explanation

Correct Answer

D:

Log the realized delay as an issue and invoke the response plan while updating related risks. This directly addresses the reported management gap: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. For Oak River Energy and its field operations and service infrastructure, a useful verification outcome is: The issue log names an owner resolution deadline and actual schedule impact.

Incorrect Answers

A:

Record the positive risk and consider an opportunity response such as enhance or exploit. This choice addresses another specific project condition: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. The actual issue at Oak River Energy is: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. That other intervention does not itself establish the required result: The issue log names an owner resolution deadline and actual schedule impact.

B:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Oak River Energy is: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. That other intervention does not itself establish the required result: The issue log names an owner resolution deadline and actual schedule impact.

C:

Create a fallback resource plan and reserve appropriate time or budget for the dependency. This choice addresses another specific project condition: The project relies on a single specialist and the contingency plan assumes that specialist is always available. The actual issue at Oak River Energy is: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. That other intervention does not itself establish the required result: The issue log names an owner resolution deadline and actual schedule impact.

Question 144

For Oak River Energy, the project steering committee reports the following delivery problem: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.
  2. The issue log names an owner resolution deadline and actual schedule impact.
  3. The risk register tracks the possible supplier delay before a failure occurs.
  4. The opportunity log names an owner action and measurable potential schedule benefit.

Explanation

Correct Answer

B:

The issue log names an owner resolution deadline and actual schedule impact. This is the relevant acceptance evidence because it tests whether the corrective action (Log the realized delay as an issue and invoke the response plan while updating related risks.) fixed the original concern (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) at Oak River Energy, rather than relying only on a task marked complete. The affected work concerns field operations and service infrastructure.

Incorrect Answers

A:

A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable. This evidence would be useful for another condition (The project relies on a single specialist and the contingency plan assumes that specialist is always available.) and its different action (Create a fallback resource plan and reserve appropriate time or budget for the dependency.). At Oak River Energy, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

C:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Oak River Energy, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

D:

The opportunity log names an owner action and measurable potential schedule benefit. This evidence would be useful for another condition (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) and its different action (Record the positive risk and consider an opportunity response such as enhance or exploit.). At Oak River Energy, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

Question 145

For Stonehaven Logistics, the project steering committee reports the following delivery problem: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. Which project management action BEST addresses the particular issue?

  1. Perform qualitative probability-impact assessment and prioritize according to defined criteria.
  2. Classify insurance as risk transfer and retain ownership of any residual project consequences.
  3. Avoid the risk by removing the unnecessary exposure through an approved scope decision.
  4. Record the uncertain event as a risk with probability impact owner and planned response.

Explanation

Correct Answer

A:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This directly addresses the reported management gap: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. For Stonehaven Logistics and its warehouse scheduling and shipping records, a useful verification outcome is: The risk matrix shows a justified rating and corresponding treatment owner.

Incorrect Answers

B:

Classify insurance as risk transfer and retain ownership of any residual project consequences. This choice addresses another specific project condition: A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination. The actual issue at Stonehaven Logistics is: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. That other intervention does not itself establish the required result: The risk matrix shows a justified rating and corresponding treatment owner.

C:

Avoid the risk by removing the unnecessary exposure through an approved scope decision. This choice addresses another specific project condition: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. The actual issue at Stonehaven Logistics is: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. That other intervention does not itself establish the required result: The risk matrix shows a justified rating and corresponding treatment owner.

D:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Stonehaven Logistics is: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. That other intervention does not itself establish the required result: The risk matrix shows a justified rating and corresponding treatment owner.

Question 146

For Stonehaven Logistics, the project steering committee reports the following delivery problem: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The revised solution no longer includes the risky function and its scope change is recorded.
  2. The risk register tracks the possible supplier delay before a failure occurs.
  3. The treatment record identifies transferred financial exposure and separately managed remaining risks.
  4. The risk matrix shows a justified rating and corresponding treatment owner.

Explanation

Correct Answer

D:

The risk matrix shows a justified rating and corresponding treatment owner. This is the relevant acceptance evidence because it tests whether the corrective action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.) fixed the original concern (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) at Stonehaven Logistics, rather than relying only on a task marked complete. The affected work concerns warehouse scheduling and shipping records.

Incorrect Answers

A:

The revised solution no longer includes the risky function and its scope change is recorded. This evidence would be useful for another condition (A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead.) and its different action (Avoid the risk by removing the unnecessary exposure through an approved scope decision.). At Stonehaven Logistics, it does not demonstrate the required project outcome: The risk matrix shows a justified rating and corresponding treatment owner.

B:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Stonehaven Logistics, it does not demonstrate the required project outcome: The risk matrix shows a justified rating and corresponding treatment owner.

C:

The treatment record identifies transferred financial exposure and separately managed remaining risks. This evidence would be useful for another condition (A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination.) and its different action (Classify insurance as risk transfer and retain ownership of any residual project consequences.). At Stonehaven Logistics, it does not demonstrate the required project outcome: The risk matrix shows a justified rating and corresponding treatment owner.

Question 147

At Sapphire Data Systems, the delivery assessment finds: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. Which project management action BEST addresses the particular issue?

  1. Perform qualitative probability-impact assessment and prioritize according to defined criteria.
  2. Classify insurance as risk transfer and retain ownership of any residual project consequences.
  3. Record the uncertain event as a risk with probability impact owner and planned response.
  4. Avoid the risk by removing the unnecessary exposure through an approved scope decision.

Explanation

Correct Answer

A:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This directly addresses the reported management gap: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. For Sapphire Data Systems and its customer tenants and managed cloud services, a useful verification outcome is: The risk matrix shows a justified rating and corresponding treatment owner.

Incorrect Answers

B:

Classify insurance as risk transfer and retain ownership of any residual project consequences. This choice addresses another specific project condition: A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination. The actual issue at Sapphire Data Systems is: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. That other intervention does not itself establish the required result: The risk matrix shows a justified rating and corresponding treatment owner.

C:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Sapphire Data Systems is: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. That other intervention does not itself establish the required result: The risk matrix shows a justified rating and corresponding treatment owner.

D:

Avoid the risk by removing the unnecessary exposure through an approved scope decision. This choice addresses another specific project condition: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. The actual issue at Sapphire Data Systems is: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. That other intervention does not itself establish the required result: The risk matrix shows a justified rating and corresponding treatment owner.

Question 148

At Sapphire Data Systems, the delivery assessment finds: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The treatment record identifies transferred financial exposure and separately managed remaining risks.
  2. The revised solution no longer includes the risky function and its scope change is recorded.
  3. The risk matrix shows a justified rating and corresponding treatment owner.
  4. The risk register tracks the possible supplier delay before a failure occurs.

Explanation

Correct Answer

C:

The risk matrix shows a justified rating and corresponding treatment owner. This is the relevant acceptance evidence because it tests whether the corrective action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.) fixed the original concern (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) at Sapphire Data Systems, rather than relying only on a task marked complete. The affected work concerns customer tenants and managed cloud services.

Incorrect Answers

A:

The treatment record identifies transferred financial exposure and separately managed remaining risks. This evidence would be useful for another condition (A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination.) and its different action (Classify insurance as risk transfer and retain ownership of any residual project consequences.). At Sapphire Data Systems, it does not demonstrate the required project outcome: The risk matrix shows a justified rating and corresponding treatment owner.

B:

The revised solution no longer includes the risky function and its scope change is recorded. This evidence would be useful for another condition (A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead.) and its different action (Avoid the risk by removing the unnecessary exposure through an approved scope decision.). At Sapphire Data Systems, it does not demonstrate the required project outcome: The risk matrix shows a justified rating and corresponding treatment owner.

D:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Sapphire Data Systems, it does not demonstrate the required project outcome: The risk matrix shows a justified rating and corresponding treatment owner.

Question 149

Blue Haven Media is delivering an IT initiative involving creative files and production workspaces with multiple distributed delivery teams. The team observes: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. Which project management action BEST addresses the particular issue?

  1. Avoid the risk by removing the unnecessary exposure through an approved scope decision.
  2. Record the uncertain event as a risk with probability impact owner and planned response.
  3. Perform qualitative probability-impact assessment and prioritize according to defined criteria.
  4. Classify insurance as risk transfer and retain ownership of any residual project consequences.

Explanation

Correct Answer

C:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This directly addresses the reported management gap: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. For Blue Haven Media and its creative files and production workspaces, a useful verification outcome is: The risk matrix shows a justified rating and corresponding treatment owner.

Incorrect Answers

A:

Avoid the risk by removing the unnecessary exposure through an approved scope decision. This choice addresses another specific project condition: A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead. The actual issue at Blue Haven Media is: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. That other intervention does not itself establish the required result: The risk matrix shows a justified rating and corresponding treatment owner.

B:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Blue Haven Media is: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. That other intervention does not itself establish the required result: The risk matrix shows a justified rating and corresponding treatment owner.

D:

Classify insurance as risk transfer and retain ownership of any residual project consequences. This choice addresses another specific project condition: A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination. The actual issue at Blue Haven Media is: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. That other intervention does not itself establish the required result: The risk matrix shows a justified rating and corresponding treatment owner.

Question 150

Blue Haven Media is delivering an IT initiative involving creative files and production workspaces with multiple distributed delivery teams. The team observes: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The revised solution no longer includes the risky function and its scope change is recorded.
  2. The risk matrix shows a justified rating and corresponding treatment owner.
  3. The risk register tracks the possible supplier delay before a failure occurs.
  4. The treatment record identifies transferred financial exposure and separately managed remaining risks.

Explanation

Correct Answer

B:

The risk matrix shows a justified rating and corresponding treatment owner. This is the relevant acceptance evidence because it tests whether the corrective action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.) fixed the original concern (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) at Blue Haven Media, rather than relying only on a task marked complete. The affected work concerns creative files and production workspaces.

Incorrect Answers

A:

The revised solution no longer includes the risky function and its scope change is recorded. This evidence would be useful for another condition (A risky technical feature can be eliminated entirely without harming objectives but the team funds controls to tolerate it instead.) and its different action (Avoid the risk by removing the unnecessary exposure through an approved scope decision.). At Blue Haven Media, it does not demonstrate the required project outcome: The risk matrix shows a justified rating and corresponding treatment owner.

C:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Blue Haven Media, it does not demonstrate the required project outcome: The risk matrix shows a justified rating and corresponding treatment owner.

D:

The treatment record identifies transferred financial exposure and separately managed remaining risks. This evidence would be useful for another condition (A one-off network cutover has a credible threat of significant loss and the vendor offers an insurance contract but management calls it risk elimination.) and its different action (Classify insurance as risk transfer and retain ownership of any residual project consequences.). At Blue Haven Media, it does not demonstrate the required project outcome: The risk matrix shows a justified rating and corresponding treatment owner.