Question 140
At Clearwater Airport, the delivery assessment finds: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The issue log names an owner resolution deadline and actual schedule impact. This is the relevant acceptance evidence because it tests whether the corrective action (Log the realized delay as an issue and invoke the response plan while updating related risks.) fixed the original concern (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) at Clearwater Airport, rather than relying only on a task marked complete. The affected work concerns operations systems and personnel access.
Incorrect Answers
A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable. This evidence would be useful for another condition (The project relies on a single specialist and the contingency plan assumes that specialist is always available.) and its different action (Create a fallback resource plan and reserve appropriate time or budget for the dependency.). At Clearwater Airport, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.
The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Clearwater Airport, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.
The opportunity log names an owner action and measurable potential schedule benefit. This evidence would be useful for another condition (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) and its different action (Record the positive risk and consider an opportunity response such as enhance or exploit.). At Clearwater Airport, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.