McAfee-Secured Website

Exam Bundle

Exam Code: PK0-005

Exam Name CompTIA Project+

Certification Provider: CompTIA

Corresponding Certification: CompTIA Project+

CompTIA PK0-005 Bundle $44.99

100% CompTIA PK0-005 Guaranteed Success With Testking Training Materials

Get Real PK0-005 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    PK0-005 Questions & Answers

    628 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual PK0-005 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • PK0-005 Video Course

    PK0-005 Video Course

    159 Video Lectures

    PK0-005 Video Course is developed by CompTIA Professionals to help you pass the PK0-005 exam.

    Description

    This course will improve your knowledge and skills required to pass CompTIA Project+ exam.
  • Study Guide

    PK0-005 Study Guide

    682 PDF Pages

    Developed by industry experts, this 682-page guide spells out in painstaking detail all of the information you need to ace PK0-005 exam.

CompTIA Project+ (PK0-005) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    628 Questions

    $124.99
  • PK0-005 Video Course

    Video Course

    159 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    682 PDF Pages

    $29.99

CompTIA PK0-005 Practice Test 14

Question 130

During an IT infrastructure modernization at Ridgeview Finance, the project coordinator identifies an issue: Two managers disagree about who can approve additional contract cost so engineers implement the change based on an informal meeting. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The decision record identifies an authorized approver and the cost effect before commitment.
  2. The change log links the request to an impact analysis and an authorized outcome.
  3. The controlled log has a single request identifier and one decision trail for the proposed feature.
  4. The change request has an approval status and authorized deployment reference before release.

Explanation

Correct Answer

A:

The decision record identifies an authorized approver and the cost effect before commitment. This is the relevant acceptance evidence because it tests whether the corrective action (Apply the documented decision authority and escalate to the responsible sponsor or board.) fixed the original concern (Two managers disagree about who can approve additional contract cost so engineers implement the change based on an informal meeting.) at Ridgeview Finance, rather than relying only on a task marked complete. The affected work concerns financial reporting and customer portals.

Incorrect Answers

B:

The change log links the request to an impact analysis and an authorized outcome. This evidence would be useful for another condition (A stakeholder requests a new dashboard after scope approval and developers implement it without assessing the schedule impact.) and its different action (Log a formal change request and assess scope cost schedule risk and resource impact before decision.). At Ridgeview Finance, it does not demonstrate the required project outcome: The decision record identifies an authorized approver and the cost effect before commitment.

C:

The controlled log has a single request identifier and one decision trail for the proposed feature. This evidence would be useful for another condition (A project lead receives the same feature change by email and chat and records two approvals for one modification.) and its different action (Consolidate duplicate submissions into one identifiable change record and maintain its history.). At Ridgeview Finance, it does not demonstrate the required project outcome: The decision record identifies an authorized approver and the cost effect before commitment.

D:

The change request has an approval status and authorized deployment reference before release. This evidence would be useful for another condition (An engineer deploys a schedule-changing feature because the change board met but no actual decision was recorded.) and its different action (Wait for and document the authorized change-control board decision before implementing.). At Ridgeview Finance, it does not demonstrate the required project outcome: The decision record identifies an authorized approver and the cost effect before commitment.

Question 131

A project governance review at Northshore Hospitality identifies this problem during a requirements discovery workshop: Two managers disagree about who can approve additional contract cost so engineers implement the change based on an informal meeting. Which project management action BEST addresses the particular issue?

  1. Apply the documented decision authority and escalate to the responsible sponsor or board.
  2. Consolidate duplicate submissions into one identifiable change record and maintain its history.
  3. Log a formal change request and assess scope cost schedule risk and resource impact before decision.
  4. Wait for and document the authorized change-control board decision before implementing.

Explanation

Correct Answer

A:

Apply the documented decision authority and escalate to the responsible sponsor or board. This directly addresses the reported management gap: Two managers disagree about who can approve additional contract cost so engineers implement the change based on an informal meeting. For Northshore Hospitality and its reservation applications and staff devices, a useful verification outcome is: The decision record identifies an authorized approver and the cost effect before commitment.

Incorrect Answers

B:

Consolidate duplicate submissions into one identifiable change record and maintain its history. This choice addresses another specific project condition: A project lead receives the same feature change by email and chat and records two approvals for one modification. The actual issue at Northshore Hospitality is: Two managers disagree about who can approve additional contract cost so engineers implement the change based on an informal meeting. That other intervention does not itself establish the required result: The decision record identifies an authorized approver and the cost effect before commitment.

C:

Log a formal change request and assess scope cost schedule risk and resource impact before decision. This choice addresses another specific project condition: A stakeholder requests a new dashboard after scope approval and developers implement it without assessing the schedule impact. The actual issue at Northshore Hospitality is: Two managers disagree about who can approve additional contract cost so engineers implement the change based on an informal meeting. That other intervention does not itself establish the required result: The decision record identifies an authorized approver and the cost effect before commitment.

D:

Wait for and document the authorized change-control board decision before implementing. This choice addresses another specific project condition: An engineer deploys a schedule-changing feature because the change board met but no actual decision was recorded. The actual issue at Northshore Hospitality is: Two managers disagree about who can approve additional contract cost so engineers implement the change based on an informal meeting. That other intervention does not itself establish the required result: The decision record identifies an authorized approver and the cost effect before commitment.

Question 132

A project governance review at Northshore Hospitality identifies this problem during a requirements discovery workshop: Two managers disagree about who can approve additional contract cost so engineers implement the change based on an informal meeting. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The change request has an approval status and authorized deployment reference before release.
  2. The change log links the request to an impact analysis and an authorized outcome.
  3. The controlled log has a single request identifier and one decision trail for the proposed feature.
  4. The decision record identifies an authorized approver and the cost effect before commitment.

Explanation

Correct Answer

D:

The decision record identifies an authorized approver and the cost effect before commitment. This is the relevant acceptance evidence because it tests whether the corrective action (Apply the documented decision authority and escalate to the responsible sponsor or board.) fixed the original concern (Two managers disagree about who can approve additional contract cost so engineers implement the change based on an informal meeting.) at Northshore Hospitality, rather than relying only on a task marked complete. The affected work concerns reservation applications and staff devices.

Incorrect Answers

A:

The change request has an approval status and authorized deployment reference before release. This evidence would be useful for another condition (An engineer deploys a schedule-changing feature because the change board met but no actual decision was recorded.) and its different action (Wait for and document the authorized change-control board decision before implementing.). At Northshore Hospitality, it does not demonstrate the required project outcome: The decision record identifies an authorized approver and the cost effect before commitment.

B:

The change log links the request to an impact analysis and an authorized outcome. This evidence would be useful for another condition (A stakeholder requests a new dashboard after scope approval and developers implement it without assessing the schedule impact.) and its different action (Log a formal change request and assess scope cost schedule risk and resource impact before decision.). At Northshore Hospitality, it does not demonstrate the required project outcome: The decision record identifies an authorized approver and the cost effect before commitment.

C:

The controlled log has a single request identifier and one decision trail for the proposed feature. This evidence would be useful for another condition (A project lead receives the same feature change by email and chat and records two approvals for one modification.) and its different action (Consolidate duplicate submissions into one identifiable change record and maintain its history.). At Northshore Hospitality, it does not demonstrate the required project outcome: The decision record identifies an authorized approver and the cost effect before commitment.

Question 133

Greenpeak Civic Services is delivering an IT initiative involving citizen services and digital identity with several affected stakeholder groups. The team observes: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. Which project management action BEST addresses the particular issue?

  1. Record the positive risk and consider an opportunity response such as enhance or exploit.
  2. Perform qualitative probability-impact assessment and prioritize according to defined criteria.
  3. Record the uncertain event as a risk with probability impact owner and planned response.
  4. Log the realized delay as an issue and invoke the response plan while updating related risks.

Explanation

Correct Answer

C:

Record the uncertain event as a risk with probability impact owner and planned response. This directly addresses the reported management gap: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. For Greenpeak Civic Services and its citizen services and digital identity, a useful verification outcome is: The risk register tracks the possible supplier delay before a failure occurs.

Incorrect Answers

A:

Record the positive risk and consider an opportunity response such as enhance or exploit. This choice addresses another specific project condition: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. The actual issue at Greenpeak Civic Services is: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. That other intervention does not itself establish the required result: The risk register tracks the possible supplier delay before a failure occurs.

B:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This choice addresses another specific project condition: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The actual issue at Greenpeak Civic Services is: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. That other intervention does not itself establish the required result: The risk register tracks the possible supplier delay before a failure occurs.

D:

Log the realized delay as an issue and invoke the response plan while updating related risks. This choice addresses another specific project condition: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The actual issue at Greenpeak Civic Services is: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. That other intervention does not itself establish the required result: The risk register tracks the possible supplier delay before a failure occurs.

Question 134

Greenpeak Civic Services is delivering an IT initiative involving citizen services and digital identity with several affected stakeholder groups. The team observes: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The opportunity log names an owner action and measurable potential schedule benefit.
  2. The issue log names an owner resolution deadline and actual schedule impact.
  3. The risk matrix shows a justified rating and corresponding treatment owner.
  4. The risk register tracks the possible supplier delay before a failure occurs.

Explanation

Correct Answer

D:

The risk register tracks the possible supplier delay before a failure occurs. This is the relevant acceptance evidence because it tests whether the corrective action (Record the uncertain event as a risk with probability impact owner and planned response.) fixed the original concern (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) at Greenpeak Civic Services, rather than relying only on a task marked complete. The affected work concerns citizen services and digital identity.

Incorrect Answers

A:

The opportunity log names an owner action and measurable potential schedule benefit. This evidence would be useful for another condition (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) and its different action (Record the positive risk and consider an opportunity response such as enhance or exploit.). At Greenpeak Civic Services, it does not demonstrate the required project outcome: The risk register tracks the possible supplier delay before a failure occurs.

B:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Greenpeak Civic Services, it does not demonstrate the required project outcome: The risk register tracks the possible supplier delay before a failure occurs.

C:

The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Greenpeak Civic Services, it does not demonstrate the required project outcome: The risk register tracks the possible supplier delay before a failure occurs.

Question 135

For Atlas Scientific, the project governance analyst reports the following delivery problem: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. Which project management action BEST addresses the particular issue?

  1. Perform qualitative probability-impact assessment and prioritize according to defined criteria.
  2. Record the positive risk and consider an opportunity response such as enhance or exploit.
  3. Record the uncertain event as a risk with probability impact owner and planned response.
  4. Log the realized delay as an issue and invoke the response plan while updating related risks.

Explanation

Correct Answer

C:

Record the uncertain event as a risk with probability impact owner and planned response. This directly addresses the reported management gap: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. For Atlas Scientific and its lab collaboration and cloud-hosted research, a useful verification outcome is: The risk register tracks the possible supplier delay before a failure occurs.

Incorrect Answers

A:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This choice addresses another specific project condition: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The actual issue at Atlas Scientific is: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. That other intervention does not itself establish the required result: The risk register tracks the possible supplier delay before a failure occurs.

B:

Record the positive risk and consider an opportunity response such as enhance or exploit. This choice addresses another specific project condition: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. The actual issue at Atlas Scientific is: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. That other intervention does not itself establish the required result: The risk register tracks the possible supplier delay before a failure occurs.

D:

Log the realized delay as an issue and invoke the response plan while updating related risks. This choice addresses another specific project condition: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The actual issue at Atlas Scientific is: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. That other intervention does not itself establish the required result: The risk register tracks the possible supplier delay before a failure occurs.

Question 136

For Atlas Scientific, the project governance analyst reports the following delivery problem: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The risk matrix shows a justified rating and corresponding treatment owner.
  2. The issue log names an owner resolution deadline and actual schedule impact.
  3. The opportunity log names an owner action and measurable potential schedule benefit.
  4. The risk register tracks the possible supplier delay before a failure occurs.

Explanation

Correct Answer

D:

The risk register tracks the possible supplier delay before a failure occurs. This is the relevant acceptance evidence because it tests whether the corrective action (Record the uncertain event as a risk with probability impact owner and planned response.) fixed the original concern (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) at Atlas Scientific, rather than relying only on a task marked complete. The affected work concerns lab collaboration and cloud-hosted research.

Incorrect Answers

A:

The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Atlas Scientific, it does not demonstrate the required project outcome: The risk register tracks the possible supplier delay before a failure occurs.

B:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Atlas Scientific, it does not demonstrate the required project outcome: The risk register tracks the possible supplier delay before a failure occurs.

C:

The opportunity log names an owner action and measurable potential schedule benefit. This evidence would be useful for another condition (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) and its different action (Record the positive risk and consider an opportunity response such as enhance or exploit.). At Atlas Scientific, it does not demonstrate the required project outcome: The risk register tracks the possible supplier delay before a failure occurs.

Question 137

At Boreal Foods, the delivery assessment finds: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. Which project management action BEST addresses the particular issue?

  1. Perform qualitative probability-impact assessment and prioritize according to defined criteria.
  2. Record the positive risk and consider an opportunity response such as enhance or exploit.
  3. Log the realized delay as an issue and invoke the response plan while updating related risks.
  4. Record the uncertain event as a risk with probability impact owner and planned response.

Explanation

Correct Answer

D:

Record the uncertain event as a risk with probability impact owner and planned response. This directly addresses the reported management gap: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. For Boreal Foods and its production systems and supplier relationships, a useful verification outcome is: The risk register tracks the possible supplier delay before a failure occurs.

Incorrect Answers

A:

Perform qualitative probability-impact assessment and prioritize according to defined criteria. This choice addresses another specific project condition: A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact. The actual issue at Boreal Foods is: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. That other intervention does not itself establish the required result: The risk register tracks the possible supplier delay before a failure occurs.

B:

Record the positive risk and consider an opportunity response such as enhance or exploit. This choice addresses another specific project condition: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. The actual issue at Boreal Foods is: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. That other intervention does not itself establish the required result: The risk register tracks the possible supplier delay before a failure occurs.

C:

Log the realized delay as an issue and invoke the response plan while updating related risks. This choice addresses another specific project condition: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The actual issue at Boreal Foods is: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. That other intervention does not itself establish the required result: The risk register tracks the possible supplier delay before a failure occurs.

Question 138

At Boreal Foods, the delivery assessment finds: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The opportunity log names an owner action and measurable potential schedule benefit.
  2. The risk register tracks the possible supplier delay before a failure occurs.
  3. The issue log names an owner resolution deadline and actual schedule impact.
  4. The risk matrix shows a justified rating and corresponding treatment owner.

Explanation

Correct Answer

B:

The risk register tracks the possible supplier delay before a failure occurs. This is the relevant acceptance evidence because it tests whether the corrective action (Record the uncertain event as a risk with probability impact owner and planned response.) fixed the original concern (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) at Boreal Foods, rather than relying only on a task marked complete. The affected work concerns production systems and supplier relationships.

Incorrect Answers

A:

The opportunity log names an owner action and measurable potential schedule benefit. This evidence would be useful for another condition (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) and its different action (Record the positive risk and consider an opportunity response such as enhance or exploit.). At Boreal Foods, it does not demonstrate the required project outcome: The risk register tracks the possible supplier delay before a failure occurs.

C:

The issue log names an owner resolution deadline and actual schedule impact. This evidence would be useful for another condition (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) and its different action (Log the realized delay as an issue and invoke the response plan while updating related risks.). At Boreal Foods, it does not demonstrate the required project outcome: The risk register tracks the possible supplier delay before a failure occurs.

D:

The risk matrix shows a justified rating and corresponding treatment owner. This evidence would be useful for another condition (A security risk has high severity but risk owners select mitigation actions without identifying probability or business impact.) and its different action (Perform qualitative probability-impact assessment and prioritize according to defined criteria.). At Boreal Foods, it does not demonstrate the required project outcome: The risk register tracks the possible supplier delay before a failure occurs.

Question 139

At Clearwater Airport, the delivery assessment finds: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. Which project management action BEST addresses the particular issue?

  1. Record the uncertain event as a risk with probability impact owner and planned response.
  2. Create a fallback resource plan and reserve appropriate time or budget for the dependency.
  3. Record the positive risk and consider an opportunity response such as enhance or exploit.
  4. Log the realized delay as an issue and invoke the response plan while updating related risks.

Explanation

Correct Answer

D:

Log the realized delay as an issue and invoke the response plan while updating related risks. This directly addresses the reported management gap: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. For Clearwater Airport and its operations systems and personnel access, a useful verification outcome is: The issue log names an owner resolution deadline and actual schedule impact.

Incorrect Answers

A:

Record the uncertain event as a risk with probability impact owner and planned response. This choice addresses another specific project condition: The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred. The actual issue at Clearwater Airport is: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. That other intervention does not itself establish the required result: The issue log names an owner resolution deadline and actual schedule impact.

B:

Create a fallback resource plan and reserve appropriate time or budget for the dependency. This choice addresses another specific project condition: The project relies on a single specialist and the contingency plan assumes that specialist is always available. The actual issue at Clearwater Airport is: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. That other intervention does not itself establish the required result: The issue log names an owner resolution deadline and actual schedule impact.

C:

Record the positive risk and consider an opportunity response such as enhance or exploit. This choice addresses another specific project condition: An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat. The actual issue at Clearwater Airport is: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. That other intervention does not itself establish the required result: The issue log names an owner resolution deadline and actual schedule impact.

Question 140

At Clearwater Airport, the delivery assessment finds: A supplier has already missed a delivery and the PM only adds it to the list of potential future risks. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable.
  2. The risk register tracks the possible supplier delay before a failure occurs.
  3. The opportunity log names an owner action and measurable potential schedule benefit.
  4. The issue log names an owner resolution deadline and actual schedule impact.

Explanation

Correct Answer

D:

The issue log names an owner resolution deadline and actual schedule impact. This is the relevant acceptance evidence because it tests whether the corrective action (Log the realized delay as an issue and invoke the response plan while updating related risks.) fixed the original concern (A supplier has already missed a delivery and the PM only adds it to the list of potential future risks.) at Clearwater Airport, rather than relying only on a task marked complete. The affected work concerns operations systems and personnel access.

Incorrect Answers

A:

A rehearsal shows another approved resource can complete the critical task if the specialist is unavailable. This evidence would be useful for another condition (The project relies on a single specialist and the contingency plan assumes that specialist is always available.) and its different action (Create a fallback resource plan and reserve appropriate time or budget for the dependency.). At Clearwater Airport, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

B:

The risk register tracks the possible supplier delay before a failure occurs. This evidence would be useful for another condition (The team has an unverified chance of a supplier delay next month and enters it as a defect that already occurred.) and its different action (Record the uncertain event as a risk with probability impact owner and planned response.). At Clearwater Airport, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.

C:

The opportunity log names an owner action and measurable potential schedule benefit. This evidence would be useful for another condition (An optional capacity improvement might significantly accelerate delivery but the team manages every opportunity as a negative threat.) and its different action (Record the positive risk and consider an opportunity response such as enhance or exploit.). At Clearwater Airport, it does not demonstrate the required project outcome: The issue log names an owner resolution deadline and actual schedule impact.