McAfee-Secured Website

Exam Bundle

Exam Code: OGEA-103

Exam Name TOGAF Enterprise Architecture Combined Part 1 and Part 2

Certification Provider: The Open Group

Corresponding Certification: TOGAF Enterprise Architecture Practitioner

The Open Group OGEA-103 Bundle $19.99

100% The Open Group OGEA-103 Guaranteed Success With Testking Training Materials

Get Real OGEA-103 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    OGEA-103 Questions & Answers

    183 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual OGEA-103 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • Study Guide

    OGEA-103 Study Guide

    488 PDF Pages

    Developed by industry experts, this 488-page guide spells out in painstaking detail all of the information you need to ace OGEA-103 exam.

TOGAF Enterprise Architecture Combined Part 1 and Part 2 (OGEA-103) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $154.98
Bundle Price: $134.99

Purchase Individually

  • Questions & Answers

    Questions & Answers

    183 Questions

    $124.99
  • Study Guide

    Study Guide

    488 PDF Pages

    $29.99

The Open Group OGEA-103 Practice Test 8

Question 70

A new claims process has no distinction between the customer, claims adjuster and approval system roles. Which area of architecture work best describes the response needed in this situation?

  1. Business scenario requirements
  2. Business scenario actors
  3. Principles implications
  4. Alternatives and trade-offs

Explanation

Correct Answer

B:

Identify relevant human and system actors when building a business scenario. The practical check is whether the scenario models actors' responsibilities and interactions consistently.

Incorrect Answers

A:

Business scenario requirements is concerned with derive requirements from a tested business scenario before proposing solutions. The requirement in this case is different: identifying relevant human and system actors when building a business scenario.

C:

Principles implications is concerned with documenting implications that describe consequences and requirements of adopting the principle. The requirement in this case is different: identifying relevant human and system actors when building a business scenario.

D:

Alternatives and trade-offs is concerned with comparing architecture alternatives using business and technical trade-off criteria. The requirement in this case is different: identifying relevant human and system actors when building a business scenario.

Question 71

Executive sponsors approve a vision without consulting customer operations who must support it. Which architecture activity or focus best matches the deficiency or design purpose described here?

  1. Phase E transition states
  2. ADM phase relationships
  3. Phase A stakeholders
  4. Phase D security infrastructure

Explanation

Correct Answer

C:

Identify stakeholders, concerns and communication needs during Phase A. The practical check is whether stakeholder map and review feedback demonstrate operational concerns were represented.

Incorrect Answers

A:

Phase E transition states is concerned with identifying feasible Transition Architectures in Phase E. The requirement in this case is different: identifying stakeholders, concerns and communication needs during Phase A.

B:

ADM phase relationships is concerned with treat Requirements Management as continuous across all ADM phases. The requirement in this case is different: identifying stakeholders, concerns and communication needs during Phase A.

D:

Phase D security infrastructure is concerned with incorporate required security services in Technology Architecture. The requirement in this case is different: identifying stakeholders, concerns and communication needs during Phase A.

Question 72

Teams model projects inconsistently and cannot connect goals, capabilities, data or application components. Which area of architecture work best describes the response needed in this situation?

  1. Implementation migration plan
  2. Content metamodel
  3. Solution building block content
  4. Reference library

Explanation

Correct Answer

B:

Use a tailored Enterprise Metamodel defining architecture entities and relationships. The practical check is whether content checks reveal consistent links between goals, capabilities, data and services.

Incorrect Answers

A:

Implementation migration plan is concerned with producing the Implementation and Migration Plan as an executable planning deliverable. The requirement in this case is different: using a tailored Enterprise Metamodel defining architecture entities and relationships.

C:

Solution building block content is concerned with describing concrete products and components as Solution Building Blocks. The requirement in this case is different: using a tailored Enterprise Metamodel defining architecture entities and relationships.

D:

Reference library is concerned with using a Reference Library for reusable external and generalized guidance. The requirement in this case is different: using a tailored Enterprise Metamodel defining architecture entities and relationships.

Question 73

A product team ships every two weeks but architecture review is possible only as one annual monolithic approval. An architect must classify the work correctly. Which activity or focus fits the facts most closely?

  1. Architecture level project
  2. Architecture landscape granularity
  3. Architecture level portfolio
  4. Digital agile alignment

Explanation

Correct Answer

D:

Integrate iterative architecture decision-making with Agile delivery cadence. The practical check is whether release controls receive timely architecture guidance and explicit exceptions.

Incorrect Answers

A:

Architecture level project is concerned with using project-level architecture to guide a defined change initiative. The requirement in this case is different: integrating iterative architecture decision-making with Agile delivery cadence.

B:

Architecture landscape granularity is concerned with organizing the Architecture Landscape into useful levels of granularity. The requirement in this case is different: integrating iterative architecture decision-making with Agile delivery cadence.

C:

Architecture level portfolio is concerned with applying portfolio-level architecture to align related change investments. The requirement in this case is different: integrating iterative architecture decision-making with Agile delivery cadence.

Question 74

A security exception is approved by a junior architect who cannot accept enterprise regulatory risk. An architect must classify the work correctly. Which activity or focus fits the facts most closely?

  1. Architecture contract governance
  2. Governance repository
  3. Governance risk ownership
  4. Governance decision appeal

Explanation

Correct Answer

C:

Require residual risk acceptance by appropriate accountable business authority. The practical check is whether approval records identify an authorized owner and boundaries of delegated authority.

Incorrect Answers

A:

Architecture contract governance is concerned with governing supplier obligations through an Architecture Contract. The requirement in this case is different: requiring residual risk acceptance by appropriate accountable business authority.

B:

Governance repository is concerned with maintaining an Architecture Governance Log and relevant repository evidence. The requirement in this case is different: requiring residual risk acceptance by appropriate accountable business authority.

D:

Governance decision appeal is concerned with establishing transparent decision appeal and escalation procedures. The requirement in this case is different: requiring residual risk acceptance by appropriate accountable business authority.

Question 75

An insurer has duplicated claims services and inconsistent interactions between customer portals and core systems. Which architecture focus or activity most directly addresses the stated need, rather than a merely adjacent issue?

  1. Architecture iteration
  2. Architecture framework
  3. Application architecture domain
  4. Architecture principles

Explanation

Correct Answer

C:

Model Application Architecture covering application components, services and interactions. The practical check is whether application communication diagrams show the source and destination of every required claims exchange.

Incorrect Answers

A:

Architecture iteration is concerned with iterate back to the affected ADM work rather than assume a strictly linear phase sequence. The requirement in this case is different: model Application Architecture covering application components, services and interactions.

B:

Architecture framework is concerned with adopt and tailor an Enterprise Architecture framework to provide consistent method, content and governance. The requirement in this case is different: model Application Architecture covering application components, services and interactions.

D:

Architecture principles is concerned with establishing agreed Architecture Principles that guide consistent architecture decisions. The requirement in this case is different: model Application Architecture covering application components, services and interactions.

Question 76

Architecture designers focus on cost and performance but omit potential identity and confidentiality failures. Which area of architecture work best describes the response needed in this situation?

  1. Risk identification
  2. Alternatives and trade-offs
  3. Principle conflict
  4. Readiness factor

Explanation

Correct Answer

A:

Identify architecture and transformation risks systematically across the target design. The practical check is whether risk log captures security, operational, financial and adoption exposures.

Incorrect Answers

B:

Alternatives and trade-offs is concerned with comparing architecture alternatives using business and technical trade-off criteria. The requirement in this case is different: identifying architecture and transformation risks systematically across the target design.

C:

Principle conflict is concerned with resolving the tension between principles and mandatory constraints with accountable governance. The requirement in this case is different: identifying architecture and transformation risks systematically across the target design.

D:

Readiness factor is concerned with assessing explicit readiness factors rather than relying on one subjective overall color. The requirement in this case is different: identifying architecture and transformation risks systematically across the target design.

Question 77

A target operating model needs specialist training and governance changes before a new application can deliver value. Which architecture focus or activity most directly addresses the stated need, rather than a merely adjacent issue?

  1. Phase B roadmap
  2. Phase F business value
  3. Phase E consolidated gaps
  4. Phase F lessons learned

Explanation

Correct Answer

A:

Identify candidate Business Architecture roadmap components in Phase B. The practical check is whether change candidates link business capability gaps to implementation planning.

Incorrect Answers

B:

Phase F business value is concerned with assign business value to work packages during Migration Planning in Phase F. The requirement in this case is different: identifying candidate Business Architecture roadmap components in Phase B.

C:

Phase E consolidated gaps is concerned with consolidate cross-domain gaps into solution opportunities during Phase E. The requirement in this case is different: identifying candidate Business Architecture roadmap components in Phase B.

D:

Phase F lessons learned is concerned with completing the ADM cycle and capture lessons learned during Phase F. The requirement in this case is different: identifying candidate Business Architecture roadmap components in Phase B.

Question 78

A generic reference integration capability becomes customized for a company's customer data model. Which area of architecture work best describes the response needed in this situation?

  1. Content artifact matrix
  2. Architecture building block relationship
  3. Enterprise continuum placement
  4. Deliverable approved status

Explanation

Correct Answer

C:

Place and manage the increasingly specific asset in the Enterprise Continuum. The practical check is whether asset classifications indicate the transition from generic guidance to organization-specific solutions.

Incorrect Answers

A:

Content artifact matrix is concerned with using a matrix artifact to show relationships between two architecture entity types. The requirement in this case is different: place and manage the increasingly specific asset in the Enterprise Continuum.

B:

Architecture building block relationship is concerned with keeping the Architecture Building Block technology-neutral and allow multiple Solution Building Block realizations. The requirement in this case is different: place and manage the increasingly specific asset in the Enterprise Continuum.

D:

Deliverable approved status is concerned with mark the reviewed and authorized deliverable Approved under governance. The requirement in this case is different: place and manage the increasingly specific asset in the Enterprise Continuum.

Question 79

Enterprise architects model only software components while a change requires business process redesign and regulatory operating controls. An architect must classify the work correctly. Which activity or focus fits the facts most closely?

  1. Architecture level strategy
  2. Architecture scoping time
  3. Applying beyond technology
  4. Architecture reuse across levels

Explanation

Correct Answer

C:

Apply the ADM across all relevant architecture domains and organizational change. The practical check is whether business, data, application and technology changes jointly support target outcomes.

Incorrect Answers

A:

Architecture level strategy is concerned with selecting strategy-level architecture work for the long-term enterprise horizon. The requirement in this case is different: applying the ADM across all relevant architecture domains and organizational change.

B:

Architecture scoping time is concerned with setting architecture time horizon and relevant transition states. The requirement in this case is different: applying the ADM across all relevant architecture domains and organizational change.

D:

Architecture reuse across levels is concerned with adapting reusable architecture assets for the target solution context and constraints. The requirement in this case is different: applying the ADM across all relevant architecture domains and organizational change.

Question 80

The architecture board counts reviews completed but cannot show whether exceptions or nonconformance decline. In a TOGAF-aligned engagement, which area best frames the required architectural decision?

  1. Governance principles enforcement
  2. Governance performance
  3. Architecture contract governance
  4. Governance exception

Explanation

Correct Answer

B:

Define governance effectiveness measures beyond meeting counts. The practical check is whether metrics track unresolved architecture risk, exceptions, remediation and value.

Incorrect Answers

A:

Governance principles enforcement is concerned with tracing review decisions to architecture principles and documented evidence. The requirement in this case is different: defining governance effectiveness measures beyond meeting counts.

C:

Architecture contract governance is concerned with governing supplier obligations through an Architecture Contract. The requirement in this case is different: defining governance effectiveness measures beyond meeting counts.

D:

Governance exception is concerned with managing architecture exceptions through formal risk-owned approval and expiry. The requirement in this case is different: defining governance effectiveness measures beyond meeting counts.