Question 450
A program sponsor asks to proceed on phase c data target although the proposed solution is Develop Target Data Architecture including logical entities, movement and ownership. The architecture review cannot confirm: Agreed canonical definitions and flows cover producer and consumer systems. Which action best restores defensible approval?
Explanation
Correct Answer
Resolve semantic differences before deployment of shared application interfaces. The required evidence was not demonstrated, so the corrected outcome must be verified before proceeding.
Incorrect Answers
That response concerns phase h performance and would be useful for a different gap. Here, the corrective step is to resolve semantic differences before deployment of shared application interfaces.
That response concerns preliminary organization and would be useful for a different gap. Here, the corrective step is to resolve semantic differences before deployment of shared application interfaces.
That response concerns phase h value realization and would be useful for a different gap. Here, the corrective step is to resolve semantic differences before deployment of shared application interfaces.