Question 130
A modernization initiative includes identity changes, data migration and application replacement with linked dependencies. An architect must classify the work correctly. Which activity or focus fits the facts most closely?
Explanation
Correct Answer
Group compatible changes into major work packages in Phase E. The practical check is whether work-package definitions show scope, dependencies and intended transition outcomes.
Incorrect Answers
Phase B organization is concerned with analyze organizational structures, responsibilities and operating models in Phase B. The requirement in this case is different: group compatible changes into major work packages in Phase E.
Phase E transition states is concerned with identifying feasible Transition Architectures in Phase E. The requirement in this case is different: group compatible changes into major work packages in Phase E.
Phase A sponsorship is concerned with establishing the architecture project and confirm business sponsorship in Phase A. The requirement in this case is different: group compatible changes into major work packages in Phase E.