Question 170
At fictional Eastfield Municipal Council, the SPM implementation team is supporting a multi-region resource-planning environment. During a quarterly audit checkpoint, they find this specific issue: A sponsor shortens the project schedule by three weeks but the same effort remains spread across the old longer capacity horizon. The reviewers must preserve traceability and test the selected response before accepting it. What review practice best reduces the recurrence risk?
Explanation
Correct Answer
Trigger resource impact review for major date or scope changes. The check is important because compressing a work window changes required concurrent capacity even when total effort stays constant.
Incorrect Answers
Reconcile role placeholders to named assignments before execution starts. This is a separate preventive check. Role demand estimates and person commitments have different certainty and scheduling implications. To address recurrence here, trigger resource impact review for major date or scope changes.
Monitor capacity-generation cadence and failed refresh jobs. This is a separate preventive check. Capacity projections can rely on precomputed supply and must be refreshed after material input changes. To address recurrence here, trigger resource impact review for major date or scope changes.
Audit regional calendars before annual capacity plans are approved. This is a separate preventive check. Work schedules determine location-specific available capacity within the same portfolio. To address recurrence here, trigger resource impact review for major date or scope changes.