Question 160
In an authorized test at fictional Westmere Logistics, the project team is assessing a multi-region resource-planning environment. During a quarterly audit checkpoint, they find this specific issue: A department moves a worker to another team without updating open assignments, leaving the original group to report unavailable capacity. The reviewers must preserve traceability and test the selected response before accepting it. What operating check should accompany future changes in this area?
Explanation
Correct Answer
Audit pending assignments during organizational transfers. This prevents the same failure mode, in which resource group membership and assignment responsibility are time-sensitive organizational data.
Incorrect Answers
Monitor capacity-generation cadence and failed refresh jobs. Capacity projections can rely on precomputed supply and must be refreshed after material input changes. It would not maintain the control needed here: audit pending assignments during organizational transfers.
Audit regional calendars before annual capacity plans are approved. Work schedules determine location-specific available capacity within the same portfolio. It would not maintain the control needed here: audit pending assignments during organizational transfers.
Audit expedited staffing exceptions and manager delegation regularly. Approval status gates governance of shared resources and should not be confused with record creation. It would not maintain the control needed here: audit pending assignments during organizational transfers.