Question 70
Following the agreed corrective action for this project concern—A construction team reports a building handover as complete even though the emergency evacuation system has not passed its agreed acceptance test.—which evidence would verify a suitable outcome?
Explanation
Correct Answer
The strongest confirmation is: The user signs the acceptance record only after evacuation performance is independently evidenced. It is evidence for the specific corrective step—Check the project product description and hold formal acceptance until the defined quality criteria are satisfied.—rather than a generic system-health signal.
Incorrect Answers
That outcome could matter in a case where user acceptance and specialist delivery responsibilities have been confused with the authorized work package process, but the present check needs to show that the user signs the acceptance record only after evacuation performance is independently evidenced.
The observation relates to a problem where activities have been scheduled before defining measurable products and the users' quality expectations; the required finding here is that the user signs the acceptance record only after evacuation performance is independently evidenced.
That outcome could matter in a case where the work package is task-focused and does not identify its product, interfaces or quality specifications, but the present check needs to show that the user signs the acceptance record only after evacuation performance is independently evidenced.