Question 50
A project assurance reviewer validates a response to this scenario: A museum digital archive stage is forecast to exceed its approved cost tolerance, but the project manager quietly reduces testing to stay on the baseline. What finding supports closure?
Explanation
Correct Answer
This finding directly demonstrates the intended result: The board receives an exception report before the forecast breach and decides the authorized response. It tests whether the chosen remediation—Raise an exception report with forecast impacts and options to the project board instead of silently changing acceptance criteria.—has addressed the cause: A forecast stage tolerance breach is being concealed through an unauthorized quality trade-off.
Incorrect Answers
It would be evidence for a problem in which activities have been scheduled before defining measurable products and the users' quality expectations. It does not verify that the board receives an exception report before the forecast breach and decides the authorized response.
The offered finding is relevant when the project board's own authorization boundary has been overlooked for a project-level exception. Here the acceptance test must show that the board receives an exception report before the forecast breach and decides the authorized response.
The offered finding is relevant when the team assumes any minor variance must be escalated to the project board rather than managed within delegated authority. Here the acceptance test must show that the board receives an exception report before the forecast breach and decides the authorized response.