Question 610
A project assurance reviewer validates a response to this scenario: A healthcare data project reports that expected benefits have disappeared, but board members insist the team finish to protect sunk costs. What finding supports closure?
Explanation
Correct Answer
The strongest confirmation is: The board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone. It is evidence for the specific corrective step—Reassess the current business case and decide whether to continue, change scope or close prematurely.—rather than a generic system-health signal.
Incorrect Answers
This result could confirm a fix when project completion has been mistaken for an automatic governance closure rather than a board decision. It would not demonstrate that the board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone.
The observation relates to a problem where responsibility for authorizing a management stage has been delegated to the delivering team without authority; the required finding here is that the board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone.
That outcome could matter in a case where the directing process is acting outside project-board tolerance limits set by the business layer, but the present check needs to show that the board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone.