Question 600
A project assurance review examines the cause of this problem: A university IT project has completed its initiation documentation but starts the first delivery stage solely on the project manager's approval. What preventive action should be introduced?
Explanation
Correct Answer
This practice reduces the documented recurrence risk: Check both approval decisions at the transition from initiation to delivery. The original root fault was: The board has not performed the distinct project authorization and first delivery stage authorization decisions. The practical health indicator is: The records show board authorization for the project and for the first delivery stage.
Incorrect Answers
This measure addresses a risk where the board cannot perform the authorize-initiation activity from unsupported assertions. The recurring failure here arises because the board has not performed the distinct project authorization and first delivery stage authorization decisions.
The control would be appropriate if responsibility for authorizing a management stage has been delegated to the delivering team without authority; the issue here is that the board has not performed the distinct project authorization and first delivery stage authorization decisions.
The proposed routine targets situations in which the board is taking over day-to-day management that should remain with the delegated project manager. To prevent the reported problem, the team must address the fact that the board has not performed the distinct project authorization and first delivery stage authorization decisions.