McAfee-Secured Website

Exam Code: PRINCE2 7 Practitioner

Exam Name: PRINCE2 7 Practitioner

Certification Provider: PRINCE2

100% PRINCE2 PRINCE2 7 Practitioner Guaranteed Success With Testking Training Materials

Get Real PRINCE2 7 Practitioner Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

93 Questions & Answers with Testing Engine

"PRINCE2 7 Practitioner Exam", also known as PRINCE2 7 Practitioner exam, is a PRINCE2 certification exam.

Pass your tests with the always up-to-date PRINCE2 7 Practitioner Exam Engine. Your PRINCE2 7 Practitioner training materials keep you at the head of the pack!

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Was: $137.49
Now: $124.99

PRINCE2 PRINCE2 7 Practitioner Practice Test 61

Question 600

A project assurance review examines the cause of this problem: A university IT project has completed its initiation documentation but starts the first delivery stage solely on the project manager's approval. What preventive action should be introduced?

  1. Use a minimum information checklist for board authorization of initiation.
  2. Check both approval decisions at the transition from initiation to delivery.
  3. Keep stage authorization in board decision procedures rather than supplier task controls.
  4. Use management by exception to separate direction from daily stage control.

Explanation

Correct Answer

B:

This practice reduces the documented recurrence risk: Check both approval decisions at the transition from initiation to delivery. The original root fault was: The board has not performed the distinct project authorization and first delivery stage authorization decisions. The practical health indicator is: The records show board authorization for the project and for the first delivery stage.

Incorrect Answers

A:

This measure addresses a risk where the board cannot perform the authorize-initiation activity from unsupported assertions. The recurring failure here arises because the board has not performed the distinct project authorization and first delivery stage authorization decisions.

C:

The control would be appropriate if responsibility for authorizing a management stage has been delegated to the delivering team without authority; the issue here is that the board has not performed the distinct project authorization and first delivery stage authorization decisions.

D:

The proposed routine targets situations in which the board is taking over day-to-day management that should remain with the delegated project manager. To prevent the reported problem, the team must address the fact that the board has not performed the distinct project authorization and first delivery stage authorization decisions.

Question 601

Apply PRINCE2 to this project decision: A transport modernization project forecasts a stage tolerance breach, and the project board orders a team manager to replan without considering the report. Which response is best supported by the method?

  1. Review the exception report and determine whether to direct an exception plan, corrective guidance or termination.
  2. Refer the project-level exception to the business layer and await the authorized decision.
  3. Refocus board involvement on strategic direction, stage decisions and exception response.
  4. Review the closing project recommendation, accepted products and post-project actions and authorize closure.

Explanation

Correct Answer

A:

Review the exception report and determine whether to direct an exception plan, corrective guidance or termination. This is the appropriate intervention because the directing level is responding to an exception without first reviewing implications and options. The specific outcome to verify is: The board makes a documented decision based on forecast impact and its authority.

Incorrect Answers

B:

That action tackles a problem where the directing process is acting outside project-board tolerance limits set by the business layer. The reported issue is instead that the directing level is responding to an exception without first reviewing implications and options.

C:

That action tackles a problem where the board is taking over day-to-day management that should remain with the delegated project manager. The reported issue is instead that the directing level is responding to an exception without first reviewing implications and options.

D:

“Review the closing project recommendation, accepted products and post-project actions and authorize closure” is useful when project completion has been mistaken for an automatic governance closure rather than a board decision. It does not resolve the current problem, in which the directing level is responding to an exception without first reviewing implications and options.

Question 602

Following the agreed corrective action for this project concern—A transport modernization project forecasts a stage tolerance breach, and the project board orders a team manager to replan without considering the report.—which evidence would verify a suitable outcome?

  1. The next stage begins only after a board decision recorded against the proposed stage plan.
  2. The requested variance is decided by the body with project-level authority.
  3. The board makes a documented decision based on forecast impact and its authority.
  4. The board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone.

Explanation

Correct Answer

C:

This finding directly demonstrates the intended result: The board makes a documented decision based on forecast impact and its authority. It tests whether the chosen remediation—Review the exception report and determine whether to direct an exception plan, corrective guidance or termination.—has addressed the cause: The directing level is responding to an exception without first reviewing implications and options.

Incorrect Answers

A:

The offered finding is relevant when responsibility for authorizing a management stage has been delegated to the delivering team without authority. Here the acceptance test must show that the board makes a documented decision based on forecast impact and its authority.

B:

The observation relates to a problem where the directing process is acting outside project-board tolerance limits set by the business layer; the required finding here is that the board makes a documented decision based on forecast impact and its authority.

D:

The observation relates to a problem where the board is neglecting continuing business justification and its responsibility to stop unjustified work; the required finding here is that the board makes a documented decision based on forecast impact and its authority.

Question 603

Which management-control deficiency underlies the following situation? A transport modernization project forecasts a stage tolerance breach, and the project board orders a team manager to replan without considering the report.

  1. The directing level is responding to an exception without first reviewing implications and options.
  2. The directing process is acting outside project-board tolerance limits set by the business layer.
  3. Responsibility for authorizing a management stage has been delegated to the delivering team without authority.
  4. The board has not performed the distinct project authorization and first delivery stage authorization decisions.

Explanation

Correct Answer

A:

The identified root cause is: The directing level is responding to an exception without first reviewing implications and options. The appropriate correction is: Review the exception report and determine whether to direct an exception plan, corrective guidance or termination. A separate validation must then show: The board makes a documented decision based on forecast impact and its authority.

Incorrect Answers

B:

The cause in this option would matter if the directing process is acting outside project-board tolerance limits set by the business layer. The reported failure instead arises because the directing level is responding to an exception without first reviewing implications and options.

C:

This diagnosis fits a situation in which responsibility for authorizing a management stage has been delegated to the delivering team without authority. Here, the directing level is responding to an exception without first reviewing implications and options.

D:

This diagnosis fits a situation in which the board has not performed the distinct project authorization and first delivery stage authorization decisions. Here, the directing level is responding to an exception without first reviewing implications and options.

Question 604

The project team has corrected the following defect: A transport modernization project forecasts a stage tolerance breach, and the project board orders a team manager to replan without considering the report. Which future assurance check should be added?

  1. Use a minimum information checklist for board authorization of initiation.
  2. Keep stage authorization in board decision procedures rather than supplier task controls.
  3. Use a formal direct-project closure decision tied to accepted outputs and follow-on accountability.
  4. Use structured board-level exception triage before ordering recovery plans.

Explanation

Correct Answer

D:

The lasting control is: Use structured board-level exception triage before ordering recovery plans. It addresses recurrence of this mechanism: The directing level is responding to an exception without first reviewing implications and options. A successful system should still demonstrate: The board makes a documented decision based on forecast impact and its authority.

Incorrect Answers

A:

This measure addresses a risk where the board cannot perform the authorize-initiation activity from unsupported assertions. The recurring failure here arises because the directing level is responding to an exception without first reviewing implications and options.

B:

The proposed routine targets situations in which responsibility for authorizing a management stage has been delegated to the delivering team without authority. To prevent the reported problem, the team must address the fact that the directing level is responding to an exception without first reviewing implications and options.

C:

This measure addresses a risk where project completion has been mistaken for an automatic governance closure rather than a board decision. The recurring failure here arises because the directing level is responding to an exception without first reviewing implications and options.

Question 605

The following project-management situation requires a decision: A construction project board rewrites the detailed daily work schedule during weekly meetings although the stage remains within tolerances. What should the team do?

  1. Request the project brief, outline justification and initiation stage plan before deciding on authorization.
  2. Reassess the current business case and decide whether to continue, change scope or close prematurely.
  3. Refer the project-level exception to the business layer and await the authorized decision.
  4. Refocus board involvement on strategic direction, stage decisions and exception response.

Explanation

Correct Answer

D:

The case requires this change: Refocus board involvement on strategic direction, stage decisions and exception response. The actual failure mechanism is: The board is taking over day-to-day management that should remain with the delegated project manager. A meaningful acceptance check is: The project manager controls routine work and the board receives decision-grade highlight information.

Incorrect Answers

A:

That action tackles a problem where the board cannot perform the authorize-initiation activity from unsupported assertions. The reported issue is instead that the board is taking over day-to-day management that should remain with the delegated project manager.

B:

The option would help when the board is neglecting continuing business justification and its responsibility to stop unjustified work, but it would not address a situation where the board is taking over day-to-day management that should remain with the delegated project manager.

C:

The option would help when the directing process is acting outside project-board tolerance limits set by the business layer, but it would not address a situation where the board is taking over day-to-day management that should remain with the delegated project manager.

Question 606

For the documented project problem below, which outcome should be verified? A construction project board rewrites the detailed daily work schedule during weekly meetings although the stage remains within tolerances.

  1. The requested variance is decided by the body with project-level authority.
  2. The project manager controls routine work and the board receives decision-grade highlight information.
  3. The board grants or declines initiation only after reviewing credible pre-project products.
  4. The board makes a documented decision based on forecast impact and its authority.

Explanation

Correct Answer

B:

Successful remediation is demonstrated when: The project manager controls routine work and the board receives decision-grade highlight information. That result connects to the targeted action: Refocus board involvement on strategic direction, stage decisions and exception response. The previously observed defect was: The board is taking over day-to-day management that should remain with the delegated project manager.

Incorrect Answers

A:

The observation relates to a problem where the directing process is acting outside project-board tolerance limits set by the business layer; the required finding here is that the project manager controls routine work and the board receives decision-grade highlight information.

C:

It would be evidence for a problem in which the board cannot perform the authorize-initiation activity from unsupported assertions. It does not verify that the project manager controls routine work and the board receives decision-grade highlight information.

D:

This result could confirm a fix when the directing level is responding to an exception without first reviewing implications and options. It would not demonstrate that the project manager controls routine work and the board receives decision-grade highlight information.

Question 607

Consider a PRINCE2 Project Management (Version 7) scenario: A construction project board rewrites the detailed daily work schedule during weekly meetings although the stage remains within tolerances. Which underlying management weakness most directly explains it?

  1. The board is neglecting continuing business justification and its responsibility to stop unjustified work.
  2. The board cannot perform the authorize-initiation activity from unsupported assertions.
  3. The board is taking over day-to-day management that should remain with the delegated project manager.
  4. The directing process is acting outside project-board tolerance limits set by the business layer.

Explanation

Correct Answer

C:

This mechanism accounts for the observation: The board is taking over day-to-day management that should remain with the delegated project manager. Address it by implementing: Refocus board involvement on strategic direction, stage decisions and exception response. Confirm the fix through: The project manager controls routine work and the board receives decision-grade highlight information.

Incorrect Answers

A:

The proposed diagnosis concerns a problem where the board is neglecting continuing business justification and its responsibility to stop unjustified work. The facts here indicate that the board is taking over day-to-day management that should remain with the delegated project manager.

B:

There could be such a cause if the board cannot perform the authorize-initiation activity from unsupported assertions. The stated incident instead arises because the board is taking over day-to-day management that should remain with the delegated project manager.

D:

This diagnosis fits a situation in which the directing process is acting outside project-board tolerance limits set by the business layer. Here, the board is taking over day-to-day management that should remain with the delegated project manager.

Question 608

After dealing with this project failure—A construction project board rewrites the detailed daily work schedule during weekly meetings although the stage remains within tolerances.—which governance safeguard should be retained?

  1. Check business-layer delegated project tolerances before every significant board authorization.
  2. Use management by exception to separate direction from daily stage control.
  3. Trigger formal board continuation reviews for material changes to justification.
  4. Keep stage authorization in board decision procedures rather than supplier task controls.

Explanation

Correct Answer

B:

To prevent the same issue, apply this check: Use management by exception to separate direction from daily stage control. The risk to contain is: The board is taking over day-to-day management that should remain with the delegated project manager. Verify control effectiveness using: The project manager controls routine work and the board receives decision-grade highlight information.

Incorrect Answers

A:

The control would be appropriate if the directing process is acting outside project-board tolerance limits set by the business layer; the issue here is that the board is taking over day-to-day management that should remain with the delegated project manager.

C:

The control would be appropriate if the board is neglecting continuing business justification and its responsibility to stop unjustified work; the issue here is that the board is taking over day-to-day management that should remain with the delegated project manager.

D:

The option addresses cases in which responsibility for authorizing a management stage has been delegated to the delivering team without authority. In the reported incident, the board is taking over day-to-day management that should remain with the delegated project manager instead.

Question 609

During a Practitioner-level project review, the following has occurred: A healthcare data project reports that expected benefits have disappeared, but board members insist the team finish to protect sunk costs. What should the accountable project role do next?

  1. Refocus board involvement on strategic direction, stage decisions and exception response.
  2. Reassess the current business case and decide whether to continue, change scope or close prematurely.
  3. Refer the project-level exception to the business layer and await the authorized decision.
  4. Present the PID and first stage plan for the project board's required decisions before delivery commitments.

Explanation

Correct Answer

B:

Choose this fix: Reassess the current business case and decide whether to continue, change scope or close prematurely. It repairs the stated issue, where the board is neglecting continuing business justification and its responsibility to stop unjustified work. The result should be independently established through: The board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone.

Incorrect Answers

A:

That action tackles a problem where the board is taking over day-to-day management that should remain with the delegated project manager. The reported issue is instead that the board is neglecting continuing business justification and its responsibility to stop unjustified work.

C:

The option would help when the directing process is acting outside project-board tolerance limits set by the business layer, but it would not address a situation where the board is neglecting continuing business justification and its responsibility to stop unjustified work.

D:

When the board has not performed the distinct project authorization and first delivery stage authorization decisions, “Present the PID and first stage plan for the project board's required decisions before delivery commitments” could be justified. Here, the board is neglecting continuing business justification and its responsibility to stop unjustified work, so this is not the needed correction.

Question 610

A project assurance reviewer validates a response to this scenario: A healthcare data project reports that expected benefits have disappeared, but board members insist the team finish to protect sunk costs. What finding supports closure?

  1. The board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone.
  2. A signed board decision closes the project with operational ownership and outstanding actions identified.
  3. The next stage begins only after a board decision recorded against the proposed stage plan.
  4. The requested variance is decided by the body with project-level authority.

Explanation

Correct Answer

A:

The strongest confirmation is: The board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone. It is evidence for the specific corrective step—Reassess the current business case and decide whether to continue, change scope or close prematurely.—rather than a generic system-health signal.

Incorrect Answers

B:

This result could confirm a fix when project completion has been mistaken for an automatic governance closure rather than a board decision. It would not demonstrate that the board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone.

C:

The observation relates to a problem where responsibility for authorizing a management stage has been delegated to the delivering team without authority; the required finding here is that the board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone.

D:

That outcome could matter in a case where the directing process is acting outside project-board tolerance limits set by the business layer, but the present check needs to show that the board decision cites forecast benefit, cost, risks and remaining obligations instead of sunk cost alone.