Question 310
The project team reports that it resolved the following issue: A health analytics project intends to deliver in short iterations but its work package specifies only a single final acceptance event. Which observed result is the best acceptance evidence?
Explanation
Correct Answer
The strongest confirmation is: Iterations yield verified product increments and remain within agreed stage reporting and tolerances. It is evidence for the specific corrective step—Define incremental product checkpoints and acceptance evidence while preserving project-level governance.—rather than a generic system-health signal.
Incorrect Answers
The offered finding is relevant when replanning has bypassed issue assessment and the relevant authority for changing approved baselines. Here the acceptance test must show that iterations yield verified product increments and remain within agreed stage reporting and tolerances.
The offered finding is relevant when the plan lists effort and spending without a complete product breakdown structure. Here the acceptance test must show that iterations yield verified product increments and remain within agreed stage reporting and tolerances.
This result could confirm a fix when the work has been decomposed by department instead of by verifiable handover products. It would not demonstrate that iterations yield verified product increments and remain within agreed stage reporting and tolerances.