Question 300
After dealing with this project failure—A procurement transformation pilot is within cost budget but its new plan omits the agreed supplier exit and rollback products.—which governance safeguard should be retained?
Explanation
Correct Answer
This practice reduces the documented recurrence risk: Run product completeness reviews against operational continuity needs when replanning. The original root fault was: The revised plan is incomplete because transition and contingency products have been omitted. The practical health indicator is: The authorized plan includes staffed and tested exit products before the pilot begins.
Incorrect Answers
The control would be appropriate if the current plan has not been re-evaluated after a material product dependency changed; the issue here is that the revised plan is incomplete because transition and contingency products have been omitted.
The proposed routine targets situations in which activity planning has preceded product-based planning and the project product description is incomplete. To prevent the reported problem, the team must address the fact that the revised plan is incomplete because transition and contingency products have been omitted.
The option addresses cases in which the team manager and project manager lack an authorized statement of products, quality methods, limits and checkpoints. In the reported incident, the revised plan is incomplete because transition and contingency products have been omitted instead.