McAfee-Secured Website

Exam Code: PRINCE2 7 Practitioner

Exam Name: PRINCE2 7 Practitioner

Certification Provider: PRINCE2

100% PRINCE2 PRINCE2 7 Practitioner Guaranteed Success With Testking Training Materials

Get Real PRINCE2 7 Practitioner Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

93 Questions & Answers with Testing Engine

"PRINCE2 7 Practitioner Exam", also known as PRINCE2 7 Practitioner exam, is a PRINCE2 certification exam.

Pass your tests with the always up-to-date PRINCE2 7 Practitioner Exam Engine. Your PRINCE2 7 Practitioner training materials keep you at the head of the pack!

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Was: $137.49
Now: $124.99

PRINCE2 PRINCE2 7 Practitioner Practice Test 17

Question 160

After dealing with this project failure—A library accessibility project proposes a costly feature that helps only a small subset of intended users and threatens the main benefit target.—which governance safeguard should be retained?

  1. Make benefit ownership acceptance a formal project closure handover criterion.
  2. Review non-financial benefits and mandatory constraints before major economic decisions.
  3. Trigger business case reviews when new external obligations threaten intended outcomes.
  4. Use a consistent benefit-versus-cost assessment for requests that change project scope.

Explanation

Correct Answer

D:

The lasting control is: Use a consistent benefit-versus-cost assessment for requests that change project scope. It addresses recurrence of this mechanism: The additional product option has not been assessed for desirability against existing project objectives. A successful system should still demonstrate: The board decision preserves a documented connection between the chosen scope and user benefit measures.

Incorrect Answers

A:

The control would be appropriate if post-project benefits responsibility is separated from the operating organization that controls actual realization; the issue here is that the additional product option has not been assessed for desirability against existing project objectives.

B:

This safeguard is useful when the appraisal is incomplete because the business case does not cover all relevant benefits and constraints. It does not prevent the present fault, where the additional product option has not been assessed for desirability against existing project objectives.

C:

The control would be appropriate if material new risk and schedule effects have not been propagated into the current business case; the issue here is that the additional product option has not been assessed for desirability against existing project objectives.

Question 161

During a Practitioner-level project review, the following has occurred: A transport ticketing scheme forecasts carbon reductions but cannot identify who will measure them after closure. What should the accountable project role do next?

  1. Document the preferred option against alternatives using whole-life costs, risk and expected benefits.
  2. Assess disposal options, update sustainability targets and include their costs in the business case.
  3. Compare the alternative against revised user benefits, cost and risk before asking the board to approve or reject it.
  4. Agree a measure, baseline, collection schedule and operational owner for the sustainability outcome.

Explanation

Correct Answer

D:

The case requires this change: Agree a measure, baseline, collection schedule and operational owner for the sustainability outcome. The actual failure mechanism is: The sustainability management approach and post-project measurement ownership are incomplete. A meaningful acceptance check is: A named business owner accepts post-project reporting and an auditable emissions baseline is retained.

Incorrect Answers

A:

This change addresses a situation in which the investment decision lacks comparative appraisal of credible options and lifecycle consequences. It leaves the current failure unresolved because the sustainability management approach and post-project measurement ownership are incomplete.

B:

This change addresses a situation in which the sustainability management approach has not captured end-of-life impacts within project decisions. It leaves the current failure unresolved because the sustainability management approach and post-project measurement ownership are incomplete.

C:

When the additional product option has not been assessed for desirability against existing project objectives, “Compare the alternative against revised user benefits, cost and risk before asking the board to approve or reject it” could be justified. Here, the sustainability management approach and post-project measurement ownership are incomplete, so this is not the needed correction.

Question 162

A project assurance reviewer validates a response to this scenario: A transport ticketing scheme forecasts carbon reductions but cannot identify who will measure them after closure. What finding supports closure?

  1. The selected option meets recorded ecological criteria or has an explicitly authorized exception.
  2. A named business owner accepts post-project reporting and an auditable emissions baseline is retained.
  3. A post-launch review shows measured queue times against the approved target.
  4. The board receives a balanced decision paper that makes the safety benefit explicit.

Explanation

Correct Answer

B:

Successful remediation is demonstrated when: A named business owner accepts post-project reporting and an auditable emissions baseline is retained. That result connects to the targeted action: Agree a measure, baseline, collection schedule and operational owner for the sustainability outcome. The previously observed defect was: The sustainability management approach and post-project measurement ownership are incomplete.

Incorrect Answers

A:

The offered finding is relevant when sustainability objectives are not being used as decision criteria alongside scope and cost. Here the acceptance test must show that a named business owner accepts post-project reporting and an auditable emissions baseline is retained.

C:

That outcome could matter in a case where the monitored indicator is a system output rather than the actual end-user benefit, but the present check needs to show that a named business owner accepts post-project reporting and an auditable emissions baseline is retained.

D:

The observation relates to a problem where the appraisal is incomplete because the business case does not cover all relevant benefits and constraints; the required finding here is that a named business owner accepts post-project reporting and an auditable emissions baseline is retained.

Question 163

In this project situation, A transport ticketing scheme forecasts carbon reductions but cannot identify who will measure them after closure. What weakness should be corrected?

  1. The business case confuses funding for delivery with funding for sustainable operation and benefit realization.
  2. The sustainability management approach and post-project measurement ownership are incomplete.
  3. Cost performance is being treated as proof of benefit success even though business outcomes fell short.
  4. The economic model understates ongoing operating expense and therefore misstates project viability.

Explanation

Correct Answer

B:

This mechanism accounts for the observation: The sustainability management approach and post-project measurement ownership are incomplete. Address it by implementing: Agree a measure, baseline, collection schedule and operational owner for the sustainability outcome. Confirm the fix through: A named business owner accepts post-project reporting and an auditable emissions baseline is retained.

Incorrect Answers

A:

The mechanism could explain a fault where the business case confuses funding for delivery with funding for sustainable operation and benefit realization; it does not account for the current condition, where the sustainability management approach and post-project measurement ownership are incomplete.

C:

The proposed diagnosis concerns a problem where cost performance is being treated as proof of benefit success even though business outcomes fell short. The facts here indicate that the sustainability management approach and post-project measurement ownership are incomplete.

D:

This diagnosis fits a situation in which the economic model understates ongoing operating expense and therefore misstates project viability. Here, the sustainability management approach and post-project measurement ownership are incomplete.

Question 164

A Practitioner recommends a permanent improvement after this problem: A transport ticketing scheme forecasts carbon reductions but cannot identify who will measure them after closure. Which control is most effective?

  1. Maintain an options appraisal trail for material solution choices.
  2. Require measurable baselines and accountable benefit owners in the initiation approval gate.
  3. Review the continuity of sustainability measurement through stage boundaries and handover.
  4. Review non-financial benefits and mandatory constraints before major economic decisions.

Explanation

Correct Answer

C:

To prevent the same issue, apply this check: Review the continuity of sustainability measurement through stage boundaries and handover. The risk to contain is: The sustainability management approach and post-project measurement ownership are incomplete. Verify control effectiveness using: A named business owner accepts post-project reporting and an auditable emissions baseline is retained.

Incorrect Answers

A:

This safeguard is useful when the investment decision lacks comparative appraisal of credible options and lifecycle consequences. It does not prevent the present fault, where the sustainability management approach and post-project measurement ownership are incomplete.

B:

The proposed routine targets situations in which the benefits management approach cannot confirm whether the project has achieved its intended outcome. To prevent the reported problem, the team must address the fact that the sustainability management approach and post-project measurement ownership are incomplete.

D:

The control would be appropriate if the appraisal is incomplete because the business case does not cover all relevant benefits and constraints; the issue here is that the sustainability management approach and post-project measurement ownership are incomplete.

Question 165

A project board member examines the following problem: A municipal records project claims improved public service as a benefit but specifies no volume or response-time baseline. Which proposed next step best fits PRINCE2?

  1. Report the benefits shortfall, update the final business case and agree an owner-led corrective or follow-up plan.
  2. Set measurable service targets, present-state baselines and review timing with the senior user.
  3. Document the preferred option against alternatives using whole-life costs, risk and expected benefits.
  4. Assign appropriate benefit owners, methods and review dates in the benefits management approach.

Explanation

Correct Answer

B:

Choose this fix: Set measurable service targets, present-state baselines and review timing with the senior user. It repairs the stated issue, where the benefits management approach cannot confirm whether the project has achieved its intended outcome. The result should be independently established through: Reported actual service outcomes can be compared with a signed baseline and target after deployment.

Incorrect Answers

A:

The option would help when cost performance is being treated as proof of benefit success even though business outcomes fell short, but it would not address a situation where the benefits management approach cannot confirm whether the project has achieved its intended outcome.

C:

The option would help when the investment decision lacks comparative appraisal of credible options and lifecycle consequences, but it would not address a situation where the benefits management approach cannot confirm whether the project has achieved its intended outcome.

D:

The option would help when post-project benefits responsibility is separated from the operating organization that controls actual realization, but it would not address a situation where the benefits management approach cannot confirm whether the project has achieved its intended outcome.

Question 166

Which result best demonstrates appropriate PRINCE2 application in this situation? A municipal records project claims improved public service as a benefit but specifies no volume or response-time baseline.

  1. The stage decision records a tested funding assumption and contingency before authorizing work.
  2. Reported actual service outcomes can be compared with a signed baseline and target after deployment.
  3. A post-launch review shows measured queue times against the approved target.
  4. The board decision preserves a documented connection between the chosen scope and user benefit measures.

Explanation

Correct Answer

B:

The strongest confirmation is: Reported actual service outcomes can be compared with a signed baseline and target after deployment. It is evidence for the specific corrective step—Set measurable service targets, present-state baselines and review timing with the senior user.—rather than a generic system-health signal.

Incorrect Answers

A:

The observation relates to a problem where funding eligibility is material to project viability but is missing from stage decision information; the required finding here is that reported actual service outcomes can be compared with a signed baseline and target after deployment.

C:

This result could confirm a fix when the monitored indicator is a system output rather than the actual end-user benefit. It would not demonstrate that reported actual service outcomes can be compared with a signed baseline and target after deployment.

D:

The offered finding is relevant when the additional product option has not been assessed for desirability against existing project objectives. Here the acceptance test must show that reported actual service outcomes can be compared with a signed baseline and target after deployment.

Question 167

The following problem has arisen during a project: A municipal records project claims improved public service as a benefit but specifies no volume or response-time baseline. Which cause fits the evidence?

  1. Sustainability objectives are not being used as decision criteria alongside scope and cost.
  2. The benefits management approach cannot confirm whether the project has achieved its intended outcome.
  3. The investment decision lacks comparative appraisal of credible options and lifecycle consequences.
  4. The sustainability management approach and post-project measurement ownership are incomplete.

Explanation

Correct Answer

B:

The failure is explained by: The benefits management approach cannot confirm whether the project has achieved its intended outcome. It supports the targeted intervention: Set measurable service targets, present-state baselines and review timing with the senior user. The observable test of success is: Reported actual service outcomes can be compared with a signed baseline and target after deployment.

Incorrect Answers

A:

The mechanism could explain a fault where sustainability objectives are not being used as decision criteria alongside scope and cost; it does not account for the current condition, where the benefits management approach cannot confirm whether the project has achieved its intended outcome.

C:

The mechanism could explain a fault where the investment decision lacks comparative appraisal of credible options and lifecycle consequences; it does not account for the current condition, where the benefits management approach cannot confirm whether the project has achieved its intended outcome.

D:

The proposed diagnosis concerns a problem where the sustainability management approach and post-project measurement ownership are incomplete. The facts here indicate that the benefits management approach cannot confirm whether the project has achieved its intended outcome.

Question 168

What recurring PRINCE2 control would best prevent this situation from happening again? A municipal records project claims improved public service as a benefit but specifies no volume or response-time baseline.

  1. Include environmental targets among change and stage acceptance measures.
  2. Require whole-life cost assumptions and owner confirmation in each business case refresh.
  3. Require measurable baselines and accountable benefit owners in the initiation approval gate.
  4. Cross-check benefits timing against the change management and project plans at every boundary.

Explanation

Correct Answer

C:

This practice reduces the documented recurrence risk: Require measurable baselines and accountable benefit owners in the initiation approval gate. The original root fault was: The benefits management approach cannot confirm whether the project has achieved its intended outcome. The practical health indicator is: Reported actual service outcomes can be compared with a signed baseline and target after deployment.

Incorrect Answers

A:

This measure addresses a risk where sustainability objectives are not being used as decision criteria alongside scope and cost. The recurring failure here arises because the benefits management approach cannot confirm whether the project has achieved its intended outcome.

B:

The proposed routine targets situations in which the economic model understates ongoing operating expense and therefore misstates project viability. To prevent the reported problem, the team must address the fact that the benefits management approach cannot confirm whether the project has achieved its intended outcome.

D:

This safeguard is useful when the benefits profile uses a realization date inconsistent with change adoption prerequisites. It does not prevent the present fault, where the benefits management approach cannot confirm whether the project has achieved its intended outcome.

Question 169

A PRINCE2 Project Management (Version 7) team faces this situation: A medical research data hub has new privacy constraints that delay deployment and reduce expected participant uptake. Which corrective governance or delivery action is most appropriate?

  1. Include grant conditions, likelihood of compliance and funding exposure in the updated business case.
  2. Update the business case's benefit, cost and risk assumptions and present feasible options to the board.
  3. Agree a real-world queue-time measurement and baseline with the senior user and update the benefits approach.
  4. Add total lifecycle cost, uncertainty and operating ownership to the forecast business case before the next decision.

Explanation

Correct Answer

B:

Update the business case's benefit, cost and risk assumptions and present feasible options to the board. This is the appropriate intervention because Material new risk and schedule effects have not been propagated into the current business case. The specific outcome to verify is: The approved course of action explicitly reflects privacy mitigation expense and reduced uptake assumptions.

Incorrect Answers

A:

When funding eligibility is material to project viability but is missing from stage decision information, “Include grant conditions, likelihood of compliance and funding exposure in the updated business case” could be justified. Here, material new risk and schedule effects have not been propagated into the current business case, so this is not the needed correction.

C:

That action tackles a problem where the monitored indicator is a system output rather than the actual end-user benefit. The reported issue is instead that material new risk and schedule effects have not been propagated into the current business case.

D:

The option would help when the economic model understates ongoing operating expense and therefore misstates project viability, but it would not address a situation where material new risk and schedule effects have not been propagated into the current business case.

Question 170

The project team reports that it resolved the following issue: A medical research data hub has new privacy constraints that delay deployment and reduce expected participant uptake. Which observed result is the best acceptance evidence?

  1. Each benefit has an agreed measure, named owner and feasible follow-up date.
  2. A named business owner accepts post-project reporting and an auditable emissions baseline is retained.
  3. The board receives a balanced decision paper that makes the safety benefit explicit.
  4. The approved course of action explicitly reflects privacy mitigation expense and reduced uptake assumptions.

Explanation

Correct Answer

D:

This finding directly demonstrates the intended result: The approved course of action explicitly reflects privacy mitigation expense and reduced uptake assumptions. It tests whether the chosen remediation—Update the business case's benefit, cost and risk assumptions and present feasible options to the board.—has addressed the cause: Material new risk and schedule effects have not been propagated into the current business case.

Incorrect Answers

A:

The observation relates to a problem where post-project benefits responsibility is separated from the operating organization that controls actual realization; the required finding here is that the approved course of action explicitly reflects privacy mitigation expense and reduced uptake assumptions.

B:

The offered finding is relevant when the sustainability management approach and post-project measurement ownership are incomplete. Here the acceptance test must show that the approved course of action explicitly reflects privacy mitigation expense and reduced uptake assumptions.

C:

It would be evidence for a problem in which the appraisal is incomplete because the business case does not cover all relevant benefits and constraints. It does not verify that the approved course of action explicitly reflects privacy mitigation expense and reduced uptake assumptions.