Question 150
A PRINCE2 practitioner has implemented a correction to this situation: A hybrid green-energy installation holds frequent team calls yet key approvals are absent from the project log and cannot be audited. Which outcome demonstrates that the correction worked?
Explanation
Correct Answer
Successful remediation is demonstrated when: Every material approval has a named decision maker, date and traceable record linked to the relevant work package. That result connects to the targeted action: Record material approvals and commitments in agreed information products while preserving useful team conversations. The previously observed defect was: Informal conversations are replacing controlled management communication and decision records.
Incorrect Answers
This result could confirm a fix when the communication management approach omits affected external stakeholder groups and their information needs. It would not demonstrate that every material approval has a named decision maker, date and traceable record linked to the relevant work package.
That outcome could matter in a case where outward communication lacks an engagement and feedback path for stakeholders harmed by project activity, but the present check needs to show that every material approval has a named decision maker, date and traceable record linked to the relevant work package.
That outcome could matter in a case where the communication channel chosen does not match the stakeholder audience's realistic access, but the present check needs to show that every material approval has a named decision maker, date and traceable record linked to the relevant work package.