McAfee-Secured Website

Exam Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 97

Question 960

What ongoing preventive practice would most reduce recurrence of: A nonprofit calls a collection of separate volunteer events one project despite no shared end result or integrated scope.

  1. Set regular stakeholder feedback and decision checkpoints.
  2. Require conflicts to be disclosed before sourcing work.
  3. Screen funding applications for project-versus-operations distinctions.
  4. Train contributors on register classification and fields.

Explanation

Correct Answer

C:

Screen funding applications for project-versus-operations distinctions. This helps prevent recurrence of: A nonprofit calls a collection of separate volunteer events one project despite no shared end result or integrated scope. The required evidence of effective control is: Each funded project has explicit start, completion and accepted output criteria.

Incorrect Answers

A:

Set regular stakeholder feedback and decision checkpoints. That is a useful control for ANOTHER case: A market-testing initiative keeps an immutable specification after customer interviews reveal the solution solves the wrong need. The current situation is better prevented by: Screen funding applications for project-versus-operations distinctions.

B:

Require conflicts to be disclosed before sourcing work. That is a useful control for ANOTHER case: A manager privately awards a contract to a close relative without disclosing the relationship. The current situation is better prevented by: Screen funding applications for project-versus-operations distinctions.

D:

Train contributors on register classification and fields. That is a useful control for ANOTHER case: A team uses a risk register to list every individual stakeholder complaint without identifying risk triggers or responses. The current situation is better prevented by: Screen funding applications for project-versus-operations distinctions.

Question 961

At a nonprofit modernization team, the review identifies: A facility project has no risk response if its sole permit reviewer becomes unavailable. Which response best addresses the specific project management problem?

  1. Assign an owner, trigger and alternate approval path within the risk response plan.
  2. Develop risk response plans and fund appropriate contingencies within governance.
  3. Sequence the test work according to lab capacity and resource constraints.
  4. Follow the procurement response plan, assess new impacts and notify affected stakeholders.

Explanation

Correct Answer

A:

Assign an owner, trigger and alternate approval path within the risk response plan. This addresses the fictional case: A facility project has no risk response if its sole permit reviewer becomes unavailable. The project-management rationale is: Planning should treat critical single points of failure as threats to schedule objectives. Verify by: A tabletop exercise finds an approved path before the permit deadline.

Incorrect Answers

B:

Develop risk response plans and fund appropriate contingencies within governance. This would address a DIFFERENT fictional project situation: A delivery plan has a detailed Gantt chart but does not specify authorized risk response costs. It is less directly applicable to: A facility project has no risk response if its sole permit reviewer becomes unavailable.

C:

Sequence the test work according to lab capacity and resource constraints. This would address a DIFFERENT fictional project situation: An offshore development team plans 12 parallel testing activities on one shared lab environment. It is less directly applicable to: A facility project has no risk response if its sole permit reviewer becomes unavailable.

D:

Follow the procurement response plan, assess new impacts and notify affected stakeholders. This would address a DIFFERENT fictional project situation: A project closes its schedule report when a vendor refuses delivery, despite an established procurement contingency. It is less directly applicable to: A facility project has no risk response if its sole permit reviewer becomes unavailable.

Question 962

The project issue was: A facility project has no risk response if its sole permit reviewer becomes unavailable. Which outcome demonstrates that its remedy worked?

  1. The engagement plan identifies representatives and review contacts for patient impacts.
  2. A tabletop exercise finds an approved path before the permit deadline.
  3. Separate documented roadmap decisions and approved project schedule, scope, costs and roles exist.
  4. Each short review incorporates verified changes before the next delivery slice.

Explanation

Correct Answer

B:

A tabletop exercise finds an approved path before the permit deadline. This validates the selected response: Assign an owner, trigger and alternate approval path within the risk response plan. The relevant management principle is: Planning should treat critical single points of failure as threats to schedule objectives.

Incorrect Answers

A:

The engagement plan identifies representatives and review contacts for patient impacts. This is evidence for ANOTHER case: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. The specific corrective response here is: Assign an owner, trigger and alternate approval path within the risk response plan.

C:

Separate documented roadmap decisions and approved project schedule, scope, costs and roles exist. This is evidence for ANOTHER case: A software product owner writes a five-year product roadmap and presents it as the approved project delivery plan. The specific corrective response here is: Assign an owner, trigger and alternate approval path within the risk response plan.

D:

Each short review incorporates verified changes before the next delivery slice. This is evidence for ANOTHER case: A manufacturing team freezes all product details up front despite weekly regulatory discoveries that regularly change requirements. The specific corrective response here is: Assign an owner, trigger and alternate approval path within the risk response plan.

Question 963

For a nonprofit modernization team, the documented failure was: A facility project has no risk response if its sole permit reviewer becomes unavailable. Which explanation is most accurate?

  1. Closure confirms agreed acceptance, not merely that the scheduled date arrived.
  2. A stakeholder register enables deliberate engagement beyond a list of names.
  3. Planning should treat critical single points of failure as threats to schedule objectives.
  4. Communication planning matches detail and frequency to audience needs.

Explanation

Correct Answer

C:

Planning should treat critical single points of failure as threats to schedule objectives. This explains the case: A facility project has no risk response if its sole permit reviewer becomes unavailable. The targeted action is: Assign an owner, trigger and alternate approval path within the risk response plan.

Incorrect Answers

A:

Closure confirms agreed acceptance, not merely that the scheduled date arrived. This rationale better explains a DIFFERENT problem: A transition meeting closes a manufacturing project while unresolved mandatory safety documentation remains with no owner. The key mechanism for the current situation is: Planning should treat critical single points of failure as threats to schedule objectives.

B:

A stakeholder register enables deliberate engagement beyond a list of names. This rationale better explains a DIFFERENT problem: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. The key mechanism for the current situation is: Planning should treat critical single points of failure as threats to schedule objectives.

D:

Communication planning matches detail and frequency to audience needs. This rationale better explains a DIFFERENT problem: A communications coordinator sends a highly technical daily report to executives whose plan calls for a monthly decision dashboard. The key mechanism for the current situation is: Planning should treat critical single points of failure as threats to schedule objectives.

Question 964

Which recurring governance check best addresses the risk of repeating: A facility project has no risk response if its sole permit reviewer becomes unavailable.

  1. Update stakeholder engagement as delivery dependencies change.
  2. Make baseline approval an explicit process gate.
  3. Reclassify risks promptly when trigger conditions occur.
  4. Review single-role dependencies during risk identification.

Explanation

Correct Answer

D:

Review single-role dependencies during risk identification. This helps prevent recurrence of: A facility project has no risk response if its sole permit reviewer becomes unavailable. The required evidence of effective control is: A tabletop exercise finds an approved path before the permit deadline.

Incorrect Answers

A:

Update stakeholder engagement as delivery dependencies change. That is a useful control for ANOTHER case: A project removes the supplier from its stakeholder register after contract signature even though supplier approval is needed for integration tests. The current situation is better prevented by: Review single-role dependencies during risk identification.

B:

Make baseline approval an explicit process gate. That is a useful control for ANOTHER case: A public-sector project tracks decisions only in hallway conversations and cannot locate baseline approvals. The current situation is better prevented by: Review single-role dependencies during risk identification.

C:

Reclassify risks promptly when trigger conditions occur. That is a useful control for ANOTHER case: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped. The current situation is better prevented by: Review single-role dependencies during risk identification.

Question 965

During a project review, stakeholders report: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides. What should the team do first?

  1. Recognize team concerns and negotiate sustainable capacity with the sponsor.
  2. Gather facts privately, manage emotions and negotiate an equitable next step.
  3. Refer funding authorization to the accountable sponsor and document the decision.
  4. Document the unverified arrival date as an assumption and validate it with the partner.

Explanation

Correct Answer

B:

Gather facts privately, manage emotions and negotiate an equitable next step. This addresses the fictional case: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides. The project-management rationale is: Respectful facilitation reduces conflict escalation and supports fair negotiation. Verify by: Both sides accept a documented solution without an unresolved relationship complaint.

Incorrect Answers

A:

Recognize team concerns and negotiate sustainable capacity with the sponsor. This would address a DIFFERENT fictional project situation: A manager spends all team meetings examining metrics but never addresses demotivation following repeated weekend work. It is less directly applicable to: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides.

C:

Refer funding authorization to the accountable sponsor and document the decision. This would address a DIFFERENT fictional project situation: A contractor asks the project manager for funding beyond the charter's authority and receives an informal approval. It is less directly applicable to: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides.

D:

Document the unverified arrival date as an assumption and validate it with the partner. This would address a DIFFERENT fictional project situation: A new app project assumes that all partner data will arrive by March without independent confirmation. It is less directly applicable to: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides.

Question 966

Following the proposed correction, what observation confirms success: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides.

  1. The issue response records team input and a validated safe plan.
  2. Retrospective feedback shows manageable commitments and improved participation.
  3. Both sides accept a documented solution without an unresolved relationship complaint.
  4. Baseline approvals demonstrate that planned commitments stay within the approved cap.

Explanation

Correct Answer

C:

Both sides accept a documented solution without an unresolved relationship complaint. This validates the selected response: Gather facts privately, manage emotions and negotiate an equitable next step. The relevant management principle is: Respectful facilitation reduces conflict escalation and supports fair negotiation.

Incorrect Answers

A:

The issue response records team input and a validated safe plan. This is evidence for ANOTHER case: A delivery lead issues commands during a tense incident and ignores team concerns about a vulnerable migration step. The specific corrective response here is: Gather facts privately, manage emotions and negotiate an equitable next step.

B:

Retrospective feedback shows manageable commitments and improved participation. This is evidence for ANOTHER case: A manager spends all team meetings examining metrics but never addresses demotivation following repeated weekend work. The specific corrective response here is: Gather facts privately, manage emotions and negotiate an equitable next step.

D:

Baseline approvals demonstrate that planned commitments stay within the approved cap. This is evidence for ANOTHER case: A finance team treats a capped annual funding limit as an unknown risk rather than a fixed spending boundary. The specific corrective response here is: Gather facts privately, manage emotions and negotiate an equitable next step.

Question 967

Which underlying planning or business-analysis mechanism explains: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides.

  1. Listening and facilitation help turn ambiguous directions into aligned work.
  2. Effective leadership leverages team expertise without confusing it with governance authority.
  3. Milestones represent significant events, not effort or elapsed task duration.
  4. Respectful facilitation reduces conflict escalation and supports fair negotiation.

Explanation

Correct Answer

D:

Respectful facilitation reduces conflict escalation and supports fair negotiation. This explains the case: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides. The targeted action is: Gather facts privately, manage emotions and negotiate an equitable next step.

Incorrect Answers

A:

Listening and facilitation help turn ambiguous directions into aligned work. This rationale better explains a DIFFERENT problem: Two teams interpret an executive statement differently and begin incompatible implementations. The key mechanism for the current situation is: Respectful facilitation reduces conflict escalation and supports fair negotiation.

B:

Effective leadership leverages team expertise without confusing it with governance authority. This rationale better explains a DIFFERENT problem: A product engineer holds critical knowledge but the sponsor excludes them from risk conversations to keep meetings short. The key mechanism for the current situation is: Respectful facilitation reduces conflict escalation and supports fair negotiation.

C:

Milestones represent significant events, not effort or elapsed task duration. This rationale better explains a DIFFERENT problem: A sponsor treats a zero-duration regulatory approval milestone as five days of actual installation effort. The key mechanism for the current situation is: Respectful facilitation reduces conflict escalation and supports fair negotiation.

Question 968

For the previous project issue, select the best preventive control: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides.

  1. Use interest-based negotiation protocols for disputes.
  2. Ask teams for recurring impediment feedback.
  3. Make feasibility reviews part of commitment approval.
  4. Maintain the current regulatory baseline in the project register.

Explanation

Correct Answer

A:

Use interest-based negotiation protocols for disputes. This helps prevent recurrence of: A procurement dispute requires neutral negotiation, but the PM publicly assigns blame before hearing both sides. The required evidence of effective control is: Both sides accept a documented solution without an unresolved relationship complaint.

Incorrect Answers

B:

Ask teams for recurring impediment feedback. That is a useful control for ANOTHER case: An agile facilitator evaluates team success by how many direct orders team members obey. The current situation is better prevented by: Use interest-based negotiation protocols for disputes.

C:

Make feasibility reviews part of commitment approval. That is a useful control for ANOTHER case: A sponsor promises an impossible delivery date, then blames the team when technical evidence contradicts it. The current situation is better prevented by: Use interest-based negotiation protocols for disputes.

D:

Maintain the current regulatory baseline in the project register. That is a useful control for ANOTHER case: A safety inspector asks for evidence of a new mandatory standard, but a team defers compliance as a possible future risk. The current situation is better prevented by: Use interest-based negotiation protocols for disputes.

Question 969

For a pharmaceutical quality project, a delivery problem is reported: A product experiment delivers a feature but does not measure whether customer service time actually improved. Which action fits the situation?

  1. Define current-state measures and target benefits in the initiation business case.
  2. Follow the procurement response plan, assess new impacts and notify affected stakeholders.
  3. Run benefit validation using the approved service-time metric and real users.
  4. Register encryption compliance as a project constraint and plan delivery within it.

Explanation

Correct Answer

C:

Run benefit validation using the approved service-time metric and real users. This addresses the fictional case: A product experiment delivers a feature but does not measure whether customer service time actually improved. The project-management rationale is: Delivery completion and value realization are distinct measures. Verify by: The benefit report compares before-and-after time with the agreed target.

Incorrect Answers

A:

Define current-state measures and target benefits in the initiation business case. This would address a DIFFERENT fictional project situation: A project initiation memo promises growth but includes no baseline of current performance. It is less directly applicable to: A product experiment delivers a feature but does not measure whether customer service time actually improved.

B:

Follow the procurement response plan, assess new impacts and notify affected stakeholders. This would address a DIFFERENT fictional project situation: A project closes its schedule report when a vendor refuses delivery, despite an established procurement contingency. It is less directly applicable to: A product experiment delivers a feature but does not measure whether customer service time actually improved.

D:

Register encryption compliance as a project constraint and plan delivery within it. This would address a DIFFERENT fictional project situation: A hospital rollout must use approved encryption regardless of cost, but staff record this mandatory condition as an optional risk. It is less directly applicable to: A product experiment delivers a feature but does not measure whether customer service time actually improved.

Question 970

How should the project team verify a successful response to: A product experiment delivers a feature but does not measure whether customer service time actually improved.

  1. Time-sensitive response actions occur by the assigned owner with reporting afterward.
  2. The mitigation has an assigned owner and funded schedule activities.
  3. Signed transition criteria move day-to-day ownership to the operations team.
  4. The benefit report compares before-and-after time with the agreed target.

Explanation

Correct Answer

D:

The benefit report compares before-and-after time with the agreed target. This validates the selected response: Run benefit validation using the approved service-time metric and real users. The relevant management principle is: Delivery completion and value realization are distinct measures.

Incorrect Answers

A:

Time-sensitive response actions occur by the assigned owner with reporting afterward. This is evidence for ANOTHER case: The risk owner identifies a trigger but refuses to act until the project manager attends the next meeting. The specific corrective response here is: Run benefit validation using the approved service-time metric and real users.

B:

The mitigation has an assigned owner and funded schedule activities. This is evidence for ANOTHER case: A project adopts a formal risk strategy but does not budget any implementation resources for its selected mitigation. The specific corrective response here is: Run benefit validation using the approved service-time metric and real users.

C:

Signed transition criteria move day-to-day ownership to the operations team. This is evidence for ANOTHER case: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion. The specific corrective response here is: Run benefit validation using the approved service-time metric and real users.