Question 950
Following the proposed correction, what observation confirms success: A monthly report corrects a schedule problem by rewriting planned value to match earned value without change authority.
Explanation
Correct Answer
The variance remains visible with transparent change decision history. This validates the selected response: Preserve the original baseline unless formal approval justifies a revision. The relevant management principle is: Rebaselining without authorization hides performance deviations.
Incorrect Answers
Earned value is supported by accepted deliverables and observed completion. This is evidence for ANOTHER case: A coordinator changes earned-value percent complete without objective evidence just to show green status. The specific corrective response here is: Preserve the original baseline unless formal approval justifies a revision.
The cost-control report identifies the deficit accurately. This is evidence for ANOTHER case: A project has earned value $70,000 and actual cost $88,000, yet the report describes its cost variance as favorable. The specific corrective response here is: Preserve the original baseline unless formal approval justifies a revision.
The WBS lists design, fit-out, integration, testing and handover outputs. This is evidence for ANOTHER case: A plan uses one undifferentiated task called build hospital with no deliverable ownership or progress measure. The specific corrective response here is: Preserve the original baseline unless formal approval justifies a revision.