Question 910
For a university infrastructure office, what is the strongest acceptance evidence after addressing: A baseline has a nine-day critical path but a scope change extends its controlling activity by four days without acceleration.
Explanation
Correct Answer
The revised critical-path calculation shows the four-day increase in duration. This validates the selected response: Forecast a 13-day earliest finish after approved change and updated network logic. The relevant management principle is: Extra time on an unchanged critical path extends completion absent other schedule adjustments.
Incorrect Answers
The status sheet records SV = −$10,000 with context about being behind planned value. This is evidence for ANOTHER case: A project reports earned value of $40,000 and planned value of $50,000 but describes its schedule variance as positive. The specific corrective response here is: Forecast a 13-day earliest finish after approved change and updated network logic.
The reconciled status report interprets positive SV correctly. This is evidence for ANOTHER case: An engineering project has earned value $75,000 and planned value $60,000 but staff report 15,000 dollars behind schedule. The specific corrective response here is: Forecast a 13-day earliest finish after approved change and updated network logic.
EV and AC reconciliation shows CV = +$10,000. This is evidence for ANOTHER case: A team has EV $95,000 and actual cost $85,000 and labels its project $10,000 over budget. The specific corrective response here is: Forecast a 13-day earliest finish after approved change and updated network logic.