McAfee-Secured Website

Exam Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 92

Question 910

For a university infrastructure office, what is the strongest acceptance evidence after addressing: A baseline has a nine-day critical path but a scope change extends its controlling activity by four days without acceleration.

  1. The revised critical-path calculation shows the four-day increase in duration.
  2. The status sheet records SV = −$10,000 with context about being behind planned value.
  3. The reconciled status report interprets positive SV correctly.
  4. EV and AC reconciliation shows CV = +$10,000.

Explanation

Correct Answer

A:

The revised critical-path calculation shows the four-day increase in duration. This validates the selected response: Forecast a 13-day earliest finish after approved change and updated network logic. The relevant management principle is: Extra time on an unchanged critical path extends completion absent other schedule adjustments.

Incorrect Answers

B:

The status sheet records SV = −$10,000 with context about being behind planned value. This is evidence for ANOTHER case: A project reports earned value of $40,000 and planned value of $50,000 but describes its schedule variance as positive. The specific corrective response here is: Forecast a 13-day earliest finish after approved change and updated network logic.

C:

The reconciled status report interprets positive SV correctly. This is evidence for ANOTHER case: An engineering project has earned value $75,000 and planned value $60,000 but staff report 15,000 dollars behind schedule. The specific corrective response here is: Forecast a 13-day earliest finish after approved change and updated network logic.

D:

EV and AC reconciliation shows CV = +$10,000. This is evidence for ANOTHER case: A team has EV $95,000 and actual cost $85,000 and labels its project $10,000 over budget. The specific corrective response here is: Forecast a 13-day earliest finish after approved change and updated network logic.

Question 911

A postincident review considers: A baseline has a nine-day critical path but a scope change extends its controlling activity by four days without acceleration. Which principle most directly accounts for the behavior?

  1. A quality plan turns desired fitness into checkable standards and procedures.
  2. Extra time on an unchanged critical path extends completion absent other schedule adjustments.
  3. Work packages support estimating, control and accountability at an appropriate level.
  4. Predictive baselines support measuring approved performance and governing deviations.

Explanation

Correct Answer

B:

Extra time on an unchanged critical path extends completion absent other schedule adjustments. This explains the case: A baseline has a nine-day critical path but a scope change extends its controlling activity by four days without acceleration. The targeted action is: Forecast a 13-day earliest finish after approved change and updated network logic.

Incorrect Answers

A:

A quality plan turns desired fitness into checkable standards and procedures. This rationale better explains a DIFFERENT problem: A project promises that testing will be excellent but the quality plan includes no measurable thresholds. The key mechanism for the current situation is: Extra time on an unchanged critical path extends completion absent other schedule adjustments.

C:

Work packages support estimating, control and accountability at an appropriate level. This rationale better explains a DIFFERENT problem: A plan uses one undifferentiated task called build hospital with no deliverable ownership or progress measure. The key mechanism for the current situation is: Extra time on an unchanged critical path extends completion absent other schedule adjustments.

D:

Predictive baselines support measuring approved performance and governing deviations. This rationale better explains a DIFFERENT problem: A construction PM begins executing a fully specified plan but no one knows when baseline changes require sponsor approval. The key mechanism for the current situation is: Extra time on an unchanged critical path extends completion absent other schedule adjustments.

Question 912

What ongoing preventive practice would most reduce recurrence of: A baseline has a nine-day critical path but a scope change extends its controlling activity by four days without acceleration.

  1. Recalculate path durations after network updates.
  2. Validate variance formulas in reporting templates.
  3. Recalculate the network after approved scope changes.
  4. Record shared-resource agreements before major assignments.

Explanation

Correct Answer

C:

Recalculate the network after approved scope changes. This helps prevent recurrence of: A baseline has a nine-day critical path but a scope change extends its controlling activity by four days without acceleration. The required evidence of effective control is: The revised critical-path calculation shows the four-day increase in duration.

Incorrect Answers

A:

Recalculate path durations after network updates. That is a useful control for ANOTHER case: A four-activity project has paths A→C of 9 days and B→D of 13 days, but the manager budgets only nine days for completion. The current situation is better prevented by: Recalculate the network after approved scope changes.

B:

Validate variance formulas in reporting templates. That is a useful control for ANOTHER case: A project reports earned value of $40,000 and planned value of $50,000 but describes its schedule variance as positive. The current situation is better prevented by: Recalculate the network after approved scope changes.

D:

Record shared-resource agreements before major assignments. That is a useful control for ANOTHER case: A functional department loans staff to a project without acknowledging the project's fixed schedule responsibilities. The current situation is better prevented by: Recalculate the network after approved scope changes.

Question 913

At a construction planning unit, the review identifies: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred. Which response best addresses the specific project management problem?

  1. Derive cost variance from earned value and actual cost to identify true efficiency.
  2. Track current forecast and approved baseline as separate configuration-controlled artifacts.
  3. Calculate performance using earned work value and incurred cost rather than cash timing alone.
  4. Define verification measures, acceptance thresholds and inspection responsibilities.

Explanation

Correct Answer

A:

Derive cost variance from earned value and actual cost to identify true efficiency. This addresses the fictional case: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred. The project-management rationale is: EV-based control helps diagnose spending relative to delivered progress. Verify by: The analysis distinguishes unit-price dispute from cost performance.

Incorrect Answers

B:

Track current forecast and approved baseline as separate configuration-controlled artifacts. This would address a DIFFERENT fictional project situation: A schedule control board receives a late delivery forecast but the project report fails to distinguish a revised forecast from approved baseline. It is less directly applicable to: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred.

C:

Calculate performance using earned work value and incurred cost rather than cash timing alone. This would address a DIFFERENT fictional project situation: A contract administrator reports a favorable monthly cash flow and assumes project cost performance is therefore favorable. It is less directly applicable to: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred.

D:

Define verification measures, acceptance thresholds and inspection responsibilities. This would address a DIFFERENT fictional project situation: A project promises that testing will be excellent but the quality plan includes no measurable thresholds. It is less directly applicable to: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred.

Question 914

The project issue was: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred. Which outcome demonstrates that its remedy worked?

  1. The cost-control report identifies the deficit accurately.
  2. The analysis distinguishes unit-price dispute from cost performance.
  3. The report shows SV −$20,000 and an explained mitigation proposal.
  4. Approved design versions and signatures remain traceable across distributed reviewers.

Explanation

Correct Answer

B:

The analysis distinguishes unit-price dispute from cost performance. This validates the selected response: Derive cost variance from earned value and actual cost to identify true efficiency. The relevant management principle is: EV-based control helps diagnose spending relative to delivered progress.

Incorrect Answers

A:

The cost-control report identifies the deficit accurately. This is evidence for ANOTHER case: A project has earned value $70,000 and actual cost $88,000, yet the report describes its cost variance as favorable. The specific corrective response here is: Derive cost variance from earned value and actual cost to identify true efficiency.

C:

The report shows SV −$20,000 and an explained mitigation proposal. This is evidence for ANOTHER case: A team has planned value $100,000 and earned value $80,000 but uses an informal percent-of-time elapsed to claim on-schedule delivery. The specific corrective response here is: Derive cost variance from earned value and actual cost to identify true efficiency.

D:

Approved design versions and signatures remain traceable across distributed reviewers. This is evidence for ANOTHER case: A regional construction team uses a fully virtual delivery group but plans only in-person approvals with no digital document control. The specific corrective response here is: Derive cost variance from earned value and actual cost to identify true efficiency.

Question 915

For a construction planning unit, the documented failure was: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred. Which explanation is most accurate?

  1. Baselines should reflect authorized scope and funding changes while retaining traceability.
  2. Predictive variance must compare against legitimate current baselines.
  3. EV-based control helps diagnose spending relative to delivered progress.
  4. Distinct project components require coordinated but identifiable responsibilities.

Explanation

Correct Answer

C:

EV-based control helps diagnose spending relative to delivered progress. This explains the case: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred. The targeted action is: Derive cost variance from earned value and actual cost to identify true efficiency.

Incorrect Answers

A:

Baselines should reflect authorized scope and funding changes while retaining traceability. This rationale better explains a DIFFERENT problem: A construction cost report omits signed change orders from the controlled cost baseline. The key mechanism for the current situation is: EV-based control helps diagnose spending relative to delivered progress.

B:

Predictive variance must compare against legitimate current baselines. This rationale better explains a DIFFERENT problem: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless. The key mechanism for the current situation is: EV-based control helps diagnose spending relative to delivered progress.

D:

Distinct project components require coordinated but identifiable responsibilities. This rationale better explains a DIFFERENT problem: A project lists stakeholder acceptance and maintenance training as tasks inside design engineering without distinct owners. The key mechanism for the current situation is: EV-based control helps diagnose spending relative to delivered progress.

Question 916

Which recurring governance check best addresses the risk of repeating: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred.

  1. Validate baseline IDs in status reporting.
  2. Close actions only after outcome verification.
  3. Review sign conventions with project analysts.
  4. Require earned-value context in significant cost exception reviews.

Explanation

Correct Answer

D:

Require earned-value context in significant cost exception reviews. This helps prevent recurrence of: A forecast says a supplier's invoice is high but does not compare work accomplished with cost incurred. The required evidence of effective control is: The analysis distinguishes unit-price dispute from cost performance.

Incorrect Answers

A:

Validate baseline IDs in status reporting. That is a useful control for ANOTHER case: A team retains an obsolete scope baseline after an approved procurement redesign, making reported variance meaningless. The current situation is better prevented by: Require earned-value context in significant cost exception reviews.

B:

Close actions only after outcome verification. That is a useful control for ANOTHER case: A team logs corrective actions without connecting them to a specific measured deviation. The current situation is better prevented by: Require earned-value context in significant cost exception reviews.

C:

Review sign conventions with project analysts. That is a useful control for ANOTHER case: An engineering project has earned value $75,000 and planned value $60,000 but staff report 15,000 dollars behind schedule. The current situation is better prevented by: Require earned-value context in significant cost exception reviews.

Question 917

During a project review, stakeholders report: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios. What should the team do first?

  1. Model actor interactions and alternate flows in a use case.
  2. Elicit real operating constraints and document an offline-use scenario with acceptance tests.
  3. Conduct inclusive elicitation with representative accessibility participants and amend acceptance criteria.
  4. Adapt stakeholder communication with appropriate localization and comprehension checks.

Explanation

Correct Answer

B:

Elicit real operating constraints and document an offline-use scenario with acceptance tests. This addresses the fictional case: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios. The project-management rationale is: Requirements must reflect the actual environment, including exception cases. Verify by: The pilot succeeds without continuous connectivity as specified.

Incorrect Answers

A:

Model actor interactions and alternate flows in a use case. This would address a DIFFERENT fictional project situation: A checkout feature description lacks any description of who initiates payment and how failure should be handled. It is less directly applicable to: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios.

C:

Conduct inclusive elicitation with representative accessibility participants and amend acceptance criteria. This would address a DIFFERENT fictional project situation: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction. It is less directly applicable to: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios.

D:

Adapt stakeholder communication with appropriate localization and comprehension checks. This would address a DIFFERENT fictional project situation: A global team distributes a release briefing in one language without checking whether affected partner sites can understand it. It is less directly applicable to: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios.

Question 918

Following the proposed correction, what observation confirms success: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios.

  1. Approved retention rules identify proper exceptions and affected data categories.
  2. A common decision table records one agreed set of rules.
  3. The pilot succeeds without continuous connectivity as specified.
  4. Prioritized needs include actual support incidents and user outcomes.

Explanation

Correct Answer

C:

The pilot succeeds without continuous connectivity as specified. This validates the selected response: Elicit real operating constraints and document an offline-use scenario with acceptance tests. The relevant management principle is: Requirements must reflect the actual environment, including exception cases.

Incorrect Answers

A:

Approved retention rules identify proper exceptions and affected data categories. This is evidence for ANOTHER case: A delivery team accepts contradictory requirements 'retain all records forever' and 'delete all records after one year'. The specific corrective response here is: Elicit real operating constraints and document an offline-use scenario with acceptance tests.

B:

A common decision table records one agreed set of rules. This is evidence for ANOTHER case: Two policy teams disagree about approval rules for an expense app and submit incompatible spreadsheets. The specific corrective response here is: Elicit real operating constraints and document an offline-use scenario with acceptance tests.

D:

Prioritized needs include actual support incidents and user outcomes. This is evidence for ANOTHER case: Customer support reports defect pain in informal chats, but analysts only collect feature requests from the sales team. The specific corrective response here is: Elicit real operating constraints and document an offline-use scenario with acceptance tests.

Question 919

Which underlying planning or business-analysis mechanism explains: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios.

  1. A requirement is only testable when expected behavior can be observed.
  2. End-to-end traceability helps prevent omitted validation and scope drift.
  3. BA practice should reflect differences across delivery approaches.
  4. Requirements must reflect the actual environment, including exception cases.

Explanation

Correct Answer

D:

Requirements must reflect the actual environment, including exception cases. This explains the case: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios. The targeted action is: Elicit real operating constraints and document an offline-use scenario with acceptance tests.

Incorrect Answers

A:

A requirement is only testable when expected behavior can be observed. This rationale better explains a DIFFERENT problem: A customer claims the new reporting dashboard is correct without comparing it to a validated example transaction. The key mechanism for the current situation is: Requirements must reflect the actual environment, including exception cases.

B:

End-to-end traceability helps prevent omitted validation and scope drift. This rationale better explains a DIFFERENT problem: A traceability spreadsheet links every feature to one design but none to a verifying test or accepted business objective. The key mechanism for the current situation is: Requirements must reflect the actual environment, including exception cases.

C:

BA practice should reflect differences across delivery approaches. This rationale better explains a DIFFERENT problem: A hybrid deployment requires fixed audit documentation but allows iterative design of user training; analysts insist on one documentation cadence for both. The key mechanism for the current situation is: Requirements must reflect the actual environment, including exception cases.

Question 920

For the previous project issue, select the best preventive control: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios.

  1. Review environmental conditions with field users.
  2. Include accessibility personas in elicitation plans.
  3. Train facilitators to avoid leading questions.
  4. Confirm reporting purpose before selecting format.

Explanation

Correct Answer

A:

Review environmental conditions with field users. This helps prevent recurrence of: A field operations team submits an email about an offline-use need, but the BA captures only cloud-connected scenarios. The required evidence of effective control is: The pilot succeeds without continuous connectivity as specified.

Incorrect Answers

B:

Include accessibility personas in elicitation plans. That is a useful control for ANOTHER case: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction. The current situation is better prevented by: Review environmental conditions with field users.

C:

Train facilitators to avoid leading questions. That is a useful control for ANOTHER case: A BA asks a small focus group whether everyone likes a feature but never captures why participants struggle. The current situation is better prevented by: Review environmental conditions with field users.

D:

Confirm reporting purpose before selecting format. That is a useful control for ANOTHER case: Executives need a weekly decision summary but the BA sends raw API test logs with no business impact explanation. The current situation is better prevented by: Review environmental conditions with field users.