Question 890
How should the project team verify a successful response to: A project team approves a feature list but has no measurable criterion for accepting the final release.
Explanation
Correct Answer
Acceptance testing traces each feature to an agreed pass or fail condition. This validates the selected response: Define testable deliverable acceptance criteria with the customer before delivery. The relevant management principle is: Clearly defined deliverables and quality criteria support controlled acceptance.
Incorrect Answers
The handover package includes required safety evidence and accepted residual items. This is evidence for ANOTHER case: A transition meeting closes a manufacturing project while unresolved mandatory safety documentation remains with no owner. The specific corrective response here is: Define testable deliverable acceptance criteria with the customer before delivery.
A tabletop exercise finds an approved path before the permit deadline. This is evidence for ANOTHER case: A facility project has no risk response if its sole permit reviewer becomes unavailable. The specific corrective response here is: Define testable deliverable acceptance criteria with the customer before delivery.
The portfolio review compares competing investments and strategic alignment across distinct initiatives. This is evidence for ANOTHER case: A university investment committee labels its unrelated campus construction and digital learning initiatives a single program. The specific corrective response here is: Define testable deliverable acceptance criteria with the customer before delivery.