Question 850
The project issue was: A manufacturing engineer schedules final assembly before a required prototype test because both have available staff. Which outcome demonstrates that its remedy worked?
Explanation
Correct Answer
The schedule prevents premature assembly even when resources are free. This validates the selected response: Correct the logical dependency so prototype acceptance precedes assembly. The relevant management principle is: Activity sequencing is driven by dependencies, not only resource capacity.
Incorrect Answers
The status sheet records SV = −$10,000 with context about being behind planned value. This is evidence for ANOTHER case: A project reports earned value of $40,000 and planned value of $50,000 but describes its schedule variance as positive. The specific corrective response here is: Correct the logical dependency so prototype acceptance precedes assembly.
The schedule contains the approval event linked to the correct predecessor work. This is evidence for ANOTHER case: A team calls a zero-effort contract signoff a work package requiring three engineers for two weeks. The specific corrective response here is: Correct the logical dependency so prototype acceptance precedes assembly.
The cost-control report identifies the deficit accurately. This is evidence for ANOTHER case: A project has earned value $70,000 and actual cost $88,000, yet the report describes its cost variance as favorable. The specific corrective response here is: Correct the logical dependency so prototype acceptance precedes assembly.