Question 830
For a national logistics rollout, what is the strongest acceptance evidence after addressing: Multiple work packages share the same engineer at the same time while a plan assumes each has full capacity.
Explanation
Correct Answer
The revised resource histogram shows feasible utilization and changed schedule impact. This validates the selected response: Level or negotiate resource assignments according to actual availability and task dependencies. The relevant management principle is: Resource feasibility affects schedule credibility and productivity.
Incorrect Answers
The action log lists responsible owners, deadlines and recovery decisions. This is evidence for ANOTHER case: A team logs each known supplier delay only as a high probability risk and leaves the issue owner blank. The specific corrective response here is: Level or negotiate resource assignments according to actual availability and task dependencies.
Approved baselines and risk plans show response owners and reserved contingency. This is evidence for ANOTHER case: A delivery plan has a detailed Gantt chart but does not specify authorized risk response costs. The specific corrective response here is: Level or negotiate resource assignments according to actual availability and task dependencies.
The initiative charter has a unique deliverable while monthly readings remain in the operating plan. This is evidence for ANOTHER case: A regional utility calls its repeated monthly meter-reading service a project even though the process has no finish date. The specific corrective response here is: Level or negotiate resource assignments according to actual availability and task dependencies.