  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 110

Question 1090

The project issue was: A safety inspector asks for evidence of a new mandatory standard, but a team defers compliance as a possible future risk. Which outcome demonstrates that its remedy worked?

  1. Authorized modifications appear in approved baseline revisions before field execution.
  2. Acceptance records demonstrate compliance with the applicable standard before handover.
  3. Independent evaluation records document a fair, reviewable procurement decision.
  4. Acceptance testing traces each feature to an agreed pass or fail condition.

Explanation

Correct Answer

B:

Acceptance records demonstrate compliance with the applicable standard before handover. This validates the selected response: Treat the currently applicable standard as an enforceable scope and quality constraint. The relevant management principle is: Existing regulations are constraints; only uncertain upcoming changes belong in risk planning.

Incorrect Answers

A:

Authorized modifications appear in approved baseline revisions before field execution. This is evidence for ANOTHER case: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes. The specific corrective response here is: Treat the currently applicable standard as an enforceable scope and quality constraint.

C:

Independent evaluation records document a fair, reviewable procurement decision. This is evidence for ANOTHER case: A manager privately awards a contract to a close relative without disclosing the relationship. The specific corrective response here is: Treat the currently applicable standard as an enforceable scope and quality constraint.

D:

Acceptance testing traces each feature to an agreed pass or fail condition. This is evidence for ANOTHER case: A project team approves a feature list but has no measurable criterion for accepting the final release. The specific corrective response here is: Treat the currently applicable standard as an enforceable scope and quality constraint.

Question 1091

For a manufacturing equipment project, the documented failure was: A safety inspector asks for evidence of a new mandatory standard, but a team defers compliance as a possible future risk. Which explanation is most accurate?

  1. Predictive planning suits comparatively stable, sequential and tightly regulated deliverables.
  2. Delivering a unique location change is finite work even when the resulting activity is ongoing.
  3. Existing regulations are constraints; only uncertain upcoming changes belong in risk planning.
  4. Delivery completion and value realization are distinct measures.

Explanation

Correct Answer

C:

Existing regulations are constraints; only uncertain upcoming changes belong in risk planning. This explains the case: A safety inspector asks for evidence of a new mandatory standard, but a team defers compliance as a possible future risk. The targeted action is: Treat the currently applicable standard as an enforceable scope and quality constraint.

Incorrect Answers

A:

Predictive planning suits comparatively stable, sequential and tightly regulated deliverables. This rationale better explains a DIFFERENT problem: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes. The key mechanism for the current situation is: Existing regulations are constraints; only uncertain upcoming changes belong in risk planning.

B:

Delivering a unique location change is finite work even when the resulting activity is ongoing. This rationale better explains a DIFFERENT problem: A temporary warehouse relocation has a defined final operating site, but managers treat it as routine daily warehousing. The key mechanism for the current situation is: Existing regulations are constraints; only uncertain upcoming changes belong in risk planning.

D:

Delivery completion and value realization are distinct measures. This rationale better explains a DIFFERENT problem: A product experiment delivers a feature but does not measure whether customer service time actually improved. The key mechanism for the current situation is: Existing regulations are constraints; only uncertain upcoming changes belong in risk planning.

Question 1092

Which recurring governance check best addresses the risk of repeating: A safety inspector asks for evidence of a new mandatory standard, but a team defers compliance as a possible future risk.

  1. Check initiation packages for binding constraints.
  2. Include a named receiving service owner in project definitions.
  3. Trace material response plans to the budget baseline.
  4. Maintain the current regulatory baseline in the project register.

Explanation

Correct Answer

D:

Maintain the current regulatory baseline in the project register. This helps prevent recurrence of: A safety inspector asks for evidence of a new mandatory standard, but a team defers compliance as a possible future risk. The required evidence of effective control is: Acceptance records demonstrate compliance with the applicable standard before handover.

Incorrect Answers

A:

Check initiation packages for binding constraints. That is a useful control for ANOTHER case: A hospital rollout must use approved encryption regardless of cost, but staff record this mandatory condition as an optional risk. The current situation is better prevented by: Maintain the current regulatory baseline in the project register.

B:

Include a named receiving service owner in project definitions. That is a useful control for ANOTHER case: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion. The current situation is better prevented by: Maintain the current regulatory baseline in the project register.

C:

Trace material response plans to the budget baseline. That is a useful control for ANOTHER case: A project adopts a formal risk strategy but does not budget any implementation resources for its selected mitigation. The current situation is better prevented by: Maintain the current regulatory baseline in the project register.

Question 1093

During a project review, stakeholders report: A project changes its customer-facing release date but does not inform warehouse training and support teams. What should the team do first?

  1. Develop risk response plans and fund appropriate contingencies within governance.
  2. Update the integrated communications and transition plans along with the schedule change.
  3. Keep the supplier as an active stakeholder until their material work and influence end.
  4. Connect the charter and benefits plan to measurable fundraising outcomes.

Explanation

Correct Answer

B:

Update the integrated communications and transition plans along with the schedule change. This addresses the fictional case: A project changes its customer-facing release date but does not inform warehouse training and support teams. The project-management rationale is: Coordinated plans prevent downstream dependencies from being overlooked. Verify by: Receiving teams acknowledge revised timing and readiness responsibilities.

Incorrect Answers

A:

Develop risk response plans and fund appropriate contingencies within governance. This would address a DIFFERENT fictional project situation: A delivery plan has a detailed Gantt chart but does not specify authorized risk response costs. It is less directly applicable to: A project changes its customer-facing release date but does not inform warehouse training and support teams.

C:

Keep the supplier as an active stakeholder until their material work and influence end. This would address a DIFFERENT fictional project situation: A project removes the supplier from its stakeholder register after contract signature even though supplier approval is needed for integration tests. It is less directly applicable to: A project changes its customer-facing release date but does not inform warehouse training and support teams.

D:

Connect the charter and benefits plan to measurable fundraising outcomes. This would address a DIFFERENT fictional project situation: A charity launches a fundraising technology project without documenting how the delivered platform advances target donations. It is less directly applicable to: A project changes its customer-facing release date but does not inform warehouse training and support teams.

Question 1094

Following the proposed correction, what observation confirms success: A project changes its customer-facing release date but does not inform warehouse training and support teams.

  1. Approved baselines and risk plans show response owners and reserved contingency.
  2. The schedule shows a dated approval event linked to a realistic installation activity.
  3. Receiving teams acknowledge revised timing and readiness responsibilities.
  4. The estimate includes shared scope assumptions and visible uncertainty.

Explanation

Correct Answer

C:

Receiving teams acknowledge revised timing and readiness responsibilities. This validates the selected response: Update the integrated communications and transition plans along with the schedule change. The relevant management principle is: Coordinated plans prevent downstream dependencies from being overlooked.

Incorrect Answers

A:

Approved baselines and risk plans show response owners and reserved contingency. This is evidence for ANOTHER case: A delivery plan has a detailed Gantt chart but does not specify authorized risk response costs. The specific corrective response here is: Update the integrated communications and transition plans along with the schedule change.

B:

The schedule shows a dated approval event linked to a realistic installation activity. This is evidence for ANOTHER case: A sponsor treats a zero-duration regulatory approval milestone as five days of actual installation effort. The specific corrective response here is: Update the integrated communications and transition plans along with the schedule change.

D:

The estimate includes shared scope assumptions and visible uncertainty. This is evidence for ANOTHER case: A planning team asks employees to estimate a complex migration separately but then averages incompatible assumptions without discussion. The specific corrective response here is: Update the integrated communications and transition plans along with the schedule change.

Question 1095

Which underlying planning or business-analysis mechanism explains: A project changes its customer-facing release date but does not inform warehouse training and support teams.

  1. Resource feasibility affects schedule credibility and productivity.
  2. Planning should treat critical single points of failure as threats to schedule objectives.
  3. Professional leadership combines accountability with transparent communication.
  4. Coordinated plans prevent downstream dependencies from being overlooked.

Explanation

Correct Answer

D:

Coordinated plans prevent downstream dependencies from being overlooked. This explains the case: A project changes its customer-facing release date but does not inform warehouse training and support teams. The targeted action is: Update the integrated communications and transition plans along with the schedule change.

Incorrect Answers

A:

Resource feasibility affects schedule credibility and productivity. This rationale better explains a DIFFERENT problem: Multiple work packages share the same engineer at the same time while a plan assumes each has full capacity. The key mechanism for the current situation is: Coordinated plans prevent downstream dependencies from being overlooked.

B:

Planning should treat critical single points of failure as threats to schedule objectives. This rationale better explains a DIFFERENT problem: A facility project has no risk response if its sole permit reviewer becomes unavailable. The key mechanism for the current situation is: Coordinated plans prevent downstream dependencies from being overlooked.

C:

Professional leadership combines accountability with transparent communication. This rationale better explains a DIFFERENT problem: A junior PM withholds forecast problems because they believe leadership means never admitting uncertainty. The key mechanism for the current situation is: Coordinated plans prevent downstream dependencies from being overlooked.

Question 1096

For the previous project issue, select the best preventive control: A project changes its customer-facing release date but does not inform warehouse training and support teams.

  1. Trigger cross-workstream impact checks on baseline changes.
  2. Reconcile estimates against deliverable decomposition.
  3. Update stakeholder engagement as delivery dependencies change.
  4. Record the rationale for lifecycle selection at initiation.

Explanation

Correct Answer

A:

Trigger cross-workstream impact checks on baseline changes. This helps prevent recurrence of: A project changes its customer-facing release date but does not inform warehouse training and support teams. The required evidence of effective control is: Receiving teams acknowledge revised timing and readiness responsibilities.

Incorrect Answers

B:

Reconcile estimates against deliverable decomposition. That is a useful control for ANOTHER case: A team has a strong cost estimate but has not included training work in the planned scope. The current situation is better prevented by: Trigger cross-workstream impact checks on baseline changes.

C:

Update stakeholder engagement as delivery dependencies change. That is a useful control for ANOTHER case: A project removes the supplier from its stakeholder register after contract signature even though supplier approval is needed for integration tests. The current situation is better prevented by: Trigger cross-workstream impact checks on baseline changes.

D:

Record the rationale for lifecycle selection at initiation. That is a useful control for ANOTHER case: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes. The current situation is better prevented by: Trigger cross-workstream impact checks on baseline changes.

Question 1097

For a small product delivery team, a delivery problem is reported: A manager privately awards a contract to a close relative without disclosing the relationship. Which action fits the situation?

  1. Reject the improper exchange, protect information, and follow formal ethical reporting channels.
  2. Revisit assumptions and consider an adaptive planning cadence with timely customer validation.
  3. Disclose the conflict and recuse from decisions under organizational procurement ethics.
  4. Keep the supplier as an active stakeholder until their material work and influence end.

Explanation

Correct Answer

C:

Disclose the conflict and recuse from decisions under organizational procurement ethics. This addresses the fictional case: A manager privately awards a contract to a close relative without disclosing the relationship. The project-management rationale is: Conflicts of interest threaten fairness even when the proposal could be technically adequate. Verify by: Independent evaluation records document a fair, reviewable procurement decision.

Incorrect Answers

A:

Reject the improper exchange, protect information, and follow formal ethical reporting channels. This would address a DIFFERENT fictional project situation: A procurement manager requests a hidden bid advantage from a supplier in exchange for confidential evaluation scores. It is less directly applicable to: A manager privately awards a contract to a close relative without disclosing the relationship.

B:

Revisit assumptions and consider an adaptive planning cadence with timely customer validation. This would address a DIFFERENT fictional project situation: A market-testing initiative keeps an immutable specification after customer interviews reveal the solution solves the wrong need. It is less directly applicable to: A manager privately awards a contract to a close relative without disclosing the relationship.

D:

Keep the supplier as an active stakeholder until their material work and influence end. This would address a DIFFERENT fictional project situation: A project removes the supplier from its stakeholder register after contract signature even though supplier approval is needed for integration tests. It is less directly applicable to: A manager privately awards a contract to a close relative without disclosing the relationship.

Question 1098

How should the project team verify a successful response to: A manager privately awards a contract to a close relative without disclosing the relationship.

  1. The selection rationale connects funded initiatives to approved strategic outcomes.
  2. The assumption log records evidence, owner and decision on schedule changes.
  3. The action plan addresses repeatable process failures rather than only assigning blame.
  4. Independent evaluation records document a fair, reviewable procurement decision.

Explanation

Correct Answer

D:

Independent evaluation records document a fair, reviewable procurement decision. This validates the selected response: Disclose the conflict and recuse from decisions under organizational procurement ethics. The relevant management principle is: Conflicts of interest threaten fairness even when the proposal could be technically adequate.

Incorrect Answers

A:

The selection rationale connects funded initiatives to approved strategic outcomes. This is evidence for ANOTHER case: A portfolio steering group always funds the project with the highest local ROI although it conflicts with organizational priorities. The specific corrective response here is: Disclose the conflict and recuse from decisions under organizational procurement ethics.

B:

The assumption log records evidence, owner and decision on schedule changes. This is evidence for ANOTHER case: A new app project assumes that all partner data will arrive by March without independent confirmation. The specific corrective response here is: Disclose the conflict and recuse from decisions under organizational procurement ethics.

C:

The action plan addresses repeatable process failures rather than only assigning blame. This is evidence for ANOTHER case: A retrospective blames one employee for recurring defect escapes without reviewing workflow causes. The specific corrective response here is: Disclose the conflict and recuse from decisions under organizational procurement ethics.

Question 1099

A project team asks why this occurs: A manager privately awards a contract to a close relative without disclosing the relationship. Which project management principle best explains it?

  1. Conflicts of interest threaten fairness even when the proposal could be technically adequate.
  2. PMI's ethical expectations emphasize honesty, responsibility, respect and fairness.
  3. Respect for rights and property applies to project delivery, not only external procurement.
  4. Approved frameworks protect scope, cost and time commitments from informal changes.

Explanation

Correct Answer

A:

Conflicts of interest threaten fairness even when the proposal could be technically adequate. This explains the case: A manager privately awards a contract to a close relative without disclosing the relationship. The targeted action is: Disclose the conflict and recuse from decisions under organizational procurement ethics.

Incorrect Answers

B:

PMI's ethical expectations emphasize honesty, responsibility, respect and fairness. This rationale better explains a DIFFERENT problem: A procurement manager requests a hidden bid advantage from a supplier in exchange for confidential evaluation scores. The key mechanism for the current situation is: Conflicts of interest threaten fairness even when the proposal could be technically adequate.

C:

Respect for rights and property applies to project delivery, not only external procurement. This rationale better explains a DIFFERENT problem: Two internal departments dispute a licensed design and one party proposes using the material without consent. The key mechanism for the current situation is: Conflicts of interest threaten fairness even when the proposal could be technically adequate.

D:

Approved frameworks protect scope, cost and time commitments from informal changes. This rationale better explains a DIFFERENT problem: A client requests an extra feature that exceeds approved scope, and the team begins work without a change decision. The key mechanism for the current situation is: Conflicts of interest threaten fairness even when the proposal could be technically adequate.

Question 1100

At a small product delivery team, the team wants to avoid repeating: A manager privately awards a contract to a close relative without disclosing the relationship. Which safeguard should it retain?

  1. Check new charter requests for an end condition and distinct deliverable.
  2. Require conflicts to be disclosed before sourcing work.
  3. Maintain the current regulatory baseline in the project register.
  4. Coach new coordinators in structured facilitation.

Explanation

Correct Answer

B:

Require conflicts to be disclosed before sourcing work. This helps prevent recurrence of: A manager privately awards a contract to a close relative without disclosing the relationship. The required evidence of effective control is: Independent evaluation records document a fair, reviewable procurement decision.

Incorrect Answers

A:

Check new charter requests for an end condition and distinct deliverable. That is a useful control for ANOTHER case: A regional utility calls its repeated monthly meter-reading service a project even though the process has no finish date. The current situation is better prevented by: Require conflicts to be disclosed before sourcing work.

C:

Maintain the current regulatory baseline in the project register. That is a useful control for ANOTHER case: A safety inspector asks for evidence of a new mandatory standard, but a team defers compliance as a possible future risk. The current situation is better prevented by: Require conflicts to be disclosed before sourcing work.

D:

Coach new coordinators in structured facilitation. That is a useful control for ANOTHER case: An inexperienced coordinator repeatedly interrupts senior subject experts and misses material project constraints. The current situation is better prevented by: Require conflicts to be disclosed before sourcing work.