McAfee-Secured Website

Exam Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 108

Question 1070

For a utilities capital-investment project, what is the strongest acceptance evidence after addressing: A transition meeting closes a manufacturing project while unresolved mandatory safety documentation remains with no owner.

  1. The handover package includes required safety evidence and accepted residual items.
  2. Approved baselines and risk plans show response owners and reserved contingency.
  3. The approved WBS and estimate both include authorized training work.
  4. A completed acceptance and transition record precedes routine operations at the new site.

Explanation

Correct Answer

A:

The handover package includes required safety evidence and accepted residual items. This validates the selected response: Keep closure contingent on required compliance deliverables and documented exception approval. The relevant management principle is: Closure confirms agreed acceptance, not merely that the scheduled date arrived.

Incorrect Answers

B:

Approved baselines and risk plans show response owners and reserved contingency. This is evidence for ANOTHER case: A delivery plan has a detailed Gantt chart but does not specify authorized risk response costs. The specific corrective response here is: Keep closure contingent on required compliance deliverables and documented exception approval.

C:

The approved WBS and estimate both include authorized training work. This is evidence for ANOTHER case: A team has a strong cost estimate but has not included training work in the planned scope. The specific corrective response here is: Keep closure contingent on required compliance deliverables and documented exception approval.

D:

A completed acceptance and transition record precedes routine operations at the new site. This is evidence for ANOTHER case: A temporary warehouse relocation has a defined final operating site, but managers treat it as routine daily warehousing. The specific corrective response here is: Keep closure contingent on required compliance deliverables and documented exception approval.

Question 1071

A postincident review considers: A transition meeting closes a manufacturing project while unresolved mandatory safety documentation remains with no owner. Which principle most directly accounts for the behavior?

  1. Quality objectives need verifiable standards to guide assurance and acceptance.
  2. Closure confirms agreed acceptance, not merely that the scheduled date arrived.
  3. Stakeholder relevance depends on project impact, not just procurement phase.
  4. Strategic change alters benefit definitions and delivery priorities.

Explanation

Correct Answer

B:

Closure confirms agreed acceptance, not merely that the scheduled date arrived. This explains the case: A transition meeting closes a manufacturing project while unresolved mandatory safety documentation remains with no owner. The targeted action is: Keep closure contingent on required compliance deliverables and documented exception approval.

Incorrect Answers

A:

Quality objectives need verifiable standards to guide assurance and acceptance. This rationale better explains a DIFFERENT problem: A quality plan specifies that software must be excellent but has no measurable tests. The key mechanism for the current situation is: Closure confirms agreed acceptance, not merely that the scheduled date arrived.

C:

Stakeholder relevance depends on project impact, not just procurement phase. This rationale better explains a DIFFERENT problem: A project removes the supplier from its stakeholder register after contract signature even though supplier approval is needed for integration tests. The key mechanism for the current situation is: Closure confirms agreed acceptance, not merely that the scheduled date arrived.

D:

Strategic change alters benefit definitions and delivery priorities. This rationale better explains a DIFFERENT problem: A sponsor changes the project purpose from cost savings to regulatory compliance without reexamining planned outcomes. The key mechanism for the current situation is: Closure confirms agreed acceptance, not merely that the scheduled date arrived.

Question 1072

What ongoing preventive practice would most reduce recurrence of: A transition meeting closes a manufacturing project while unresolved mandatory safety documentation remains with no owner.

  1. Reject nonmeasurable quality definitions at planning review.
  2. Revalidate business-case assumptions at authorization gates.
  3. Use closure readiness criteria with required compliance items.
  4. Reserve a postdeployment measurement window in the benefits plan.

Explanation

Correct Answer

C:

Use closure readiness criteria with required compliance items. This helps prevent recurrence of: A transition meeting closes a manufacturing project while unresolved mandatory safety documentation remains with no owner. The required evidence of effective control is: The handover package includes required safety evidence and accepted residual items.

Incorrect Answers

A:

Reject nonmeasurable quality definitions at planning review. That is a useful control for ANOTHER case: A quality plan specifies that software must be excellent but has no measurable tests. The current situation is better prevented by: Use closure readiness criteria with required compliance items.

B:

Revalidate business-case assumptions at authorization gates. That is a useful control for ANOTHER case: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate. The current situation is better prevented by: Use closure readiness criteria with required compliance items.

D:

Reserve a postdeployment measurement window in the benefits plan. That is a useful control for ANOTHER case: A product experiment delivers a feature but does not measure whether customer service time actually improved. The current situation is better prevented by: Use closure readiness criteria with required compliance items.

Question 1073

At a distributed delivery organization, the review identifies: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion. Which response best addresses the specific project management problem?

  1. Define completion at solution acceptance and formal handover to operations rather than business service termination.
  2. Evaluate a suitable adaptive or hybrid lifecycle with incremental stakeholder feedback rather than forcing an unchanging plan.
  3. Charter the one-time warehouse move as a project with planned operational handoff.
  4. Route material schedule changes through the agreed integrated change-control process.

Explanation

Correct Answer

A:

Define completion at solution acceptance and formal handover to operations rather than business service termination. This addresses the fictional case: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion. The project-management rationale is: A project's unique deliverable can support an indefinite operating capability after closure. Verify by: Signed transition criteria move day-to-day ownership to the operations team.

Incorrect Answers

B:

Evaluate a suitable adaptive or hybrid lifecycle with incremental stakeholder feedback rather than forcing an unchanging plan. This would address a DIFFERENT fictional project situation: A manufacturing team freezes all product details up front despite weekly regulatory discoveries that regularly change requirements. It is less directly applicable to: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion.

C:

Charter the one-time warehouse move as a project with planned operational handoff. This would address a DIFFERENT fictional project situation: A temporary warehouse relocation has a defined final operating site, but managers treat it as routine daily warehousing. It is less directly applicable to: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion.

D:

Route material schedule changes through the agreed integrated change-control process. This would address a DIFFERENT fictional project situation: A project team revises the delivery date by email but never updates the approved schedule baseline. It is less directly applicable to: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion.

Question 1074

The project issue was: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion. Which outcome demonstrates that its remedy worked?

  1. Each funded project has explicit start, completion and accepted output criteria.
  2. Signed transition criteria move day-to-day ownership to the operations team.
  3. Independent evaluation records document a fair, reviewable procurement decision.
  4. The action plan addresses repeatable process failures rather than only assigning blame.

Explanation

Correct Answer

B:

Signed transition criteria move day-to-day ownership to the operations team. This validates the selected response: Define completion at solution acceptance and formal handover to operations rather than business service termination. The relevant management principle is: A project's unique deliverable can support an indefinite operating capability after closure.

Incorrect Answers

A:

Each funded project has explicit start, completion and accepted output criteria. This is evidence for ANOTHER case: A nonprofit calls a collection of separate volunteer events one project despite no shared end result or integrated scope. The specific corrective response here is: Define completion at solution acceptance and formal handover to operations rather than business service termination.

C:

Independent evaluation records document a fair, reviewable procurement decision. This is evidence for ANOTHER case: A manager privately awards a contract to a close relative without disclosing the relationship. The specific corrective response here is: Define completion at solution acceptance and formal handover to operations rather than business service termination.

D:

The action plan addresses repeatable process failures rather than only assigning blame. This is evidence for ANOTHER case: A retrospective blames one employee for recurring defect escapes without reviewing workflow causes. The specific corrective response here is: Define completion at solution acceptance and formal handover to operations rather than business service termination.

Question 1075

For a distributed delivery organization, the documented failure was: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion. Which explanation is most accurate?

  1. Work grouping follows purpose and unique deliverables rather than mere shared staffing.
  2. Conflicts of interest threaten fairness even when the proposal could be technically adequate.
  3. A project's unique deliverable can support an indefinite operating capability after closure.
  4. Effective meetings use synchronous time where discussion adds value.

Explanation

Correct Answer

C:

A project's unique deliverable can support an indefinite operating capability after closure. This explains the case: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion. The targeted action is: Define completion at solution acceptance and formal handover to operations rather than business service termination.

Incorrect Answers

A:

Work grouping follows purpose and unique deliverables rather than mere shared staffing. This rationale better explains a DIFFERENT problem: A nonprofit calls a collection of separate volunteer events one project despite no shared end result or integrated scope. The key mechanism for the current situation is: A project's unique deliverable can support an indefinite operating capability after closure.

B:

Conflicts of interest threaten fairness even when the proposal could be technically adequate. This rationale better explains a DIFFERENT problem: A manager privately awards a contract to a close relative without disclosing the relationship. The key mechanism for the current situation is: A project's unique deliverable can support an indefinite operating capability after closure.

D:

Effective meetings use synchronous time where discussion adds value. This rationale better explains a DIFFERENT problem: Weekly status meetings consist only of reading slides already distributed, while project blockers go unaddressed. The key mechanism for the current situation is: A project's unique deliverable can support an indefinite operating capability after closure.

Question 1076

Which recurring governance check best addresses the risk of repeating: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion.

  1. Record the rationale for lifecycle selection at initiation.
  2. Reassess lifecycle suitability when uncertainty changes materially.
  3. Separate ideation from decision ranking in workshops.
  4. Include a named receiving service owner in project definitions.

Explanation

Correct Answer

D:

Include a named receiving service owner in project definitions. This helps prevent recurrence of: A new fulfillment product will continue operating for years, so its implementation team refuses to define project completion. The required evidence of effective control is: Signed transition criteria move day-to-day ownership to the operations team.

Incorrect Answers

A:

Record the rationale for lifecycle selection at initiation. That is a useful control for ANOTHER case: A bridge replacement has approved engineering drawings and tightly constrained safety dependencies, but a team insists on weekly unrestricted scope changes. The current situation is better prevented by: Include a named receiving service owner in project definitions.

B:

Reassess lifecycle suitability when uncertainty changes materially. That is a useful control for ANOTHER case: A manufacturing team freezes all product details up front despite weekly regulatory discoveries that regularly change requirements. The current situation is better prevented by: Include a named receiving service owner in project definitions.

C:

Separate ideation from decision ranking in workshops. That is a useful control for ANOTHER case: A team rejects unusual design possibilities before exploring options for a new delivery process. The current situation is better prevented by: Include a named receiving service owner in project definitions.

Question 1077

During a project review, stakeholders report: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate. What should the team do first?

  1. Record relevant stakeholder roles, interests, influence and planned engagement.
  2. Refresh assumptions, cost and benefits forecasts and present the decision transparently.
  3. Sequence the test work according to lab capacity and resource constraints.
  4. Apply the approved information classification and stakeholder-specific communication channel.

Explanation

Correct Answer

B:

Refresh assumptions, cost and benefits forecasts and present the decision transparently. This addresses the fictional case: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate. The project-management rationale is: Benefit planning informs authorization and investment trade-offs. Verify by: The sponsor signs an initiation decision using current values and confidence levels.

Incorrect Answers

A:

Record relevant stakeholder roles, interests, influence and planned engagement. This would address a DIFFERENT fictional project situation: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. It is less directly applicable to: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate.

C:

Sequence the test work according to lab capacity and resource constraints. This would address a DIFFERENT fictional project situation: An offshore development team plans 12 parallel testing activities on one shared lab environment. It is less directly applicable to: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate.

D:

Apply the approved information classification and stakeholder-specific communication channel. This would address a DIFFERENT fictional project situation: Project teams send confidential risk details to a broad mailing list despite a stakeholder communication plan limiting distribution. It is less directly applicable to: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate.

Question 1078

Following the proposed correction, what observation confirms success: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate.

  1. Milestone status changes only on the documented event rather than elapsed working time.
  2. The risk register contains uncertain event descriptions, owners and responses.
  3. The sponsor signs an initiation decision using current values and confidence levels.
  4. Experts confirm that the documented constraints reflect their input.

Explanation

Correct Answer

C:

The sponsor signs an initiation decision using current values and confidence levels. This validates the selected response: Refresh assumptions, cost and benefits forecasts and present the decision transparently. The relevant management principle is: Benefit planning informs authorization and investment trade-offs.

Incorrect Answers

A:

Milestone status changes only on the documented event rather than elapsed working time. This is evidence for ANOTHER case: A planning analyst records milestones as hours worked and reports inaccurate schedule progress. The specific corrective response here is: Refresh assumptions, cost and benefits forecasts and present the decision transparently.

B:

The risk register contains uncertain event descriptions, owners and responses. This is evidence for ANOTHER case: A team uses a risk register to list every individual stakeholder complaint without identifying risk triggers or responses. The specific corrective response here is: Refresh assumptions, cost and benefits forecasts and present the decision transparently.

D:

Experts confirm that the documented constraints reflect their input. This is evidence for ANOTHER case: An inexperienced coordinator repeatedly interrupts senior subject experts and misses material project constraints. The specific corrective response here is: Refresh assumptions, cost and benefits forecasts and present the decision transparently.

Question 1079

Which underlying planning or business-analysis mechanism explains: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate.

  1. Financial constraints and resource plans must be reconciled jointly.
  2. Closure confirms agreed acceptance, not merely that the scheduled date arrived.
  3. Meeting effectiveness depends on useful outcomes rather than attendance alone.
  4. Benefit planning informs authorization and investment trade-offs.

Explanation

Correct Answer

D:

Benefit planning informs authorization and investment trade-offs. This explains the case: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate. The targeted action is: Refresh assumptions, cost and benefits forecasts and present the decision transparently.

Incorrect Answers

A:

Financial constraints and resource plans must be reconciled jointly. This rationale better explains a DIFFERENT problem: A procurement workstream estimates capacity for ten contractors but the sponsor has approved funds for only six. The key mechanism for the current situation is: Benefit planning informs authorization and investment trade-offs.

B:

Closure confirms agreed acceptance, not merely that the scheduled date arrived. This rationale better explains a DIFFERENT problem: A transition meeting closes a manufacturing project while unresolved mandatory safety documentation remains with no owner. The key mechanism for the current situation is: Benefit planning informs authorization and investment trade-offs.

C:

Meeting effectiveness depends on useful outcomes rather than attendance alone. This rationale better explains a DIFFERENT problem: A project meeting repeatedly exceeds an hour with no agenda or decision owner and produces no actions. The key mechanism for the current situation is: Benefit planning informs authorization and investment trade-offs.

Question 1080

For the previous project issue, select the best preventive control: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate.

  1. Revalidate business-case assumptions at authorization gates.
  2. Validate measurement units in status reports.
  3. Revalidate stakeholder records after organizational changes.
  4. Require causal evidence in major corrective-action proposals.

Explanation

Correct Answer

A:

Revalidate business-case assumptions at authorization gates. This helps prevent recurrence of: A pilot demonstrates technology feasibility but sponsor approval is based on a hidden and outdated benefits estimate. The required evidence of effective control is: The sponsor signs an initiation decision using current values and confidence levels.

Incorrect Answers

B:

Validate measurement units in status reports. That is a useful control for ANOTHER case: A planning analyst records milestones as hours worked and reports inaccurate schedule progress. The current situation is better prevented by: Revalidate business-case assumptions at authorization gates.

C:

Revalidate stakeholder records after organizational changes. That is a useful control for ANOTHER case: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. The current situation is better prevented by: Revalidate business-case assumptions at authorization gates.

D:

Require causal evidence in major corrective-action proposals. That is a useful control for ANOTHER case: Stakeholders disagree about causes of late handoffs, and the PM immediately replaces the project schedule without diagnosis. The current situation is better prevented by: Revalidate business-case assumptions at authorization gates.