McAfee-Secured Website

Exam Bundle

Exam Code: CAPM

Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 102

Question 1010

The project issue was: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped. Which outcome demonstrates that its remedy worked?

  1. Resolution evidence and closure owner are recorded for the reported complaint.
  2. The issue owner and recovery decision are visible in the incident and project logs.
  3. Baseline approvals demonstrate that planned commitments stay within the approved cap.
  4. The decision record distinguishes facts, assumptions and unresolved questions.

Explanation

Correct Answer

B:

The issue owner and recovery decision are visible in the incident and project logs. This validates the selected response: Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences. The relevant management principle is: Realized adverse events need issue management rather than only assumption tracking.

Incorrect Answers

A:

Resolution evidence and closure owner are recorded for the reported complaint. This is evidence for ANOTHER case: A software team calls an unresolved customer complaint a constraint despite no policy limiting how it may be resolved. The specific corrective response here is: Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences.

C:

Baseline approvals demonstrate that planned commitments stay within the approved cap. This is evidence for ANOTHER case: A finance team treats a capped annual funding limit as an unknown risk rather than a fixed spending boundary. The specific corrective response here is: Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences.

D:

The decision record distinguishes facts, assumptions and unresolved questions. This is evidence for ANOTHER case: A PM sees two opposing stakeholder opinions and assumes a majority vote reveals the full root cause. The specific corrective response here is: Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences.

Question 1011

For a regional transit-project team, the documented failure was: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped. Which explanation is most accurate?

  1. Respect for rights and property applies to project delivery, not only external procurement.
  2. A current defect requires action, while a constraint sets a permitted boundary.
  3. Realized adverse events need issue management rather than only assumption tracking.
  4. Approved frameworks protect scope, cost and time commitments from informal changes.

Explanation

Correct Answer

C:

Realized adverse events need issue management rather than only assumption tracking. This explains the case: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped. The targeted action is: Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences.

Incorrect Answers

A:

Respect for rights and property applies to project delivery, not only external procurement. This rationale better explains a DIFFERENT problem: Two internal departments dispute a licensed design and one party proposes using the material without consent. The key mechanism for the current situation is: Realized adverse events need issue management rather than only assumption tracking.

B:

A current defect requires action, while a constraint sets a permitted boundary. This rationale better explains a DIFFERENT problem: A software team calls an unresolved customer complaint a constraint despite no policy limiting how it may be resolved. The key mechanism for the current situation is: Realized adverse events need issue management rather than only assumption tracking.

D:

Approved frameworks protect scope, cost and time commitments from informal changes. This rationale better explains a DIFFERENT problem: A client requests an extra feature that exceeds approved scope, and the team begins work without a change decision. The key mechanism for the current situation is: Realized adverse events need issue management rather than only assumption tracking.

Question 1012

Which recurring governance check best addresses the risk of repeating: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped.

  1. Maintain the current regulatory baseline in the project register.
  2. Reconcile charter objectives with deliverable-oriented scope statements.
  3. Reconcile scarce skill demand with availability before baseline.
  4. Reclassify risks promptly when trigger conditions occur.

Explanation

Correct Answer

D:

Reclassify risks promptly when trigger conditions occur. This helps prevent recurrence of: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped. The required evidence of effective control is: The issue owner and recovery decision are visible in the incident and project logs.

Incorrect Answers

A:

Maintain the current regulatory baseline in the project register. That is a useful control for ANOTHER case: A safety inspector asks for evidence of a new mandatory standard, but a team defers compliance as a possible future risk. The current situation is better prevented by: Reclassify risks promptly when trigger conditions occur.

B:

Reconcile charter objectives with deliverable-oriented scope statements. That is a useful control for ANOTHER case: A sponsor promises a mobile app and training but the scope statement lists only application coding. The current situation is better prevented by: Reclassify risks promptly when trigger conditions occur.

C:

Reconcile scarce skill demand with availability before baseline. That is a useful control for ANOTHER case: A remote migration is staffed with four developers although the schedule requires one specialized network reviewer unavailable that month. The current situation is better prevented by: Reclassify risks promptly when trigger conditions occur.

Question 1013

During a project review, stakeholders report: A project team revises the delivery date by email but never updates the approved schedule baseline. What should the team do first?

  1. Sequence the test work according to lab capacity and resource constraints.
  2. Route material schedule changes through the agreed integrated change-control process.
  3. Record relevant stakeholder roles, interests, influence and planned engagement.
  4. Invite objective evidence and coach the team toward process correction rather than blame.

Explanation

Correct Answer

B:

Route material schedule changes through the agreed integrated change-control process. This addresses the fictional case: A project team revises the delivery date by email but never updates the approved schedule baseline. The project-management rationale is: Forecasts and approved baselines are not interchangeable governance artifacts. Verify by: Stakeholders can distinguish the approved revised baseline from a scenario forecast.

Incorrect Answers

A:

Sequence the test work according to lab capacity and resource constraints. This would address a DIFFERENT fictional project situation: An offshore development team plans 12 parallel testing activities on one shared lab environment. It is less directly applicable to: A project team revises the delivery date by email but never updates the approved schedule baseline.

C:

Record relevant stakeholder roles, interests, influence and planned engagement. This would address a DIFFERENT fictional project situation: A hospital project identifies patient advocates but omits their influence and communication expectations from its stakeholder register. It is less directly applicable to: A project team revises the delivery date by email but never updates the approved schedule baseline.

D:

Invite objective evidence and coach the team toward process correction rather than blame. This would address a DIFFERENT fictional project situation: The project manager responds defensively to a quality finding and discourages testers from reporting defects. It is less directly applicable to: A project team revises the delivery date by email but never updates the approved schedule baseline.

Question 1014

Following the proposed correction, what observation confirms success: A project team revises the delivery date by email but never updates the approved schedule baseline.

  1. A tabletop exercise finds an approved path before the permit deadline.
  2. The revised resource histogram shows feasible utilization and changed schedule impact.
  3. Stakeholders can distinguish the approved revised baseline from a scenario forecast.
  4. Meeting notes contain resolved decisions, owners and due dates.

Explanation

Correct Answer

C:

Stakeholders can distinguish the approved revised baseline from a scenario forecast. This validates the selected response: Route material schedule changes through the agreed integrated change-control process. The relevant management principle is: Forecasts and approved baselines are not interchangeable governance artifacts.

Incorrect Answers

A:

A tabletop exercise finds an approved path before the permit deadline. This is evidence for ANOTHER case: A facility project has no risk response if its sole permit reviewer becomes unavailable. The specific corrective response here is: Route material schedule changes through the agreed integrated change-control process.

B:

The revised resource histogram shows feasible utilization and changed schedule impact. This is evidence for ANOTHER case: Multiple work packages share the same engineer at the same time while a plan assumes each has full capacity. The specific corrective response here is: Route material schedule changes through the agreed integrated change-control process.

D:

Meeting notes contain resolved decisions, owners and due dates. This is evidence for ANOTHER case: A project meeting repeatedly exceeds an hour with no agenda or decision owner and produces no actions. The specific corrective response here is: Route material schedule changes through the agreed integrated change-control process.

Question 1015

Which underlying planning or business-analysis mechanism explains: A project team revises the delivery date by email but never updates the approved schedule baseline.

  1. A schedule alone cannot address uncertain threats to project objectives.
  2. Effective planning considers multiple constraints and performance dimensions, not dates alone.
  3. Communication strategies define who needs which information and when.
  4. Forecasts and approved baselines are not interchangeable governance artifacts.

Explanation

Correct Answer

D:

Forecasts and approved baselines are not interchangeable governance artifacts. This explains the case: A project team revises the delivery date by email but never updates the approved schedule baseline. The targeted action is: Route material schedule changes through the agreed integrated change-control process.

Incorrect Answers

A:

A schedule alone cannot address uncertain threats to project objectives. This rationale better explains a DIFFERENT problem: A delivery plan has a detailed Gantt chart but does not specify authorized risk response costs. The key mechanism for the current situation is: Forecasts and approved baselines are not interchangeable governance artifacts.

B:

Effective planning considers multiple constraints and performance dimensions, not dates alone. This rationale better explains a DIFFERENT problem: A marketing launch has cost and schedule plans but no account of quality targets or risks. The key mechanism for the current situation is: Forecasts and approved baselines are not interchangeable governance artifacts.

C:

Communication strategies define who needs which information and when. This rationale better explains a DIFFERENT problem: A project status report conceals a significant variance even though the communication plan names the sponsor as an immediate escalation recipient. The key mechanism for the current situation is: Forecasts and approved baselines are not interchangeable governance artifacts.

Question 1016

For the previous project issue, select the best preventive control: A project team revises the delivery date by email but never updates the approved schedule baseline.

  1. Audit variance explanations against controlled versions.
  2. Require transition-ready documentation before final closure.
  3. Reject nonmeasurable quality definitions at planning review.
  4. Test emergency risk procedures through drills.

Explanation

Correct Answer

A:

Audit variance explanations against controlled versions. This helps prevent recurrence of: A project team revises the delivery date by email but never updates the approved schedule baseline. The required evidence of effective control is: Stakeholders can distinguish the approved revised baseline from a scenario forecast.

Incorrect Answers

B:

Require transition-ready documentation before final closure. That is a useful control for ANOTHER case: A completed ERP release has no acceptance record and the builders remain responsible for routine user support indefinitely. The current situation is better prevented by: Audit variance explanations against controlled versions.

C:

Reject nonmeasurable quality definitions at planning review. That is a useful control for ANOTHER case: A quality plan specifies that software must be excellent but has no measurable tests. The current situation is better prevented by: Audit variance explanations against controlled versions.

D:

Test emergency risk procedures through drills. That is a useful control for ANOTHER case: An engineering project observes a new safety hazard but waits for its next monthly review despite an immediate-response risk trigger. The current situation is better prevented by: Audit variance explanations against controlled versions.

Question 1017

For a manufacturing equipment project, a delivery problem is reported: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance. Which action fits the situation?

  1. Raise concerns with evidence while retaining sponsor ownership of investment authorization.
  2. Invite objective evidence and coach the team toward process correction rather than blame.
  3. Map accountable, responsible, consulted and informed roles according to actual governance.
  4. Reject the improper exchange, protect information, and follow formal ethical reporting channels.

Explanation

Correct Answer

C:

Map accountable, responsible, consulted and informed roles according to actual governance. This addresses the fictional case: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance. The project-management rationale is: Explicit role assignment avoids work gaps and unauthorized decisions. Verify by: The revised responsibility map includes the required approvals and consultations.

Incorrect Answers

A:

Raise concerns with evidence while retaining sponsor ownership of investment authorization. This would address a DIFFERENT fictional project situation: A project manager tries to replace a sponsor's business case because of personal preference without involving governance. It is less directly applicable to: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance.

B:

Invite objective evidence and coach the team toward process correction rather than blame. This would address a DIFFERENT fictional project situation: The project manager responds defensively to a quality finding and discourages testers from reporting defects. It is less directly applicable to: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance.

D:

Reject the improper exchange, protect information, and follow formal ethical reporting channels. This would address a DIFFERENT fictional project situation: A procurement manager requests a hidden bid advantage from a supplier in exchange for confidential evaluation scores. It is less directly applicable to: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance.

Question 1018

How should the project team verify a successful response to: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance.

  1. Both teams reference one approved requirement and implementation decision.
  2. The sponsor receives risk and forecast updates before the decision deadline.
  3. Approved baselines and risk plans show response owners and reserved contingency.
  4. The revised responsibility map includes the required approvals and consultations.

Explanation

Correct Answer

D:

The revised responsibility map includes the required approvals and consultations. This validates the selected response: Map accountable, responsible, consulted and informed roles according to actual governance. The relevant management principle is: Explicit role assignment avoids work gaps and unauthorized decisions.

Incorrect Answers

A:

Both teams reference one approved requirement and implementation decision. This is evidence for ANOTHER case: Two teams interpret an executive statement differently and begin incompatible implementations. The specific corrective response here is: Map accountable, responsible, consulted and informed roles according to actual governance.

B:

The sponsor receives risk and forecast updates before the decision deadline. This is evidence for ANOTHER case: A junior PM withholds forecast problems because they believe leadership means never admitting uncertainty. The specific corrective response here is: Map accountable, responsible, consulted and informed roles according to actual governance.

C:

Approved baselines and risk plans show response owners and reserved contingency. This is evidence for ANOTHER case: A delivery plan has a detailed Gantt chart but does not specify authorized risk response costs. The specific corrective response here is: Map accountable, responsible, consulted and informed roles according to actual governance.

Question 1019

A project team asks why this occurs: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance. Which project management principle best explains it?

  1. Explicit role assignment avoids work gaps and unauthorized decisions.
  2. Leadership builds effectiveness through influence and support, not only positional control.
  3. Empathy and self-management improve communication under conflict.
  4. Planned response frameworks support consistent decisions during disruptions.

Explanation

Correct Answer

A:

Explicit role assignment avoids work gaps and unauthorized decisions. This explains the case: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance. The targeted action is: Map accountable, responsible, consulted and informed roles according to actual governance.

Incorrect Answers

B:

Leadership builds effectiveness through influence and support, not only positional control. This rationale better explains a DIFFERENT problem: An agile facilitator evaluates team success by how many direct orders team members obey. The key mechanism for the current situation is: Explicit role assignment avoids work gaps and unauthorized decisions.

C:

Empathy and self-management improve communication under conflict. This rationale better explains a DIFFERENT problem: A customer review becomes confrontational because the manager dismisses frustration as irrelevant to technical status. The key mechanism for the current situation is: Explicit role assignment avoids work gaps and unauthorized decisions.

D:

Planned response frameworks support consistent decisions during disruptions. This rationale better explains a DIFFERENT problem: A project closes its schedule report when a vendor refuses delivery, despite an established procurement contingency. The key mechanism for the current situation is: Explicit role assignment avoids work gaps and unauthorized decisions.

Question 1020

At a manufacturing equipment project, the team wants to avoid repeating: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance. Which safeguard should it retain?

  1. Ask teams for recurring impediment feedback.
  2. Review RACI when project teams change.
  3. Establish respectful defect and escalation norms.
  4. Reconcile scarce skill demand with availability before baseline.

Explanation

Correct Answer

B:

Review RACI when project teams change. This helps prevent recurrence of: A cross-functional project assigns only one person to every deliverable and ignores consultative roles in finance and compliance. The required evidence of effective control is: The revised responsibility map includes the required approvals and consultations.

Incorrect Answers

A:

Ask teams for recurring impediment feedback. That is a useful control for ANOTHER case: An agile facilitator evaluates team success by how many direct orders team members obey. The current situation is better prevented by: Review RACI when project teams change.

C:

Establish respectful defect and escalation norms. That is a useful control for ANOTHER case: The project manager responds defensively to a quality finding and discourages testers from reporting defects. The current situation is better prevented by: Review RACI when project teams change.

D:

Reconcile scarce skill demand with availability before baseline. That is a useful control for ANOTHER case: A remote migration is staffed with four developers although the schedule requires one specialized network reviewer unavailable that month. The current situation is better prevented by: Review RACI when project teams change.