Exam Name Certified Associate in Project Management (PMI-100)

Certification Provider: PMI

Corresponding Certification: CAPM

PMI CAPM Bundle $44.99

100% PMI CAPM Guaranteed Success With Testking Training Materials

Get Real CAPM Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    CAPM Questions & Answers

    688 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual CAPM exam while allowing you to hone and measure every aspect of your test-taking ability.

  • CAPM Video Course

    CAPM Video Course

    123 Video Lectures

    CAPM Video Course is developed by PMI Professionals to help you pass the CAPM exam.

    Description

    This course will improve your knowledge and skills required to pass Certified Associate in Project Management (PMI-100) exam.
  • Study Guide

    CAPM Study Guide

    719 PDF Pages

    Developed by industry experts, this 719-page guide spells out in painstaking detail all of the information you need to ace CAPM exam.

Certified Associate in Project Management (PMI-100) (CAPM) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    688 Questions

    $124.99
  • CAPM Video Course

    Video Course

    123 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    719 PDF Pages

    $29.99

PMI CAPM Practice Test 101

Question 1000

For the previous project issue, select the best preventive control: Project teams send confidential risk details to a broad mailing list despite a stakeholder communication plan limiting distribution.

  1. Check distribution permissions in sensitive status templates.
  2. Validate benefit baselines before budget approval.
  3. Trigger benefit-plan review on substantial objective changes.
  4. Screen funding applications for project-versus-operations distinctions.

Explanation

Correct Answer

A:

Check distribution permissions in sensitive status templates. This helps prevent recurrence of: Project teams send confidential risk details to a broad mailing list despite a stakeholder communication plan limiting distribution. The required evidence of effective control is: Only authorized recipients receive the sensitive risk assessment.

Incorrect Answers

B:

Validate benefit baselines before budget approval. That is a useful control for ANOTHER case: A project initiation memo promises growth but includes no baseline of current performance. The current situation is better prevented by: Check distribution permissions in sensitive status templates.

C:

Trigger benefit-plan review on substantial objective changes. That is a useful control for ANOTHER case: A sponsor changes the project purpose from cost savings to regulatory compliance without reexamining planned outcomes. The current situation is better prevented by: Check distribution permissions in sensitive status templates.

D:

Screen funding applications for project-versus-operations distinctions. That is a useful control for ANOTHER case: A nonprofit calls a collection of separate volunteer events one project despite no shared end result or integrated scope. The current situation is better prevented by: Check distribution permissions in sensitive status templates.

Question 1001

For a distributed delivery organization, a delivery problem is reported: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget. Which action fits the situation?

  1. Correct the logical dependency so prototype acceptance precedes assembly.
  2. Define verification measures, acceptance thresholds and inspection responsibilities.
  3. Report SV = $4,000 favorable and CV = −$7,000 unfavorable as separate observations.
  4. Negotiate a documented allocation and escalation path consistent with the organizational structure.

Explanation

Correct Answer

C:

Report SV = $4,000 favorable and CV = −$7,000 unfavorable as separate observations. This addresses the fictional case: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget. The project-management rationale is: Schedule and cost earned-value indicators can move in opposite directions. Verify by: The report correctly presents positive schedule variance with negative cost variance.

Incorrect Answers

A:

Correct the logical dependency so prototype acceptance precedes assembly. This would address a DIFFERENT fictional project situation: A manufacturing engineer schedules final assembly before a required prototype test because both have available staff. It is less directly applicable to: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget.

B:

Define verification measures, acceptance thresholds and inspection responsibilities. This would address a DIFFERENT fictional project situation: A project promises that testing will be excellent but the quality plan includes no measurable thresholds. It is less directly applicable to: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget.

D:

Negotiate a documented allocation and escalation path consistent with the organizational structure. This would address a DIFFERENT fictional project situation: A functional department loans staff to a project without acknowledging the project's fixed schedule responsibilities. It is less directly applicable to: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget.

Question 1002

How should the project team verify a successful response to: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget.

  1. The forecasted duration matches the network's valid 14-day critical path.
  2. Supplier interfaces pass controlled integration tests with consistent baselines.
  3. A reviewable schedule links procurement, installation and inspection in the required order.
  4. The report correctly presents positive schedule variance with negative cost variance.

Explanation

Correct Answer

D:

The report correctly presents positive schedule variance with negative cost variance. This validates the selected response: Report SV = $4,000 favorable and CV = −$7,000 unfavorable as separate observations. The relevant management principle is: Schedule and cost earned-value indicators can move in opposite directions.

Incorrect Answers

A:

The forecasted duration matches the network's valid 14-day critical path. This is evidence for ANOTHER case: A dependency graph shows two parallel work paths of 14 and 11 days, and the team adds both to forecast a 25-day project. The specific corrective response here is: Report SV = $4,000 favorable and CV = −$7,000 unfavorable as separate observations.

B:

Supplier interfaces pass controlled integration tests with consistent baselines. This is evidence for ANOTHER case: A project integrates hardware and software without a plan for managing interface changes between two suppliers. The specific corrective response here is: Report SV = $4,000 favorable and CV = −$7,000 unfavorable as separate observations.

C:

A reviewable schedule links procurement, installation and inspection in the required order. This is evidence for ANOTHER case: A manufacturing renovation has clear specifications and sequential safety inspections, yet the team cannot identify which activities must finish before others begin. The specific corrective response here is: Report SV = $4,000 favorable and CV = −$7,000 unfavorable as separate observations.

Question 1003

A project team asks why this occurs: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget. Which project management principle best explains it?

  1. Schedule and cost earned-value indicators can move in opposite directions.
  2. Integration management aligns dependent deliverables into a working whole.
  3. A quality plan turns desired fitness into checkable standards and procedures.
  4. Work started is not necessarily work earned under the agreed measurement method.

Explanation

Correct Answer

A:

Schedule and cost earned-value indicators can move in opposite directions. This explains the case: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget. The targeted action is: Report SV = $4,000 favorable and CV = −$7,000 unfavorable as separate observations.

Incorrect Answers

B:

Integration management aligns dependent deliverables into a working whole. This rationale better explains a DIFFERENT problem: A project integrates hardware and software without a plan for managing interface changes between two suppliers. The key mechanism for the current situation is: Schedule and cost earned-value indicators can move in opposite directions.

C:

A quality plan turns desired fitness into checkable standards and procedures. This rationale better explains a DIFFERENT problem: A project promises that testing will be excellent but the quality plan includes no measurable thresholds. The key mechanism for the current situation is: Schedule and cost earned-value indicators can move in opposite directions.

D:

Work started is not necessarily work earned under the agreed measurement method. This rationale better explains a DIFFERENT problem: A project measures its entire progress solely by number of tasks started, not accepted work packages. The key mechanism for the current situation is: Schedule and cost earned-value indicators can move in opposite directions.

Question 1004

At a distributed delivery organization, the team wants to avoid repeating: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget. Which safeguard should it retain?

  1. Recompute critical paths before crash or fast-track proposals.
  2. Include both metrics in performance reviews.
  3. Audit cross-vendor interface agreements before testing.
  4. Include sign checks in financial reporting scripts.

Explanation

Correct Answer

B:

Include both metrics in performance reviews. This helps prevent recurrence of: A software release has earned value $32,000, planned value $28,000 and actual cost $39,000, but a manager assumes being ahead means under budget. The required evidence of effective control is: The report correctly presents positive schedule variance with negative cost variance.

Incorrect Answers

A:

Recompute critical paths before crash or fast-track proposals. That is a useful control for ANOTHER case: A project network has multiple paths with a 20-day maximum path, but the team accelerates a noncritical five-day activity and expects an earlier completion. The current situation is better prevented by: Include both metrics in performance reviews.

C:

Audit cross-vendor interface agreements before testing. That is a useful control for ANOTHER case: A project integrates hardware and software without a plan for managing interface changes between two suppliers. The current situation is better prevented by: Include both metrics in performance reviews.

D:

Include sign checks in financial reporting scripts. That is a useful control for ANOTHER case: A project has earned value $70,000 and actual cost $88,000, yet the report describes its cost variance as favorable. The current situation is better prevented by: Include both metrics in performance reviews.

Question 1005

A CAPM-level project coordinator sees: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction. What is the best next approved step?

  1. Resolve the conflict with compliance and records stakeholders using a decision record.
  2. Conduct observation and contextual interviews with representative nurses.
  3. Validate against agreed user acceptance conditions before authorizing delivery.
  4. Conduct inclusive elicitation with representative accessibility participants and amend acceptance criteria.

Explanation

Correct Answer

D:

Conduct inclusive elicitation with representative accessibility participants and amend acceptance criteria. This addresses the fictional case: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction. The project-management rationale is: Diverse stakeholders reveal requirements otherwise hidden by narrow sampling. Verify by: Assisted and keyboard-only navigation pass documented tests.

Incorrect Answers

A:

Resolve the conflict with compliance and records stakeholders using a decision record. This would address a DIFFERENT fictional project situation: A delivery team accepts contradictory requirements 'retain all records forever' and 'delete all records after one year'. It is less directly applicable to: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction.

B:

Conduct observation and contextual interviews with representative nurses. This would address a DIFFERENT fictional project situation: A BA wants to understand how nurses hand over patients but sends only a yes/no survey without observing the real workflow. It is less directly applicable to: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction.

C:

Validate against agreed user acceptance conditions before authorizing delivery. This would address a DIFFERENT fictional project situation: A bank feature passes all developer unit tests but fails the customer's documented transaction rejection criteria. It is less directly applicable to: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction.

Question 1006

For an independent research initiative, what is the strongest acceptance evidence after addressing: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction.

  1. Assisted and keyboard-only navigation pass documented tests.
  2. Requirement signoff identifies current roles and workflow evidence.
  3. The process map captures handoff exceptions and timing constraints.
  4. Safety obligations have documented ownership and tested acceptance evidence.

Explanation

Correct Answer

A:

Assisted and keyboard-only navigation pass documented tests. This validates the selected response: Conduct inclusive elicitation with representative accessibility participants and amend acceptance criteria. The relevant management principle is: Diverse stakeholders reveal requirements otherwise hidden by narrow sampling.

Incorrect Answers

B:

Requirement signoff identifies current roles and workflow evidence. This is evidence for ANOTHER case: A team reuses last year's requirements interviews though this year's users and business processes differ substantially. The specific corrective response here is: Conduct inclusive elicitation with representative accessibility participants and amend acceptance criteria.

C:

The process map captures handoff exceptions and timing constraints. This is evidence for ANOTHER case: A BA wants to understand how nurses hand over patients but sends only a yes/no survey without observing the real workflow. The specific corrective response here is: Conduct inclusive elicitation with representative accessibility participants and amend acceptance criteria.

D:

Safety obligations have documented ownership and tested acceptance evidence. This is evidence for ANOTHER case: A safety-sensitive medical device project uses informal sticky notes as the sole record of legally mandated requirements. The specific corrective response here is: Conduct inclusive elicitation with representative accessibility participants and amend acceptance criteria.

Question 1007

A postincident review considers: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction. Which principle most directly accounts for the behavior?

  1. Elicitation method should match audience size and information depth.
  2. Diverse stakeholders reveal requirements otherwise hidden by narrow sampling.
  3. Focus groups can surface qualitative needs beyond a simple vote.
  4. Shared terminology prevents semantic misunderstandings across stakeholder groups.

Explanation

Correct Answer

B:

Diverse stakeholders reveal requirements otherwise hidden by narrow sampling. This explains the case: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction. The targeted action is: Conduct inclusive elicitation with representative accessibility participants and amend acceptance criteria.

Incorrect Answers

A:

Elicitation method should match audience size and information depth. This rationale better explains a DIFFERENT problem: Hundreds of customers need to rank proposed portal features, but the team plans individual hour-long interviews with every user. The key mechanism for the current situation is: Diverse stakeholders reveal requirements otherwise hidden by narrow sampling.

C:

Focus groups can surface qualitative needs beyond a simple vote. This rationale better explains a DIFFERENT problem: A BA asks a small focus group whether everyone likes a feature but never captures why participants struggle. The key mechanism for the current situation is: Diverse stakeholders reveal requirements otherwise hidden by narrow sampling.

D:

Shared terminology prevents semantic misunderstandings across stakeholder groups. This rationale better explains a DIFFERENT problem: Two vendor teams use incompatible terms for customer identifiers and integration requirements repeatedly fail review. The key mechanism for the current situation is: Diverse stakeholders reveal requirements otherwise hidden by narrow sampling.

Question 1008

What ongoing preventive practice would most reduce recurrence of: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction.

  1. Require measurable requirements before development commitment.
  2. Combine quantitative reach with qualitative follow-up.
  3. Include accessibility personas in elicitation plans.
  4. Review fixed deadlines during roadmap decisions.

Explanation

Correct Answer

C:

Include accessibility personas in elicitation plans. This helps prevent recurrence of: A BA collects requirements from executives only, then discovers that accessibility users cannot complete the main transaction. The required evidence of effective control is: Assisted and keyboard-only navigation pass documented tests.

Incorrect Answers

A:

Require measurable requirements before development commitment. That is a useful control for ANOTHER case: A mobile banking team writes only 'make payments easy' as a requirement and starts development. The current situation is better prevented by: Include accessibility personas in elicitation plans.

B:

Combine quantitative reach with qualitative follow-up. That is a useful control for ANOTHER case: Hundreds of customers need to rank proposed portal features, but the team plans individual hour-long interviews with every user. The current situation is better prevented by: Include accessibility personas in elicitation plans.

D:

Review fixed deadlines during roadmap decisions. That is a useful control for ANOTHER case: A compliance update has a legal enforcement date after a planned marketing feature release, but the roadmap prioritizes marketing and delays the mandatory work. The current situation is better prevented by: Include accessibility personas in elicitation plans.

Question 1009

At a regional transit-project team, the review identifies: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped. Which response best addresses the specific project management problem?

  1. Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences.
  2. Revise the proposed scope through authorized agreement to include acceptance and training deliverables.
  3. Consider a hybrid approach with fixed governance gates and iterative experimentation.
  4. Refer funding authorization to the accountable sponsor and document the decision.

Explanation

Correct Answer

A:

Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences. This addresses the fictional case: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped. The project-management rationale is: Realized adverse events need issue management rather than only assumption tracking. Verify by: The issue owner and recovery decision are visible in the incident and project logs.

Incorrect Answers

B:

Revise the proposed scope through authorized agreement to include acceptance and training deliverables. This would address a DIFFERENT fictional project situation: A sponsor promises a mobile app and training but the scope statement lists only application coding. It is less directly applicable to: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped.

C:

Consider a hybrid approach with fixed governance gates and iterative experimentation. This would address a DIFFERENT fictional project situation: A research lab has a fixed compliance deadline but uncertain technical experiments and insists every activity must follow one lifecycle. It is less directly applicable to: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped.

D:

Refer funding authorization to the accountable sponsor and document the decision. This would address a DIFFERENT fictional project situation: A contractor asks the project manager for funding beyond the charter's authority and receives an informal approval. It is less directly applicable to: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped.

Question 1010

The project issue was: An IT manager describes a critical vendor outage as merely a planning assumption after service has already stopped. Which outcome demonstrates that its remedy worked?

  1. Resolution evidence and closure owner are recorded for the reported complaint.
  2. The issue owner and recovery decision are visible in the incident and project logs.
  3. Baseline approvals demonstrate that planned commitments stay within the approved cap.
  4. The decision record distinguishes facts, assumptions and unresolved questions.

Explanation

Correct Answer

B:

The issue owner and recovery decision are visible in the incident and project logs. This validates the selected response: Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences. The relevant management principle is: Realized adverse events need issue management rather than only assumption tracking.

Incorrect Answers

A:

Resolution evidence and closure owner are recorded for the reported complaint. This is evidence for ANOTHER case: A software team calls an unresolved customer complaint a constraint despite no policy limiting how it may be resolved. The specific corrective response here is: Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences.

C:

Baseline approvals demonstrate that planned commitments stay within the approved cap. This is evidence for ANOTHER case: A finance team treats a capped annual funding limit as an unknown risk rather than a fixed spending boundary. The specific corrective response here is: Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences.

D:

The decision record distinguishes facts, assumptions and unresolved questions. This is evidence for ANOTHER case: A PM sees two opposing stakeholder opinions and assumes a majority vote reveals the full root cause. The specific corrective response here is: Escalate the outage as a live issue and apply incident response while reviewing its schedule consequences.