Question 570
An infrastructure administrator receives the following incident: An engineer installs a replacement PSU of matching rated wattage but different unsupported part family, and the chassis continues to report redundancy faults. Which measured result most directly proves that this specific problem is resolved?
Explanation
Correct Answer
This is the measurable acceptance result for the described case: With the correct part installed, both feeds report accepted status and a single-feed failure test keeps the host powered. It validates the corrective operation (Use a vendor-qualified PSU model and verify power redundancy and BMC hardware status after supported installation.) rather than a related but different system check.
Incorrect Answers
This observation would help verify a different incident: A GPU fails during production training and a field technician opens the energized chassis without following the vendor's power and electrostatic discharge procedure. It does not directly establish the required result for the current case: With the correct part installed, both feeds report accepted status and a single-feed failure test keeps the host powered.
This observation would help verify a different incident: A ConnectX adapter is replaced with a nominally compatible part but the new device uses firmware that the fabric switch does not support at the required link rate. It does not directly establish the required result for the current case: With the correct part installed, both feeds report accepted status and a single-feed failure test keeps the host powered.
This observation would help verify a different incident: A mixed Intel and AMD CPU GPU cluster shows slower model preprocessing on one hardware family, while operators compare only GPU clock rates. It does not directly establish the required result for the current case: With the correct part installed, both feeds report accepted status and a single-feed failure test keeps the host powered.