Question 590
At Cedarfield Hospitality, the guest data administration team maintains an international booking and reservations database estate with requirements for high-volume seasonal reservations and reliable failover. After a claimed fix, the release reviewer evaluates: A team proposes an expensive multisite synchronous architecture without first determining business RTO, RPO or acceptable downtime cost. Which observed result BEST proves the intended problem is corrected?
Explanation
Correct Answer
A recorded tabletop and controlled test confirm the selected design meets agreed loss and outage targets at an approved cost. That observable result supports resolution of: A team proposes an expensive multisite synchronous architecture without first determining business RTO, RPO or acceptable downtime cost. The corresponding corrective change is: Elicit measurable recovery objectives and choose the minimum-supported HA/DR architecture that meets risk and cost constraints. The Cedarfield Hospitality reviewer can distinguish demonstrated database behavior from an untested change claim.
Incorrect Answers
A controlled failover or recovery test shows the last recoverable transaction is within the agreed five-minute loss window. That result is evidence for another corrective change: Select an HA/DR design with a measured recovery point objective that fits five minutes, not backup frequency alone. The alternative problem is: A business declares that it can lose no more than five minutes of transactions but its only recovery plan is a nightly backup. The current Cedarfield Hospitality issue is instead: A team proposes an expensive multisite synchronous architecture without first determining business RTO, RPO or acceptable downtime cost. Its decisive acceptance evidence would be: A recorded tabletop and controlled test confirm the selected design meets agreed loss and outage targets at an approved cost.
A controlled accidental deletion is recovered to a selected pre-deletion timestamp and the restored database is usable. That result is evidence for another corrective change: Include point-in-time restore and appropriate retention planning alongside high-availability features to handle user or application mistakes. The alternative problem is: An Azure SQL Database application has no backup-restore runbook because its developers assume built-in platform availability prevents logical data deletion. The current Cedarfield Hospitality issue is instead: A team proposes an expensive multisite synchronous architecture without first determining business RTO, RPO or acceptable downtime cost. Its decisive acceptance evidence would be: A recorded tabletop and controlled test confirm the selected design meets agreed loss and outage targets at an approved cost.
The promoted recovery database sustains the required transaction throughput and client latency instead of merely accepting connections. That result is evidence for another corrective change: Size the recovery replica and network path for the documented recovery workload and run representative failover load tests. The alternative problem is: A cross-region failover plan assumes secondary read replicas will always have identical performance capacity to the primary without sizing them. The current Cedarfield Hospitality issue is instead: A team proposes an expensive multisite synchronous architecture without first determining business RTO, RPO or acceptable downtime cost. Its decisive acceptance evidence would be: A recorded tabletop and controlled test confirm the selected design meets agreed loss and outage targets at an approved cost.