McAfee-Secured Website

Exam Bundle

Exam Code: AZ-800

Exam Name Administering Windows Server Hybrid Core Infrastructure

Certification Provider: Microsoft

Corresponding Certification: Microsoft Certified: Windows Server Hybrid Administrator Associate

Microsoft AZ-800 Bundle $44.99

100% Microsoft AZ-800 Guaranteed Success With Testking Training Materials

Get Real AZ-800 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    AZ-800 Questions & Answers

    311 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual AZ-800 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • AZ-800 Video Course

    AZ-800 Video Course

    150 Video Lectures

    AZ-800 Video Course is developed by Microsoft Professionals to help you pass the AZ-800 exam.

    Description

    This course will improve your knowledge and skills required to pass Administering Windows Server Hybrid Core Infrastructure exam.
  • Study Guide

    AZ-800 Study Guide

    430 PDF Pages

    Developed by industry experts, this 430-page guide spells out in painstaking detail all of the information you need to ace AZ-800 exam.

Administering Windows Server Hybrid Core Infrastructure (AZ-800) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    311 Questions

    $124.99
  • AZ-800 Video Course

    Video Course

    150 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    430 PDF Pages

    $29.99

Microsoft AZ-800 Practice Test 47

Question 460

A Windows Server administrator proposes this action: Review startup, minimum, maximum and buffer Dynamic Memory settings against actual workload. Which situation most specifically calls for this action?

  1. A VM backup relies on consistent guest quiescence but its integration service is disabled.
  2. A VM repeatedly stalls during memory demand spikes despite a capable Hyper-V host.
  3. New VM workloads require network access through a host physical adapter.
  4. A lab Windows Server VM must itself run Hyper-V workloads for training.

Explanation

Correct Answer

B:

This scenario is the specific context for Dynamic Memory mis-sizing. The appropriate action is to Review startup, minimum, maximum and buffer Dynamic Memory settings against actual workload. Expected outcome: The guest has a memory allocation policy compatible with its peaks and host capacity.

Incorrect Answers

A:

This situation concerns Hyper-V integration services. It would call for: Verify relevant Hyper-V integration services and guest support before changing storage drivers. Expected result: Host-initiated guest coordination can operate where integration services support it. It does not directly motivate the specified Dynamic Memory mis-sizing action.

C:

This situation concerns External vSwitch physical uplink. It would call for: Bind a Hyper-V external virtual switch to the approved host NIC and verify host access settings. Expected result: VM adapters can reach the designated external network segment. It does not directly motivate the specified Dynamic Memory mis-sizing action.

D:

This situation concerns Nested virtualization lab. It would call for: Enable supported nested virtualization settings on the parent Hyper-V VM. Expected result: The nested Windows Server can expose virtualization extensions to its guest hypervisor. It does not directly motivate the specified Dynamic Memory mis-sizing action.

Question 461

In an archival Windows Server hybrid scenario, A VM backup relies on consistent guest quiescence but its integration service is disabled. Which administrative action most directly addresses the stated requirement?

  1. Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites.
  2. Configure a supported NIC teaming design with correct switch/NIC compatibility.
  3. Review startup, minimum, maximum and buffer Dynamic Memory settings against actual workload.
  4. Verify relevant Hyper-V integration services and guest support before changing storage drivers.

Explanation

Correct Answer

D:

This directly addresses Hyper-V integration services: Host-initiated guest coordination can operate where integration services support it.

Incorrect Answers

A:

This option would instead address Discrete Device Assignment planning: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. In that situation, the expected outcome is: The device can be assigned directly only when host, guest and hardware support it. It does not resolve the primary Hyper-V integration services requirement described here.

B:

This option would instead address NIC teaming failover: Configure a supported NIC teaming design with correct switch/NIC compatibility. In that situation, the expected outcome is: A single uplink failure need not sever the host's planned connectivity. It does not resolve the primary Hyper-V integration services requirement described here.

C:

This option would instead address Dynamic Memory mis-sizing: Review startup, minimum, maximum and buffer Dynamic Memory settings against actual workload. In that situation, the expected outcome is: The guest has a memory allocation policy compatible with its peaks and host capacity. It does not resolve the primary Hyper-V integration services requirement described here.

Question 462

A Windows Server administrator takes this approved action: Verify relevant Hyper-V integration services and guest support before changing storage drivers. Which operational result most directly confirms the intended outcome?

  1. Host-initiated guest coordination can operate where integration services support it.
  2. The device can be assigned directly only when host, guest and hardware support it.
  3. A single uplink failure need not sever the host's planned connectivity.
  4. The guest has a memory allocation policy compatible with its peaks and host capacity.

Explanation

Correct Answer

A:

This confirms the intended result for Hyper-V integration services: Host-initiated guest coordination can operate where integration services support it.

Incorrect Answers

B:

This is the outcome associated with Discrete Device Assignment planning, achieved instead by: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. It is not the direct confirmation of the proposed action.

C:

This is the outcome associated with NIC teaming failover, achieved instead by: Configure a supported NIC teaming design with correct switch/NIC compatibility. It is not the direct confirmation of the proposed action.

D:

This is the outcome associated with Dynamic Memory mis-sizing, achieved instead by: Review startup, minimum, maximum and buffer Dynamic Memory settings against actual workload. It is not the direct confirmation of the proposed action.

Question 463

In a Windows Server hybrid environment, A VM backup relies on consistent guest quiescence but its integration service is disabled. A colleague instead proposes: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. Which response is more directly applicable to the original requirement?

  1. Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites.
  2. Verify relevant Hyper-V integration services and guest support before changing storage drivers.
  3. Configure a supported NIC teaming design with correct switch/NIC compatibility.
  4. Review startup, minimum, maximum and buffer Dynamic Memory settings against actual workload.

Explanation

Correct Answer

B:

The action needed for Hyper-V integration services is: Verify relevant Hyper-V integration services and guest support before changing storage drivers. The expected result is: Host-initiated guest coordination can operate where integration services support it.

Incorrect Answers

A:

This option would instead address Discrete Device Assignment planning: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. In that situation, the expected outcome is: The device can be assigned directly only when host, guest and hardware support it. It does not resolve the primary Hyper-V integration services requirement described here.

C:

This option would instead address NIC teaming failover: Configure a supported NIC teaming design with correct switch/NIC compatibility. In that situation, the expected outcome is: A single uplink failure need not sever the host's planned connectivity. It does not resolve the primary Hyper-V integration services requirement described here.

D:

This option would instead address Dynamic Memory mis-sizing: Review startup, minimum, maximum and buffer Dynamic Memory settings against actual workload. In that situation, the expected outcome is: The guest has a memory allocation policy compatible with its peaks and host capacity. It does not resolve the primary Hyper-V integration services requirement described here.

Question 464

A Windows Server administrator proposes this action: Verify relevant Hyper-V integration services and guest support before changing storage drivers. Which situation most specifically calls for this action?

  1. A specialized VM requires direct access to a compatible physical PCIe device.
  2. A Hyper-V host has two uplinks and needs resilient network connectivity.
  3. A VM backup relies on consistent guest quiescence but its integration service is disabled.
  4. A VM repeatedly stalls during memory demand spikes despite a capable Hyper-V host.

Explanation

Correct Answer

C:

This scenario is the specific context for Hyper-V integration services. The appropriate action is to Verify relevant Hyper-V integration services and guest support before changing storage drivers. Expected outcome: Host-initiated guest coordination can operate where integration services support it.

Incorrect Answers

A:

This situation concerns Discrete Device Assignment planning. It would call for: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. Expected result: The device can be assigned directly only when host, guest and hardware support it. It does not directly motivate the specified Hyper-V integration services action.

B:

This situation concerns NIC teaming failover. It would call for: Configure a supported NIC teaming design with correct switch/NIC compatibility. Expected result: A single uplink failure need not sever the host's planned connectivity. It does not directly motivate the specified Hyper-V integration services action.

D:

This situation concerns Dynamic Memory mis-sizing. It would call for: Review startup, minimum, maximum and buffer Dynamic Memory settings against actual workload. Expected result: The guest has a memory allocation policy compatible with its peaks and host capacity. It does not directly motivate the specified Hyper-V integration services action.

Question 465

In an archival Windows Server hybrid scenario, A specialized VM requires direct access to a compatible physical PCIe device. Which administrative action most directly addresses the stated requirement?

  1. Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites.
  2. Assess supported GPU partitioning configuration and host driver prerequisites.
  3. Evaluate shielded VMs and a guarded fabric with Host Guardian Service where supported.
  4. Verify relevant Hyper-V integration services and guest support before changing storage drivers.

Explanation

Correct Answer

A:

This directly addresses Discrete Device Assignment planning: The device can be assigned directly only when host, guest and hardware support it.

Incorrect Answers

B:

This option would instead address GPU partitioning workload: Assess supported GPU partitioning configuration and host driver prerequisites. In that situation, the expected outcome is: Multiple VM workloads can be allocated GPU partitions on capable systems. It does not resolve the primary Discrete Device Assignment planning requirement described here.

C:

This option would instead address Shielded VM protection: Evaluate shielded VMs and a guarded fabric with Host Guardian Service where supported. In that situation, the expected outcome is: VM protection depends on attested hosts and shielded virtual disk security. It does not resolve the primary Discrete Device Assignment planning requirement described here.

D:

This option would instead address Hyper-V integration services: Verify relevant Hyper-V integration services and guest support before changing storage drivers. In that situation, the expected outcome is: Host-initiated guest coordination can operate where integration services support it. It does not resolve the primary Discrete Device Assignment planning requirement described here.

Question 466

A Windows Server administrator takes this approved action: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. Which operational result most directly confirms the intended outcome?

  1. Multiple VM workloads can be allocated GPU partitions on capable systems.
  2. The device can be assigned directly only when host, guest and hardware support it.
  3. VM protection depends on attested hosts and shielded virtual disk security.
  4. Host-initiated guest coordination can operate where integration services support it.

Explanation

Correct Answer

B:

This confirms the intended result for Discrete Device Assignment planning: The device can be assigned directly only when host, guest and hardware support it.

Incorrect Answers

A:

This is the outcome associated with GPU partitioning workload, achieved instead by: Assess supported GPU partitioning configuration and host driver prerequisites. It is not the direct confirmation of the proposed action.

C:

This is the outcome associated with Shielded VM protection, achieved instead by: Evaluate shielded VMs and a guarded fabric with Host Guardian Service where supported. It is not the direct confirmation of the proposed action.

D:

This is the outcome associated with Hyper-V integration services, achieved instead by: Verify relevant Hyper-V integration services and guest support before changing storage drivers. It is not the direct confirmation of the proposed action.

Question 467

In a Windows Server hybrid environment, A specialized VM requires direct access to a compatible physical PCIe device. A colleague instead proposes: Assess supported GPU partitioning configuration and host driver prerequisites. Which response is more directly applicable to the original requirement?

  1. Assess supported GPU partitioning configuration and host driver prerequisites.
  2. Evaluate shielded VMs and a guarded fabric with Host Guardian Service where supported.
  3. Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites.
  4. Verify relevant Hyper-V integration services and guest support before changing storage drivers.

Explanation

Correct Answer

C:

The action needed for Discrete Device Assignment planning is: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. The expected result is: The device can be assigned directly only when host, guest and hardware support it.

Incorrect Answers

A:

This option would instead address GPU partitioning workload: Assess supported GPU partitioning configuration and host driver prerequisites. In that situation, the expected outcome is: Multiple VM workloads can be allocated GPU partitions on capable systems. It does not resolve the primary Discrete Device Assignment planning requirement described here.

B:

This option would instead address Shielded VM protection: Evaluate shielded VMs and a guarded fabric with Host Guardian Service where supported. In that situation, the expected outcome is: VM protection depends on attested hosts and shielded virtual disk security. It does not resolve the primary Discrete Device Assignment planning requirement described here.

D:

This option would instead address Hyper-V integration services: Verify relevant Hyper-V integration services and guest support before changing storage drivers. In that situation, the expected outcome is: Host-initiated guest coordination can operate where integration services support it. It does not resolve the primary Discrete Device Assignment planning requirement described here.

Question 468

A Windows Server administrator proposes this action: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. Which situation most specifically calls for this action?

  1. Several graphics-intensive VMs should share a compatible GPU without exclusive passthrough.
  2. A highly sensitive VM must prevent unauthorized fabric administrators from inspecting its virtual disks.
  3. A VM backup relies on consistent guest quiescence but its integration service is disabled.
  4. A specialized VM requires direct access to a compatible physical PCIe device.

Explanation

Correct Answer

D:

This scenario is the specific context for Discrete Device Assignment planning. The appropriate action is to Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. Expected outcome: The device can be assigned directly only when host, guest and hardware support it.

Incorrect Answers

A:

This situation concerns GPU partitioning workload. It would call for: Assess supported GPU partitioning configuration and host driver prerequisites. Expected result: Multiple VM workloads can be allocated GPU partitions on capable systems. It does not directly motivate the specified Discrete Device Assignment planning action.

B:

This situation concerns Shielded VM protection. It would call for: Evaluate shielded VMs and a guarded fabric with Host Guardian Service where supported. Expected result: VM protection depends on attested hosts and shielded virtual disk security. It does not directly motivate the specified Discrete Device Assignment planning action.

C:

This situation concerns Hyper-V integration services. It would call for: Verify relevant Hyper-V integration services and guest support before changing storage drivers. Expected result: Host-initiated guest coordination can operate where integration services support it. It does not directly motivate the specified Discrete Device Assignment planning action.

Question 469

In an archival Windows Server hybrid scenario, Several graphics-intensive VMs should share a compatible GPU without exclusive passthrough. Which administrative action most directly addresses the stated requirement?

  1. Configure appropriate Hyper-V VM resource controls or CPU groups for the specified workload.
  2. Assess supported GPU partitioning configuration and host driver prerequisites.
  3. Validate guarded fabric and Host Guardian Service trust on the destination host.
  4. Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites.

Explanation

Correct Answer

B:

This directly addresses GPU partitioning workload: Multiple VM workloads can be allocated GPU partitions on capable systems.

Incorrect Answers

A:

This option would instead address Hyper-V CPU resource group: Configure appropriate Hyper-V VM resource controls or CPU groups for the specified workload. In that situation, the expected outcome is: CPU scheduling enforces the intended workload resource boundaries. It does not resolve the primary GPU partitioning workload requirement described here.

C:

This option would instead address Protected VM host migration: Validate guarded fabric and Host Guardian Service trust on the destination host. In that situation, the expected outcome is: A protected VM migration succeeds only to an authorized guarded host. It does not resolve the primary GPU partitioning workload requirement described here.

D:

This option would instead address Discrete Device Assignment planning: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. In that situation, the expected outcome is: The device can be assigned directly only when host, guest and hardware support it. It does not resolve the primary GPU partitioning workload requirement described here.

Question 470

A Windows Server administrator takes this approved action: Assess supported GPU partitioning configuration and host driver prerequisites. Which operational result most directly confirms the intended outcome?

  1. CPU scheduling enforces the intended workload resource boundaries.
  2. A protected VM migration succeeds only to an authorized guarded host.
  3. Multiple VM workloads can be allocated GPU partitions on capable systems.
  4. The device can be assigned directly only when host, guest and hardware support it.

Explanation

Correct Answer

C:

This confirms the intended result for GPU partitioning workload: Multiple VM workloads can be allocated GPU partitions on capable systems.

Incorrect Answers

A:

This is the outcome associated with Hyper-V CPU resource group, achieved instead by: Configure appropriate Hyper-V VM resource controls or CPU groups for the specified workload. It is not the direct confirmation of the proposed action.

B:

This is the outcome associated with Protected VM host migration, achieved instead by: Validate guarded fabric and Host Guardian Service trust on the destination host. It is not the direct confirmation of the proposed action.

D:

This is the outcome associated with Discrete Device Assignment planning, achieved instead by: Evaluate Hyper-V Discrete Device Assignment and device isolation prerequisites. It is not the direct confirmation of the proposed action.