Question 440
A Windows Server administrator proposes this action: Onboard the machine through the Connected Machine agent before requesting supported Arc extension deployment. Which situation most specifically calls for this action?
Explanation
Correct Answer
This scenario is the specific context for Azure service extension prerequisite. The appropriate action is to Onboard the machine through the Connected Machine agent before requesting supported Arc extension deployment. Expected outcome: The server becomes eligible for extensions managed through Azure Arc.
Incorrect Answers
This situation concerns Azure Arc Connected Machine onboarding. It would call for: Install and register the Azure Connected Machine agent with an approved subscription and identity. Expected result: The external server is represented as an Azure Arc-enabled server resource. It does not directly motivate the specified Azure service extension prerequisite action.
This situation concerns Maintenance configuration schedule. It would call for: Create an Update Manager maintenance configuration and associate the authorized server scope. Expected result: Update installations occur during the specified maintenance schedule. It does not directly motivate the specified Azure service extension prerequisite action.
This situation concerns Arc resource inventory tagging. It would call for: Apply resource groups, tags and role assignments appropriate to the Azure Arc server resources. Expected result: Policy and reporting can target registered machines by approved organizational scope. It does not directly motivate the specified Azure service extension prerequisite action.