Question 80
Fictional Bluewater Technical Works is completing a plant modernization assessment charter with plant engineering and operations personnel. During a system commissioning handoff, the case presents this industrial security assessment concern: A scanning team schedules active equipment inquiries for a maintenance turnaround but has no approval from the process owner coordinating energization tests. The team must prioritize safe operation, authorized assessment methods, and evidence from the actual process environment. Which repeatable governance check should keep the assessment finding current?
Explanation
Correct Answer
Reapprove assessment windows after turnaround plans, plant states, or safety permits change. That recurring check targets the underlying weakness: a nominal maintenance window is not inherently safe because industrial equipment may be transitioning through sensitive states.
Incorrect Answers
Recheck instrument consequences after alarm limits, equipment capacities, or protective logic change. Loss of measurement integrity can influence physical process response even when control computers remain online. The relevant follow-up is: Reapprove assessment windows after turnaround plans, plant states, or safety permits change.
Review support account necessity, validity, and closure after every contractor exit and project phase. An external actor does not require exploitation of a software flaw when standing remote privileges already provide a control pathway. The relevant follow-up is: Reapprove assessment windows after turnaround plans, plant states, or safety permits change.
Reevaluate update trust and supplier contact controls when distribution channels or vendor processes change. Maintenance supply chains can become attack paths when software origin and integrity are not independently verified. The relevant follow-up is: Reapprove assessment windows after turnaround plans, plant states, or safety permits change.