Question 1050
Fictional Brookfield Plant Systems is completing a plant risk governance audit with plant engineering and operations personnel. During a controlled maintenance planning session, the case presents this industrial security assessment concern: A plant director accepts residual risk from an aging operator workstation but the report provides no interim monitoring, expiration date, or reapproval trigger. The team must prioritize safe operation, authorized assessment methods, and evidence from the actual process environment. Which maintenance or change-trigger review should accompany the proposed decision?
Explanation
Correct Answer
Track expiry and reassess after significant vendor advisories, process changes, and control failures. That recurring check targets the underlying weakness: risk acceptance is a conditional governance decision that requires visibility into whether the original assumptions remain true.
Incorrect Answers
Recheck safety-critical control assumptions after machinery guarding or safety-system modifications. Worker protection consequences should be evaluated on the physical hazard, not only on downtime or IT service interruption. The relevant follow-up is: Track expiry and reassess after significant vendor advisories, process changes, and control failures.
Reassess cyclic exposure when maintenance frequency, remote support, or privileged access procedures change. Short high-exposure periods can dominate a scenario's credible attack opportunity even if the asset is offline much of the month. The relevant follow-up is: Track expiry and reassess after significant vendor advisories, process changes, and control failures.
Reassess target-to-current gaps after firewall policy changes and new risk findings. The strength of an installed control is a baseline measurement, not proof that the system has enough protection for its consequences. The relevant follow-up is: Track expiry and reassess after significant vendor advisories, process changes, and control failures.