Question 1030
Fictional Northshore Plant Operations is completing an industrial risk reporting and handoff review with plant engineering and operations personnel. During an operator-led risk workshop, the case presents this industrial security assessment concern: A control integrator edits the zone diagram after risk signoff, but the issued report still references an earlier version with different permitted links. The team must prioritize safe operation, authorized assessment methods, and evidence from the actual process environment. What ongoing verification best prevents the specific gap from returning?
Explanation
Correct Answer
Review interdocument revision consistency whenever network or process design changes. It helps maintain the control because architecture and risk documents are coupled evidence; inconsistent revisions can invalidate previously approved threat pathways.
Incorrect Answers
Tie controller additions and cabinet modifications to asset-register updates and periodic reconciliation. Unlisted control assets cannot be evaluated for credible exposure, supportability, or consequences simply by counting servers. To reduce recurrence in this case, review interdocument revision consistency whenever network or process design changes.
Require device-specific safe-discovery approval whenever assessment tools or control hardware change. Industrial devices may react unpredictably to unexpected traffic even when conventional IT scanners consider probes nonintrusive. To reduce recurrence in this case, review interdocument revision consistency whenever network or process design changes.
Reassess capture coverage after network redesign, controller redundancy changes, and new segmented links. Passive collection cannot prove absence of a vulnerability on network paths it never monitored. To reduce recurrence in this case, review interdocument revision consistency whenever network or process design changes.