Question 310
At Ironwood Public Services, the city network service team is preparing a new municipal office activation. The operational constraint is an approved redundant path. The change ticket is marked completed for this reported failure: A user connects to an access port but cannot reach peers because the switchport is assigned VLAN 40 instead of required VLAN 140. Which result BEST demonstrates that this specific issue was resolved?
Explanation
Correct Answer
The host MAC appears in VLAN 140 and can reach its expected local peers. This is the relevant acceptance observation for the reported issue: A user connects to an access port but cannot reach peers because the switchport is assigned VLAN 40 instead of required VLAN 140. The intended corrective choice is: Compare port VLAN membership with the documented access VLAN and correct the mismatch. At Ironwood Public Services, this outcome verifies actual operation under an approved redundant path, rather than only a ticket marked complete.
Incorrect Answers
Both neighbors share the intended subnet and ICMP tests pass after correction. Such an observation would verify a separate issue: Two directly connected routed ports have addresses from different /30 networks and cannot ping each other. It would follow the distinct action: Compare subnet masks and interface addressing and restore a consistent point-to-point IP plan. Here the reported failure is A user connects to an access port but cannot reach peers because the switchport is assigned VLAN 40 instead of required VLAN 140. The decisive result for Ironwood Public Services must instead be: The host MAC appears in VLAN 140 and can reach its expected local peers.
Power allocation fits the camera class and the camera boots without denial counters increasing. Such an observation would verify a separate issue: A PoE-powered camera stays dark while the link is otherwise healthy; telemetry reports insufficient allocation budget. It would follow the distinct action: Diagnose available PoE budget and port power limits rather than changing VLAN or routing. Here the reported failure is A user connects to an access port but cannot reach peers because the switchport is assigned VLAN 40 instead of required VLAN 140. The decisive result for Ironwood Public Services must instead be: The host MAC appears in VLAN 140 and can reach its expected local peers.
The VLAN interface becomes operational with the intended member-link state. Such an observation would verify a separate issue: A switch hosts VLAN 320 endpoints but reports its routed VLAN interface down with no active member ports. It would follow the distinct action: Inspect SVI operational prerequisites including active VLAN membership and correct L3 configuration. Here the reported failure is A user connects to an access port but cannot reach peers because the switchport is assigned VLAN 40 instead of required VLAN 140. The decisive result for Ironwood Public Services must instead be: The host MAC appears in VLAN 140 and can reach its expected local peers.