Question 80
During a planned campus-network change at a public library in Portland, operators discover that a new switch receives a campus template with the wrong management VLAN during its initial onboarding. The design must preserve staff and visitor wireless access. Which post-change observation is the strongest acceptance evidence?
Explanation
Correct Answer
This observation tests the Zero-touch provisioning and initial management requirement at a public library in Portland. The expected result is that the device acquires the expected bootstrap configuration and checks in to the authorized management system without a manual rescue. The necessary correction is to validate supported DHCP/ZTP provisioning information and management reachability, then apply the intended software and site template; a saved configuration alone would not prove it is working. In this case, the observed fault is that a new switch receives a campus template with the wrong management VLAN during its initial onboarding.
Incorrect Answers
At a public library in Portland, this measures a different network requirement, PoE budgets and AP or phone edge connectivity. The case describes that a new switch receives a campus template with the wrong management VLAN during its initial onboarding, so accepting this result would leave the primary fault without direct verification.
At a public library in Portland, this would verify Aruba Central inventory and device onboarding, not the failure reported in this scenario. The requested closure criterion instead concerns Zero-touch provisioning and initial management: the device acquires the expected bootstrap configuration and checks in to the authorized management system without a manual rescue.
At a public library in Portland, the observation may be useful for a separate Campus uplinks, link speed and optics validation test, but it does not establish that a new switch receives a campus template with the wrong management VLAN during its initial onboarding has been resolved. The relevant check is the Zero-touch provisioning and initial management outcome.