Question 980
Evergreen Hospital is delivering an IT initiative involving care coordination and staff identity services with multiple distributed delivery teams. The team observes: An Agile team reports increasing task completion while its sprint still misses the commitment and cannot explain remaining work. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The chart shows why remaining work exceeds the expected level before the sprint ends. This is the relevant acceptance evidence because it tests whether the corrective action (Use a burndown chart with actual outstanding work versus the planned sprint trajectory.) fixed the original concern (An Agile team reports increasing task completion while its sprint still misses the commitment and cannot explain remaining work.) at Evergreen Hospital, rather than relying only on a task marked complete. The affected work concerns care coordination and staff identity services.
Incorrect Answers
The chart reveals that completion progress coexists with newly added backlog scope. This evidence would be useful for another condition (A product owner wants to display both rising delivered scope and new scope requests but a chart shows only remaining tasks.) and its different action (Use a burnup chart with a completed-work series and a total-scope series.). At Evergreen Hospital, it does not demonstrate the required project outcome: The chart shows why remaining work exceeds the expected level before the sprint ends.
The chart reveals dominant categories and enables a focused improvement decision. This evidence would be useful for another condition (A release has many defect categories and the quality lead cannot tell which few causes produce most rework.) and its different action (Use a Pareto chart to rank defect categories by frequency or impact.). At Evergreen Hospital, it does not demonstrate the required project outcome: The chart shows why remaining work exceeds the expected level before the sprint ends.
The chart shows the sustained rise and its timing relative to a process change. This evidence would be useful for another condition (The team sees cycle time rise over successive weeks but individual weekly reports conceal the trend.) and its different action (Plot performance measures in time order using a run chart.). At Evergreen Hospital, it does not demonstrate the required project outcome: The chart shows why remaining work exceeds the expected level before the sprint ends.