Question 970
Sandstone Publishing is delivering an IT initiative involving editorial documents and partner applications subject to a limited implementation budget. The team observes: The sponsor asks how many days a project will take but the estimate has best likely and worst cases with unequal plausibility. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The estimate and assumptions can be independently recomputed from the three inputs. This is the relevant acceptance evidence because it tests whether the corrective action (Use three-point PERT reasoning to calculate and communicate a weighted expected duration.) fixed the original concern (The sponsor asks how many days a project will take but the estimate has best likely and worst cases with unequal plausibility.) at Sandstone Publishing, rather than relying only on a task marked complete. The affected work concerns editorial documents and partner applications.
Incorrect Answers
The forecast uses the team's measured trend rather than treating cross-team points as equivalent. This evidence would be useful for another condition (The Scrum team cannot judge delivery capacity because it compares different story-point definitions from unrelated teams.) and its different action (Track velocity within the same stable team and estimation approach across iterations.). At Sandstone Publishing, it does not demonstrate the required project outcome: The estimate and assumptions can be independently recomputed from the three inputs.
The review identifies signals outside expected limits instead of reacting to normal noise. This evidence would be useful for another condition (Quality measurements fluctuate within expected common-cause limits but managers treat every single data point as an emergency.) and its different action (Use a control chart with appropriately derived control limits to distinguish exceptional variation.). At Sandstone Publishing, it does not demonstrate the required project outcome: The estimate and assumptions can be independently recomputed from the three inputs.
The chart reveals dominant categories and enables a focused improvement decision. This evidence would be useful for another condition (A release has many defect categories and the quality lead cannot tell which few causes produce most rework.) and its different action (Use a Pareto chart to rank defect categories by frequency or impact.). At Sandstone Publishing, it does not demonstrate the required project outcome: The estimate and assumptions can be independently recomputed from the three inputs.