Question 520
Sundown Freight is delivering an IT initiative involving transport systems and partner document access with several affected stakeholder groups. The team observes: A regulatory project launches without recognizing an external regulator as a stakeholder whose approval can block release. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The stakeholder plan identifies the regulator's approval requirement and lead time. This is the relevant acceptance evidence because it tests whether the corrective action (Assess external stakeholder influence and include applicable review gates in the initiation plan.) fixed the original concern (A regulatory project launches without recognizing an external regulator as a stakeholder whose approval can block release.) at Sundown Freight, rather than relying only on a task marked complete. The affected work concerns transport systems and partner document access.
Incorrect Answers
A reviewer retrieves controlled project records with traceable custody and approved permissions. This evidence would be useful for another condition (Employees store preliminary migration records in personal folders despite a requirement for auditable project documentation.) and its different action (Define a records management plan with retention location access and version rules.). At Sundown Freight, it does not demonstrate the required project outcome: The stakeholder plan identifies the regulator's approval requirement and lead time.
A sample contractor account receives only the documented access after approval. This evidence would be useful for another condition (New contractors need system access but permissions are granted ad hoc before requirements and approvers are identified.) and its different action (Define access needs and approval responsibilities during initiation before provisioning.). At Sundown Freight, it does not demonstrate the required project outcome: The stakeholder plan identifies the regulator's approval requirement and lead time.
The stakeholder register includes relevant business privacy and operations owners. This evidence would be useful for another condition (An integration project assigns technical work before identifying privacy representatives and affected operational users.) and its different action (Identify and analyze stakeholders for influence interest impact and engagement.). At Sundown Freight, it does not demonstrate the required project outcome: The stakeholder plan identifies the regulator's approval requirement and lead time.