Question 500
At Westlake Retail, the delivery assessment finds: The project sponsor requests an implementation design while the team has not yet reviewed constraints from prior feasibility work. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The initiation decision references verified requirements and documented design tradeoffs. This is the relevant acceptance evidence because it tests whether the corrective action (Review existing artifacts architecture assumptions and constraints before choosing solution design.) fixed the original concern (The project sponsor requests an implementation design while the team has not yet reviewed constraints from prior feasibility work.) at Westlake Retail, rather than relying only on a task marked complete. The affected work concerns online commerce and inventory workflows.
Incorrect Answers
A later milestone review evaluates the pilot against objective agreed thresholds. This evidence would be useful for another condition (Project participants disagree about whether a pilot is successful because its completion criteria were never defined.) and its different action (Document measurable objectives and project success criteria in the charter.). At Westlake Retail, it does not demonstrate the required project outcome: The initiation decision references verified requirements and documented design tradeoffs.
The signed charter authorizes the PM and defines the initiation boundaries. This evidence would be useful for another condition (The PM schedules implementation before a sponsor has formally authorized the intended outcome or named the project manager.) and its different action (Create and approve a project charter with purpose high-level scope sponsor and authority.). At Westlake Retail, it does not demonstrate the required project outcome: The initiation decision references verified requirements and documented design tradeoffs.
The approval record shows technical input and authorization by the intended business owner. This evidence would be useful for another condition (The initiation team assigns a technical architect to approve every business acceptance decision without consulting the process owner.) and its different action (Separate technical design responsibility from business acceptance accountability in the RACI.). At Westlake Retail, it does not demonstrate the required project outcome: The initiation decision references verified requirements and documented design tradeoffs.