Question 360
At Summit Rail Authority, the delivery assessment finds: An engineer is overloaded and team conflict worsens while the PM assumes the group is fully performing without intervention. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
Team feedback and task throughput show improved collaboration and a manageable workload. This is the relevant acceptance evidence because it tests whether the corrective action (Assess team development and workload constraints and facilitate constructive norms and conflict resolution.) fixed the original concern (An engineer is overloaded and team conflict worsens while the PM assumes the group is fully performing without intervention.) at Summit Rail Authority, rather than relying only on a task marked complete. The affected work concerns ticketing and customer-service applications.
Incorrect Answers
The resource plan shows agreed project capacity without ignoring functional obligations. This evidence would be useful for another condition (A cross-functional matrix project assigns all engineers full time although functional managers still own their operational workloads.) and its different action (Negotiate resource commitments with functional managers and document allocation in the matrix structure.). At Summit Rail Authority, it does not demonstrate the required project outcome: Team feedback and task throughput show improved collaboration and a manageable workload.
The resourcing plan fills the security capability gap and assigned tasks pass technical review. This evidence would be useful for another condition (A project lacks cloud security expertise but the manager adds equipment rather than addressing the skills deficit.) and its different action (Perform a skills gap analysis and obtain training or qualified specialist support.). At Summit Rail Authority, it does not demonstrate the required project outcome: Team feedback and task throughput show improved collaboration and a manageable workload.
The task review identifies one accountable owner and clear responsible participants for each key deliverable. This evidence would be useful for another condition (Two teams assume the same person is accountable for every task and conflicting approvals halt delivery.) and its different action (Define resource responsibilities and decision authority in a project responsibility assignment matrix.). At Summit Rail Authority, it does not demonstrate the required project outcome: Team feedback and task throughput show improved collaboration and a manageable workload.