Question 350
For Linden Manufacturing, the implementation team reports the following delivery problem: Two teams assume the same person is accountable for every task and conflicting approvals halt delivery. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The task review identifies one accountable owner and clear responsible participants for each key deliverable. This is the relevant acceptance evidence because it tests whether the corrective action (Define resource responsibilities and decision authority in a project responsibility assignment matrix.) fixed the original concern (Two teams assume the same person is accountable for every task and conflicting approvals halt delivery.) at Linden Manufacturing, rather than relying only on a task marked complete. The affected work concerns plant operations and product design information.
Incorrect Answers
A named replacement can execute the critical architecture checklist without the departing specialist. This evidence would be useful for another condition (A project's only database architect plans to leave before final cutover but succession and knowledge transfer are not scheduled.) and its different action (Plan successor coverage and documented knowledge transfer before the resource exits.). At Linden Manufacturing, it does not demonstrate the required project outcome: The task review identifies one accountable owner and clear responsible participants for each key deliverable.
The resourcing plan fills the security capability gap and assigned tasks pass technical review. This evidence would be useful for another condition (A project lacks cloud security expertise but the manager adds equipment rather than addressing the skills deficit.) and its different action (Perform a skills gap analysis and obtain training or qualified specialist support.). At Linden Manufacturing, it does not demonstrate the required project outcome: The task review identifies one accountable owner and clear responsible participants for each key deliverable.
The resource plan shows agreed project capacity without ignoring functional obligations. This evidence would be useful for another condition (A cross-functional matrix project assigns all engineers full time although functional managers still own their operational workloads.) and its different action (Negotiate resource commitments with functional managers and document allocation in the matrix structure.). At Linden Manufacturing, it does not demonstrate the required project outcome: The task review identifies one accountable owner and clear responsible participants for each key deliverable.