Question 270
A project governance review at Summit Rail Authority identifies this problem during a requirements discovery workshop: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?
Explanation
Correct Answer
The performance report identifies schedule variance and links corrective actions to the forecast. This is the relevant acceptance evidence because it tests whether the corrective action (Compare earned progress with the approved schedule baseline using a suitable performance measure.) fixed the original concern (A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule.) at Summit Rail Authority, rather than relying only on a task marked complete. The affected work concerns ticketing and customer-service applications.
Incorrect Answers
The test results show both the repaired defect and previously working related features still pass. This evidence would be useful for another condition (After a code fix, developers test only the changed method while an unrelated feature breaks in the build.) and its different action (Run regression testing on affected end-to-end functionality after the fix.). At Summit Rail Authority, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.
Authorized business users sign off on scenarios that reflect expected operational workflows. This evidence would be useful for another condition (A QA team runs unit tests and declares the product accepted although end users have never checked business workflows.) and its different action (Schedule user acceptance testing against approved business requirements in addition to technical tests.). At Summit Rail Authority, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.
The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs. This evidence would be useful for another condition (A delivery is deemed high quality only because it met the budget although serious defects remain unresolved.) and its different action (Assess quality outcomes and acceptance defects separately from cost and schedule performance.). At Summit Rail Authority, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.