McAfee-Secured Website

Exam Bundle

Exam Code: PK0-005

Exam Name CompTIA Project+

Certification Provider: CompTIA

Corresponding Certification: CompTIA Project+

CompTIA PK0-005 Bundle $44.99

100% CompTIA PK0-005 Guaranteed Success With Testking Training Materials

Get Real PK0-005 Exam Questions & Expert Verified Answers as Experienced on the Real Exam!

  • Questions & Answers

    PK0-005 Questions & Answers

    628 Questions & Answers

    The ultimate exam preparation tool, Questions & Answers mirrors the actual PK0-005 exam while allowing you to hone and measure every aspect of your test-taking ability.

  • PK0-005 Video Course

    PK0-005 Video Course

    159 Video Lectures

    PK0-005 Video Course is developed by CompTIA Professionals to help you pass the PK0-005 exam.

    Description

    This course will improve your knowledge and skills required to pass CompTIA Project+ exam.
  • Study Guide

    PK0-005 Study Guide

    682 PDF Pages

    Developed by industry experts, this 682-page guide spells out in painstaking detail all of the information you need to ace PK0-005 exam.

CompTIA Project+ (PK0-005) Practice Tests

Satisfaction Guaranteed

Money Back Guarantee

Testking provides hassle-free money back guarantee with our products. That is because we have 100% trust in the abilities of our professional and experience product team, and our record is a proof of that.

99.6% PASS RATE
Total Cost: $194.97
Bundle Price: $149.98

Purchase Individually

  • Questions & Answers

    Questions & Answers

    628 Questions

    $124.99
  • PK0-005 Video Course

    Video Course

    159 Video Lectures

    $39.99
  • Study Guide

    Study Guide

    682 PDF Pages

    $29.99

CompTIA PK0-005 Practice Test 27

Question 260

During a product deployment planning session at Linden Manufacturing, the project coordinator identifies an issue: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. Authorized business users sign off on scenarios that reflect expected operational workflows.
  2. The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.
  3. A later release checklist includes and verifies the specific process improvement.
  4. The performance report identifies schedule variance and links corrective actions to the forecast.

Explanation

Correct Answer

B:

The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs. This is the relevant acceptance evidence because it tests whether the corrective action (Assess quality outcomes and acceptance defects separately from cost and schedule performance.) fixed the original concern (A delivery is deemed high quality only because it met the budget although serious defects remain unresolved.) at Linden Manufacturing, rather than relying only on a task marked complete. The affected work concerns plant operations and product design information.

Incorrect Answers

A:

Authorized business users sign off on scenarios that reflect expected operational workflows. This evidence would be useful for another condition (A QA team runs unit tests and declares the product accepted although end users have never checked business workflows.) and its different action (Schedule user acceptance testing against approved business requirements in addition to technical tests.). At Linden Manufacturing, it does not demonstrate the required project outcome: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

C:

A later release checklist includes and verifies the specific process improvement. This evidence would be useful for another condition (Team members repeat a known production handoff error after every release because no lessons learned are recorded.) and its different action (Hold a structured retrospective and assign follow-up improvement actions to owners.). At Linden Manufacturing, it does not demonstrate the required project outcome: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

D:

The performance report identifies schedule variance and links corrective actions to the forecast. This evidence would be useful for another condition (A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule.) and its different action (Compare earned progress with the approved schedule baseline using a suitable performance measure.). At Linden Manufacturing, it does not demonstrate the required project outcome: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

Question 261

A project governance review at Cobalt Aerospace identifies this problem during a vendor selection exercise: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. Which project management action BEST addresses the particular issue?

  1. Assess quality outcomes and acceptance defects separately from cost and schedule performance.
  2. Compare earned progress with the approved schedule baseline using a suitable performance measure.
  3. Schedule user acceptance testing against approved business requirements in addition to technical tests.
  4. Hold a structured retrospective and assign follow-up improvement actions to owners.

Explanation

Correct Answer

A:

Assess quality outcomes and acceptance defects separately from cost and schedule performance. This directly addresses the reported management gap: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. For Cobalt Aerospace and its engineering programs and secure collaboration, a useful verification outcome is: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

Incorrect Answers

B:

Compare earned progress with the approved schedule baseline using a suitable performance measure. This choice addresses another specific project condition: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. The actual issue at Cobalt Aerospace is: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. That other intervention does not itself establish the required result: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

C:

Schedule user acceptance testing against approved business requirements in addition to technical tests. This choice addresses another specific project condition: A QA team runs unit tests and declares the product accepted although end users have never checked business workflows. The actual issue at Cobalt Aerospace is: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. That other intervention does not itself establish the required result: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

D:

Hold a structured retrospective and assign follow-up improvement actions to owners. This choice addresses another specific project condition: Team members repeat a known production handoff error after every release because no lessons learned are recorded. The actual issue at Cobalt Aerospace is: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. That other intervention does not itself establish the required result: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

Question 262

A project governance review at Cobalt Aerospace identifies this problem during a vendor selection exercise: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The performance report identifies schedule variance and links corrective actions to the forecast.
  2. A later release checklist includes and verifies the specific process improvement.
  3. The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.
  4. Authorized business users sign off on scenarios that reflect expected operational workflows.

Explanation

Correct Answer

C:

The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs. This is the relevant acceptance evidence because it tests whether the corrective action (Assess quality outcomes and acceptance defects separately from cost and schedule performance.) fixed the original concern (A delivery is deemed high quality only because it met the budget although serious defects remain unresolved.) at Cobalt Aerospace, rather than relying only on a task marked complete. The affected work concerns engineering programs and secure collaboration.

Incorrect Answers

A:

The performance report identifies schedule variance and links corrective actions to the forecast. This evidence would be useful for another condition (A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule.) and its different action (Compare earned progress with the approved schedule baseline using a suitable performance measure.). At Cobalt Aerospace, it does not demonstrate the required project outcome: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

B:

A later release checklist includes and verifies the specific process improvement. This evidence would be useful for another condition (Team members repeat a known production handoff error after every release because no lessons learned are recorded.) and its different action (Hold a structured retrospective and assign follow-up improvement actions to owners.). At Cobalt Aerospace, it does not demonstrate the required project outcome: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

D:

Authorized business users sign off on scenarios that reflect expected operational workflows. This evidence would be useful for another condition (A QA team runs unit tests and declares the product accepted although end users have never checked business workflows.) and its different action (Schedule user acceptance testing against approved business requirements in addition to technical tests.). At Cobalt Aerospace, it does not demonstrate the required project outcome: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

Question 263

A project affecting warehouse scheduling and shipping records at Stonehaven Logistics encounters a management concern: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. Which project management action BEST addresses the particular issue?

  1. Schedule user acceptance testing against approved business requirements in addition to technical tests.
  2. Assess quality outcomes and acceptance defects separately from cost and schedule performance.
  3. Compare earned progress with the approved schedule baseline using a suitable performance measure.
  4. Hold a structured retrospective and assign follow-up improvement actions to owners.

Explanation

Correct Answer

B:

Assess quality outcomes and acceptance defects separately from cost and schedule performance. This directly addresses the reported management gap: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. For Stonehaven Logistics and its warehouse scheduling and shipping records, a useful verification outcome is: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

Incorrect Answers

A:

Schedule user acceptance testing against approved business requirements in addition to technical tests. This choice addresses another specific project condition: A QA team runs unit tests and declares the product accepted although end users have never checked business workflows. The actual issue at Stonehaven Logistics is: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. That other intervention does not itself establish the required result: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

C:

Compare earned progress with the approved schedule baseline using a suitable performance measure. This choice addresses another specific project condition: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. The actual issue at Stonehaven Logistics is: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. That other intervention does not itself establish the required result: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

D:

Hold a structured retrospective and assign follow-up improvement actions to owners. This choice addresses another specific project condition: Team members repeat a known production handoff error after every release because no lessons learned are recorded. The actual issue at Stonehaven Logistics is: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. That other intervention does not itself establish the required result: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

Question 264

A project affecting warehouse scheduling and shipping records at Stonehaven Logistics encounters a management concern: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.
  2. The performance report identifies schedule variance and links corrective actions to the forecast.
  3. Authorized business users sign off on scenarios that reflect expected operational workflows.
  4. A later release checklist includes and verifies the specific process improvement.

Explanation

Correct Answer

A:

The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs. This is the relevant acceptance evidence because it tests whether the corrective action (Assess quality outcomes and acceptance defects separately from cost and schedule performance.) fixed the original concern (A delivery is deemed high quality only because it met the budget although serious defects remain unresolved.) at Stonehaven Logistics, rather than relying only on a task marked complete. The affected work concerns warehouse scheduling and shipping records.

Incorrect Answers

B:

The performance report identifies schedule variance and links corrective actions to the forecast. This evidence would be useful for another condition (A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule.) and its different action (Compare earned progress with the approved schedule baseline using a suitable performance measure.). At Stonehaven Logistics, it does not demonstrate the required project outcome: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

C:

Authorized business users sign off on scenarios that reflect expected operational workflows. This evidence would be useful for another condition (A QA team runs unit tests and declares the product accepted although end users have never checked business workflows.) and its different action (Schedule user acceptance testing against approved business requirements in addition to technical tests.). At Stonehaven Logistics, it does not demonstrate the required project outcome: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

D:

A later release checklist includes and verifies the specific process improvement. This evidence would be useful for another condition (Team members repeat a known production handoff error after every release because no lessons learned are recorded.) and its different action (Hold a structured retrospective and assign follow-up improvement actions to owners.). At Stonehaven Logistics, it does not demonstrate the required project outcome: The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

Question 265

A project affecting care team access and regulated data handling at Evermere Health encounters a management concern: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. Which project management action BEST addresses the particular issue?

  1. Run regression testing on affected end-to-end functionality after the fix.
  2. Compare earned progress with the approved schedule baseline using a suitable performance measure.
  3. Schedule user acceptance testing against approved business requirements in addition to technical tests.
  4. Assess quality outcomes and acceptance defects separately from cost and schedule performance.

Explanation

Correct Answer

B:

Compare earned progress with the approved schedule baseline using a suitable performance measure. This directly addresses the reported management gap: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. For Evermere Health and its care team access and regulated data handling, a useful verification outcome is: The performance report identifies schedule variance and links corrective actions to the forecast.

Incorrect Answers

A:

Run regression testing on affected end-to-end functionality after the fix. This choice addresses another specific project condition: After a code fix, developers test only the changed method while an unrelated feature breaks in the build. The actual issue at Evermere Health is: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. That other intervention does not itself establish the required result: The performance report identifies schedule variance and links corrective actions to the forecast.

C:

Schedule user acceptance testing against approved business requirements in addition to technical tests. This choice addresses another specific project condition: A QA team runs unit tests and declares the product accepted although end users have never checked business workflows. The actual issue at Evermere Health is: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. That other intervention does not itself establish the required result: The performance report identifies schedule variance and links corrective actions to the forecast.

D:

Assess quality outcomes and acceptance defects separately from cost and schedule performance. This choice addresses another specific project condition: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. The actual issue at Evermere Health is: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. That other intervention does not itself establish the required result: The performance report identifies schedule variance and links corrective actions to the forecast.

Question 266

A project affecting care team access and regulated data handling at Evermere Health encounters a management concern: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The performance report identifies schedule variance and links corrective actions to the forecast.
  2. The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.
  3. The test results show both the repaired defect and previously working related features still pass.
  4. Authorized business users sign off on scenarios that reflect expected operational workflows.

Explanation

Correct Answer

A:

The performance report identifies schedule variance and links corrective actions to the forecast. This is the relevant acceptance evidence because it tests whether the corrective action (Compare earned progress with the approved schedule baseline using a suitable performance measure.) fixed the original concern (A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule.) at Evermere Health, rather than relying only on a task marked complete. The affected work concerns care team access and regulated data handling.

Incorrect Answers

B:

The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs. This evidence would be useful for another condition (A delivery is deemed high quality only because it met the budget although serious defects remain unresolved.) and its different action (Assess quality outcomes and acceptance defects separately from cost and schedule performance.). At Evermere Health, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.

C:

The test results show both the repaired defect and previously working related features still pass. This evidence would be useful for another condition (After a code fix, developers test only the changed method while an unrelated feature breaks in the build.) and its different action (Run regression testing on affected end-to-end functionality after the fix.). At Evermere Health, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.

D:

Authorized business users sign off on scenarios that reflect expected operational workflows. This evidence would be useful for another condition (A QA team runs unit tests and declares the product accepted although end users have never checked business workflows.) and its different action (Schedule user acceptance testing against approved business requirements in addition to technical tests.). At Evermere Health, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.

Question 267

During an IT infrastructure modernization at Riverbend Automotive, the program coordinator identifies an issue: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. Which project management action BEST addresses the particular issue?

  1. Compare earned progress with the approved schedule baseline using a suitable performance measure.
  2. Assess quality outcomes and acceptance defects separately from cost and schedule performance.
  3. Run regression testing on affected end-to-end functionality after the fix.
  4. Schedule user acceptance testing against approved business requirements in addition to technical tests.

Explanation

Correct Answer

A:

Compare earned progress with the approved schedule baseline using a suitable performance measure. This directly addresses the reported management gap: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. For Riverbend Automotive and its vehicle engineering and customer services, a useful verification outcome is: The performance report identifies schedule variance and links corrective actions to the forecast.

Incorrect Answers

B:

Assess quality outcomes and acceptance defects separately from cost and schedule performance. This choice addresses another specific project condition: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. The actual issue at Riverbend Automotive is: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. That other intervention does not itself establish the required result: The performance report identifies schedule variance and links corrective actions to the forecast.

C:

Run regression testing on affected end-to-end functionality after the fix. This choice addresses another specific project condition: After a code fix, developers test only the changed method while an unrelated feature breaks in the build. The actual issue at Riverbend Automotive is: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. That other intervention does not itself establish the required result: The performance report identifies schedule variance and links corrective actions to the forecast.

D:

Schedule user acceptance testing against approved business requirements in addition to technical tests. This choice addresses another specific project condition: A QA team runs unit tests and declares the product accepted although end users have never checked business workflows. The actual issue at Riverbend Automotive is: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. That other intervention does not itself establish the required result: The performance report identifies schedule variance and links corrective actions to the forecast.

Question 268

During an IT infrastructure modernization at Riverbend Automotive, the program coordinator identifies an issue: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.
  2. Authorized business users sign off on scenarios that reflect expected operational workflows.
  3. The test results show both the repaired defect and previously working related features still pass.
  4. The performance report identifies schedule variance and links corrective actions to the forecast.

Explanation

Correct Answer

D:

The performance report identifies schedule variance and links corrective actions to the forecast. This is the relevant acceptance evidence because it tests whether the corrective action (Compare earned progress with the approved schedule baseline using a suitable performance measure.) fixed the original concern (A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule.) at Riverbend Automotive, rather than relying only on a task marked complete. The affected work concerns vehicle engineering and customer services.

Incorrect Answers

A:

The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs. This evidence would be useful for another condition (A delivery is deemed high quality only because it met the budget although serious defects remain unresolved.) and its different action (Assess quality outcomes and acceptance defects separately from cost and schedule performance.). At Riverbend Automotive, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.

B:

Authorized business users sign off on scenarios that reflect expected operational workflows. This evidence would be useful for another condition (A QA team runs unit tests and declares the product accepted although end users have never checked business workflows.) and its different action (Schedule user acceptance testing against approved business requirements in addition to technical tests.). At Riverbend Automotive, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.

C:

The test results show both the repaired defect and previously working related features still pass. This evidence would be useful for another condition (After a code fix, developers test only the changed method while an unrelated feature breaks in the build.) and its different action (Run regression testing on affected end-to-end functionality after the fix.). At Riverbend Automotive, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.

Question 269

A project governance review at Summit Rail Authority identifies this problem during a requirements discovery workshop: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. Which project management action BEST addresses the particular issue?

  1. Assess quality outcomes and acceptance defects separately from cost and schedule performance.
  2. Compare earned progress with the approved schedule baseline using a suitable performance measure.
  3. Run regression testing on affected end-to-end functionality after the fix.
  4. Schedule user acceptance testing against approved business requirements in addition to technical tests.

Explanation

Correct Answer

B:

Compare earned progress with the approved schedule baseline using a suitable performance measure. This directly addresses the reported management gap: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. For Summit Rail Authority and its ticketing and customer-service applications, a useful verification outcome is: The performance report identifies schedule variance and links corrective actions to the forecast.

Incorrect Answers

A:

Assess quality outcomes and acceptance defects separately from cost and schedule performance. This choice addresses another specific project condition: A delivery is deemed high quality only because it met the budget although serious defects remain unresolved. The actual issue at Summit Rail Authority is: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. That other intervention does not itself establish the required result: The performance report identifies schedule variance and links corrective actions to the forecast.

C:

Run regression testing on affected end-to-end functionality after the fix. This choice addresses another specific project condition: After a code fix, developers test only the changed method while an unrelated feature breaks in the build. The actual issue at Summit Rail Authority is: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. That other intervention does not itself establish the required result: The performance report identifies schedule variance and links corrective actions to the forecast.

D:

Schedule user acceptance testing against approved business requirements in addition to technical tests. This choice addresses another specific project condition: A QA team runs unit tests and declares the product accepted although end users have never checked business workflows. The actual issue at Summit Rail Authority is: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. That other intervention does not itself establish the required result: The performance report identifies schedule variance and links corrective actions to the forecast.

Question 270

A project governance review at Summit Rail Authority identifies this problem during a requirements discovery workshop: A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule. The team reports that it has taken corrective action. Which observation BEST verifies that the original issue is resolved?

  1. The performance report identifies schedule variance and links corrective actions to the forecast.
  2. The test results show both the repaired defect and previously working related features still pass.
  3. Authorized business users sign off on scenarios that reflect expected operational workflows.
  4. The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs.

Explanation

Correct Answer

A:

The performance report identifies schedule variance and links corrective actions to the forecast. This is the relevant acceptance evidence because it tests whether the corrective action (Compare earned progress with the approved schedule baseline using a suitable performance measure.) fixed the original concern (A project tracks calendar milestones but has no way to show whether completed value is behind the planned schedule.) at Summit Rail Authority, rather than relying only on a task marked complete. The affected work concerns ticketing and customer-service applications.

Incorrect Answers

B:

The test results show both the repaired defect and previously working related features still pass. This evidence would be useful for another condition (After a code fix, developers test only the changed method while an unrelated feature breaks in the build.) and its different action (Run regression testing on affected end-to-end functionality after the fix.). At Summit Rail Authority, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.

C:

Authorized business users sign off on scenarios that reflect expected operational workflows. This evidence would be useful for another condition (A QA team runs unit tests and declares the product accepted although end users have never checked business workflows.) and its different action (Schedule user acceptance testing against approved business requirements in addition to technical tests.). At Summit Rail Authority, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.

D:

The closeout decision records defect severity and acceptance status alongside cost and schedule KPIs. This evidence would be useful for another condition (A delivery is deemed high quality only because it met the budget although serious defects remain unresolved.) and its different action (Assess quality outcomes and acceptance defects separately from cost and schedule performance.). At Summit Rail Authority, it does not demonstrate the required project outcome: The performance report identifies schedule variance and links corrective actions to the forecast.